AI summaryEpsom and Ewell Borough Council's Strategy and Resources Committee unanimously noted an urgent officer decision to approve a two year fixed gas contract at a 6.2 p/kwh unit rate, with final agreement delegated. [D][P2][P5][P9][P29]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedThe urgent decision was to approve option 3. [D][P9][P28]
Money6.2 p/kwh unit price [P29]For the approved 24 month contract. [P9][P29]
What happens nextFinal gas contract agreement [P9]Head of Property and Regeneration to finalise the contract. [P9]
Who it affectsCouncil gas metered sites [P11]The council's listed gas metered sites. [P11]

What was decided

The committee unanimously noted the urgent decision and the reasons for it.

The urgent decision was to approve option 3, a fixed 24 month gas contract at 6.2 p/kwh. Report P9, P28, P29

Authority was delegated to the Head of Property and Regeneration to finalise and agree the contract. Report P9

Why

The existing gas contract expired on 30/09/2026 and renewal was required. Report P10, P20

Option 3 had the lowest unit rate of all the options and gave price certainty during significant market volatility. Report P20, P33, P39

Gas prices only stood for one day, so the decision could not wait until the next scheduled committee. Report P7

What happens next

The Head of Property and Regeneration will finalise and agree the gas contract. Report P9

The money

  • 6.2 p/kwh unit price Selected fixed unit rate for the 24 month contract Report P29
  • £165,706 per annum Current annual gas spending Report P13
  • £103,274.63 per annum Estimated annual spend under the September 2023 contract Report P12
  • 7.6 p/kwh unit price Option 2 fixed rate for 12 months Report P27
  • over 10.5p/kwh Out of contract rate under option 4 Report P31
  • around 9p a unit Gas unit price discussed for the decision Report P18
  • 4.68p Previously locked in unit price Report P18

Options considered

  • Rejected: Option 1: Short term fixed contract to April 2027, then a flexible framework contract. Option 3 was identified as offering the lowest unit rate and price certainty. Report P26, P28, P33, P39
  • Rejected: Option 2: Fixed contract for 12 months at 7.6 p/kwh unit price. Option 3 was identified as offering the lowest unit rate and price certainty. Report P27, P28, P33, P39
  • Chosen: Option 3: Fixed contract for 24 months at a rate of 6.2 p/kwh unit price. It had the lowest unit rate of all options and ensured price certainty. Report P28, P29, P33, P39
  • Rejected: Option 4: Do nothing. The council would have faced an out of contract rate of over 10.5p/kwh. Report P30, P31, P33

Implications

  • Financial: Current gas spending is £165,706 per annum. The September 2023 contract had estimated spend of £103,274.63 per annum. Report P12, P13
  • Financial: Option 3 was identified as offering the cheapest unit rate. Doing nothing would have exposed the council to an out of contract rate of over 10.5p/kwh. Report P31, P33
  • Financial: The annual consumption basis under the September 2023 contract was 2,125,536 kwh. Report P12
  • Legal: Legal services were consulted and provided no comments. The decision falls within General Consent, so no further approval from the Shadow Authority was required. It was in line with the council's constitution and contractual and financial procedures. Report P21, P22, P34, P38
  • Equalities: No equalities implications were identified. Report P35
  • Climate: No climate change implications were identified. Report P35
  • Risk: Financial risks were considered. Finance said option 3 offered the lowest financial risk and some certainty during significant volatility. The report linked volatile prices to the war in Iran and closure of the strait of Hormuz. Report P17, P20, P36
  • Other: Gas bills include wholesale cost, transportation, losses, levies, metering, supplier margin and VAT. Raw energy cost is generally only 35% of the actual bill. Report P14, P15, P16

Who and where

  • Epsom and Ewell Borough Council Report P2, P9
  • Council gas metered sites: Town Hall, Bourne Hall, Community & Wellbeing Centre, Playhouse(2no), Auriol park, King Georges Field, Horton Country park, Ewell Court House (2no), Nonsuch (3no) Report P11
  • SEFE, the incumbent gas supplier Report P12, P26

Timeline

  • September 2023: The council secured a three year gas contract with SEFE, with estimated spend of £103,274.63 per annum. Report P12
  • 30/09/2026: The gas contract expired and required renewal. Report P10, P20, P33
  • 6 October 2026: The officer requested authorisation for the urgent decision. Report P4
  • 6/10/26: The decision was needed by this date. The Chair or Vice Chair supported the urgent decision. Report P8, P40, P42
  • 2026-11-10: The Strategy and Resources Committee noted the urgent decision and its reasons.

Plain English for the jargon

  • General Consent: The approval category under which no further Shadow Authority approval was required. [P34]
  • Shadow Authority: The body from which no further approval was required for this decision. [P34]
  • raw energy cost: The wholesale component of the bill, generally only 35% of the actual bill. [P15][P16]
  • levies: Environmental and social obligation costs included in the energy bill. [P15]
  • unbilled volumes: Losses included in the energy bill. [P15]
  • out of contract rate: The higher rate that would apply if the council did nothing, stated as over 10.5p/kwh. [P31]
  • kwh: The unit used for annual gas consumption and unit prices. [P12][P29]
  • fixed contract: A gas supply contract with a fixed unit price for its stated term. [P26][P27][P29]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item7

Resolved

Following consideration, it was unanimously resolved to: (1) Note the urgent decision taken and the reasons for that decision.
Word for word from the decision Epsom and Ewell published for this meeting. Source: democracy.epsom-ewell.gov.uk

Follow this further

Built from Epsom and Ewell's papers

What the report saysPro

Report to Strategy and Resources Committee

REFERENCE: DEC 164

EPSOM AND EWELL BOROUGH COUNCIL

DECISIONS/ACTIONS TAKEN IN CONSULTATION WITH COMMITTEE CHAIR

Officer requesting authorisation: Tony Foxwell Date of request: 6 October 2026

Committee concerned: Strategy & Resources committee

Subject: Gas Contract Renewal

Reason why this decision/action cannot wait until the next scheduled committee: Prices only stand for one day.

When the decision/action is needed by: 6/10/26

Proposed action/decision: 1. To approve option 3, the two-year fixed term contract for the provision of gas. 2. To delegate authority to the Head of Property and Regeneration to finalise and agree the contract.

Background Information EEBC gas contract is due to expire on 30/09/2026 and requires renewal.

The gas metered sites are:  Town Hall  Bourne Hall  Community & Wellbeing Centre  Playhouse(2no)  Auriol park  King Georges Field  Horton Country park  Ewell Court House (2no)  Nonsuch (3no)

EEBC secured a 3-year contract in September 2023 with a supplier called SEFE based on an annual consumption of 2,125,536 kwh use at an estimated spend of £103,274.63 per annum.

We currently spend £165,706 per annum.

Energy costs are made up of several factors which contribute to the final energy cost, not just the unit price.

 the raw energy cost (or wholesale cost)  the cost of transportation (or transmission & distribution)  losses (or unbilled volumes)  levies (or environmental and social obligation costs)  metering costs (or supplier operating costs)  the supplier’s margin (or profit)  VAT

The raw energy cost is generally only 35% of the actual bill.

These are still very volatile times with the war in Iran, and the closure of the strait of Hormuz has prevented gas tankers getting through, this in turn has increased gas and oil prices throughout the world.

Discussions have taken place with our energy consultant Inspired Energy regarding costs and proposals over the past month. The market is not in a good place with gas unit prices around 9p a unit, when we were previously locked in at 4.68p. As prices are still extremely high it would not be best value to lock into a fixed contract for a long period of time.

Finance consulted: Yes

Finance comments: As the current gas contract expired on 30 September 2026 a decision is required to avoid being charged at higher unit rates. In the current circumstances option 3 offers lowest financial risk and provides some certainty during a time of significant volatility in the current market.

Legal consulted: Yes

Legal comments: None

Considered the following (Para 3.2 Appendix 2 of the Council’s Constitution).

Consultation views: N/A

Range of options considered: 4 options considered below.

There are various options to consider, all fixed option prices have been given by the current incumbent SEFE. Option 1 A short-term fixed contract to take us up to April 2027 and then on to a flexible framework contract.

Option 2 A fixed contract for 12 months at 7.6 p/kwh unit price

Option 3 (Recommended)

A fixed contract for 24 months at a rate of 6.2 p/kwh unit price.

Option 4 - Do Nothing Option

If we do nothing we will go on a high out of contract rate of over 10.5p/kwh.

Staffing, financial, and legal implications:

As the current gas contract expired on 30 September 2026 a decision is required to avoid the Council being on significantly higher out of contract rates. Option 3 offers the cheapest unit rates than all the other options and ensures certainty.

In relation to s24, this decision falls within General Consent and no further approval is required from the Shadow Authority.

Policy framework, equalities, climate change or wellbeing implications: N/A

Risks: Financial risks considered.

Other guidance: N/A

Constitution, contract and financial procedures and regulations: This decision is in line with the council’s constitution, contractual and financial procedures.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Urgent Decision Appendix 1Decisions 185 KB DownloadRead as text
PDF
Urgent DecisionDecisions 228 KB Download

At this meeting

Whole meeting

Who was there

0 of 15 attended
ND
Councillor Neil Dallen MBEChair, expected
HD
Councillor Hannah DaltonVice-Chair, expected
JB
Councillor John BeckettCommittee Member, expected
AC
Councillor Alex ColeyCommittee Member, expected
KC
Councillor Kate ChinnCommittee Member, expected
SG
Councillor Shanice GoldmanCommittee Member, expected
RL
Councillor Robert LeachCommittee Member, expected
HR
Councillor Humphrey ReynoldsCommittee Member, expected
ON
Oliver NelsonOfficer, expected
JK
Jackie KingOfficer, expected
AB
Andrew BircherOfficer, expected
CC
Cagdas CanbolatOfficer, expected

All 15 on the meeting page

On this subject at Epsom and Ewell

Search all
  1. Urgent DecisionThis decision
  2. Urgent DecisionsNoted
  3. Use of Urgent Decisions Annual ReportAgreed
  4. Urgent DecisionsNoted
  5. Urgent DecisionsNoted
  6. Urgent DecisionsNoted

More from Epsom and Ewell Strategy and Resources Committee

All decisions
MeetingDecisionOutcome
10 Nov 2026 Exceptional CIL-Related Ex Gratia Payment PolicyFollowing consideration, the committee unanimously resolved tot was resolved: (1) Note the contents of the Government... Noted Open
10 Nov 2026 Response to consultationFollowing consideration, the committee unanimously resolved to: (1) Note the report Noted Open
10 Nov 2026 Conferring the Title of Honorary FreewomanFollowing consideration, the committee agreed with 7 votes for and 1 member not voting to: (1) recommend that the Cou... Agreed Open
10 Nov 2026 Update from the Town Twinning Working GroupFollowing consideration, the committee agreed with 6 votes for, 1 abstention and 1 member not voting to: (1) Note the... Agreed Open
10 Nov 2026 Request for an item of business under CPR 3 of Appendix 5 of the Constitution: To update the committee on progress of the work being undertaken on EEBC Strategic Priority: Hook Road ArenaFollowing consideration, the committee resolved with 4 votes for and 3 abstentions to: (1) Note that a report regardi... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies