General Fund Capital Monitoring 2023/24 and Revised Capital Programme for 2024/25 and Future Years

Agreed Executive 2 papers

Executive agreed this item on Tuesday 9 July 2024. Below is the council's own wording, with the papers it was decided on.

Item74

Resolved

Agreed: RECOMMENDED that Council approves:- (1) the overall financial position for the 2023/24 Annual Capital Programme; and (2) the amendments and further funding requests to the Council’s Annual Capital Programme for 2024/25. (3) £85,000 for the City Wall following tender returns, £185,000 to complete the RAMM re-roofing works and £88,120 as a contribution to a scheme to repair the roof at St Nicholas Priory. The additions would be funded by borrowing. Reason for As set out in the report and as amended at the meeting.
Word for word from the decision Exeter published for this meeting. Source: committees.exeter.gov.uk

Follow this further

Built from Exeter's papers

What the report saysPro

Report to Executive, 7 pages

APPENDIX 1

2023/24 CAPITAL MONITORING TO MARCH 2024

2023/24 Budget to 2023/24 be Carried Forward Programme 2023/24 Capital to 2024/25 and Variances 2023/24 Spend Beyond (Under)/Over Responsible Officer Scheme Programme

£ £ £

Transformation Annual Contribution to Strata 53,900 53,904 0 4 ECC Civic Centre HFX Door Access Replacement 14,940 14,937 0 (3) System Upgrade Cost 2012 Server replacement 15,720 12,239 3,481 0 GIS Cloud Migration 2,510 2,276 234 0 AV Equipment - Hybrid Meeting Rooms 48,800 0 48,800 0 IT Replacement Programme 75,000 88,589 0 13,589 Director Idox System for Planning 60,680 0 60,680 0 Financial Management 96,760 116,637 (19,877) 0 NCSC Zero Trust 53,910 0 53,910 0 PSTN Replacement 30,000 407 29,593 0 Microsoft Power Apps 35,930 0 35,930 0 Sharegate 5,750 0 5,750 0 TOTAL 493,900 288,989 218,501 13,590

Net Zero Exeter and City Management Parks Infrastructure 6,330 6,146 184 0 Parks Anti-Intrusion Measures 18,060 10,403 7,657 0 Ash Die Back Tree Replacement 50,000 53,786 (3,786) 0 Service Manager - Public & Green Space Northbrook Wild Arboretum 144,230 16,096 128,134 0 Play Areas 176,990 175,086 1,904 0 St Thomas Splashpad 41,480 41,475 0 (5) 2023/24 Budget to 2023/24 be Carried Forward Programme 2023/24 Capital to 2024/25 and Variances 2023/24 Spend Beyond (Under)/Over Responsible Officer Scheme Programme

£ £ £

Bowling Green Marshes Coastal Defence Scheme 3,500 2,131 1,369 0 Cricklepit Bridge 10,000 0 10,000 0 Trews Weir Refurb 30,000 20,490 9,510 0 District Street Lighting 50,000 0 50,000 0 Exeter Quay Cellars Cliff Face 181,640 262,763 (81,123) 0 Mallison Bridge 25,000 25,000 0 0 Engineering & Assets Manager Bonhay Rd/Andlaw House Footpath 3,250 5,200 (1,950) 0 Landfill Gas Extraction Systems 13,900 10,650 3,250 0 Mincinglake Valley Park Reed Beds & Pipe Inlet 2,260 1,848 412 0 Bromhams Farm Playing Fields 117,740 27,429 90,311 0 ECC Bridge Repair Programme 26,190 26,193 0 3 Countess Wear Retaining Wall Rebuild 24,600 18,606 5,994 0 Oxford Road Car Park Retaining Wall 1,500 1,502 0 2 Waste Infrastructure 40,000 39,663 337 0 Improved recycling containers 90,000 87,890 2,110 0 Service Manager - Recycling, Waste & Fleet Enhance the Materials Reclamations Facility 20,000 13,500 6,500 0 Fleet Lease costs 927,200 16,910 910,290 0 Disabled Facility Grants 1,502,120 1,454,293 47,827 0 Service Manager - Environmental Health & CCTV improvements 415,630 318,519 97,111 0 Community Safety DEFRA Air Quality Grant 49,000 36,000 13,000 0 Noise Monitoring Equipment 45,000 16,243 28,757 0 Exeter Canal Bank Repairs 25,000 0 25,000 0 Harbour Master Harbour Team Workboat 23,080 28,462 0 5,382 Energy Saving Projects 12,400 12,403 0 3 Service Manager - Net Zero & Business Riverside & RAMM Decarbonisation Projects 1,250,000 361,783 29,187 (859,030) Shared Prosperity Fund 64,320 64,323 0 3 Miscellaneous Capitalised Staff Costs 195,020 0 0 (195,020) TOTAL 5,585,440 3,154,793 1,381,984 (1,048,663)

City Development, Housing & Supporting People Director Next Steps/Rough Sleepers Accommodation Programme Property Acquisitions 517,930 517,959 0 29 TOTAL 517,930 517,959 0 29 2023/24 Budget to 2023/24 be Carried Forward Programme 2023/24 Capital to 2024/25 and Variances 2023/24 Spend Beyond (Under)/Over Responsible Officer Scheme Programme

£ £ £

Communications, Culture and Leisure Facilities Council Signage Improvement 79,090 69,241 9,849 0 Riverside Leisure Centre 50,480 21,485 28,995 0 Riverside Sports Hall Roof 15,130 15,134 0 4 Leisure Complex - Fit Out 100,000 12,578 87,422 0 Director Leisure Complex - Build Project 100,000 73,395 26,605 0 Bus Station Construction 282,370 74,663 207,707 0 Leisure Property enhancements 100,000 79,356 20,644 0 Leisure Equipment Replacement Programme 100,000 61,641 0 (38,359) TOTAL 827,070 407,493 381,222 (38,355)

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendices: Qtr 4 Capital MonitoringReport 7 pages DownloadRead as text
PDF
General Fund Capital Monitoring 2023/24 and Revised Capital Programme for 2024/25 and Future YearsReport 240 KB Copy on its way

At this meeting

Whole meeting

On this subject at Exeter

Search all
  1. General Fund Capital Monitoring 2023/24 and Revised Capital Programme for 2024/25 and Future YearsThis decision
  2. General Fund Estimates and Capital Programme 2026/27Agreed
  3. Overview of General Fund Revenue Budget 2023/24 - Quarter 4Agreed
  4. Overview of General Fund Revenue Budget 2023/24 – Quarter 3Agreed
  5. 2023/24 General Fund Capital Monitoring Statement – Quarter 3Agreed
  6. General Fund / HRA Estimates and Capital Programme 2024/25Agreed

More from Exeter Executive

All decisions
MeetingDecisionOutcome
17 Aug 2026 Neighbourhood Community Infrastructure Levy ConsultationAgreed: RESOLVED that Executive: (1) approve the continued use of Neighbourhood Community Infrastructure Levy (CIL) f... Agreed Open
17 Aug 2026 Review of Exeter Business Centre Ltd.AGREED: RESOLVED that Executive: (1) note the current position of Exeter Business Centre Ltd and the review of Exeter... Agreed Open
17 Aug 2026 Members’ Allowances and Expenses Paid 2025/26AGREED: RESOLVED that the Executive note the allowances paid to and expenses claimed by Members in 2025/26. Reason fo... Agreed Open
28 Apr 2026 Exeter City Centre Vision and Strategy 2026 – 2031 Public ConsultationAgreed: RESOLVED that: 1) the publication of the draft City Centre Strategy 2026 – 2031 be approved for public consul... Agreed Open
28 Apr 2026 Exeter Cultural Strategy 2026 – 2031 Public ConsultationAgreed: RESOLVED that: 1) the publication of the draft Cultural Strategy 2026 - 2031 be approved for public consultat... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies