RESOLVED that the Executive agrees: (a) to award a contract to Balfour Beatty in the sum of £229,971 for the timber replacement of the Salterns Promenade and the construction of a cycleway (with a rural surface) to the north of the sea wall; (b) to proceed with the construction of the cycleway prior to Hampshire County Council resolving the land issues; and (c) to increase the capital budget by £20,000 to a total of £233,000.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 10 February 2014 Portfolio: Leisure and Community Subject: Award of Contract - Salterns Promenade Repairs Report of: Director of Community Strategy/Policy: Leisure Strategy
Corporate Leisure for Health and for Fun Objective:
Purpose: This report presents the tenders received for repairs to the Salterns Promenade and for the possible construction of a cycleway to the north of the current sea wall.
Executive summary: At its meeting in November 2012, the Executive approved a project to repair a 700m stretch of the Salterns Promenade as a long term solution to the deterioration of the timber kerbing on the seaward edge of the promenade.
Separate to the project to repair the Promenade, Hampshire County Council (HCC) has been pursuing a project to construct a cycleway to the north of the existing sea wall to become part of the National Cycleway Network (NCN).
To minimise disruption to users of the promenade, the two authorities have worked in partnership to jointly procure and construct the two adjacent projects.
Tenders have been received and it is recommended that a contract be awarded to Balfour Beatty for the repairs to the Salterns Promenade in the sum of £199,881.
Insufficient funding is available for the cycleway and the Executive is asked to consider whether to proceed with this, and if so to agree the surface finish, the additional capital budget required and whether to proceed at risk due to the unresolved land issues. Recommendation: The Executive considers: (a) That a contract be awarded to Balfour Beatty in the sum of £229,971 for the timber replacement of the Salterns Promenade and the construction of a cycleway (with a rural surface) to the north of the sea wall. (b) That the Executive consider whether to proceed with the construction of the cycleway prior to Hampshire County Council resolving the land issues. (c) That the capital budget be increased by £20,000 to a total of £233,000.
Reason: To allow the repairs to the Salterns Promenade to be completed and remove the trip hazards currently present due to the deteriorating condition of the timber planking.
Cost of proposals: The repairs to the promenade can be funded from the existing capital budget.
Inclusion of the cycleway with a rural footpath can be accommodated within the currently approved budget with the addition of the £20,000 from SUSTRANS. However only £3,000 contingency would remain for any unforeseen works.
Appendix A: Tender Evaluation
Background papers: Report to the Executive for Decision dated 12 November 2012 –Salterns Promenade. Executive Briefing Paper Date: 10 February 2014
Subject: Award of Contract - Salterns Promenade Repairs
Briefing by: Director of Community
Portfolio: Leisure and Community
INTRODUCTION
1. At its meeting in November 2012, the Executive approved a project to repair a 700m stretch of the Salterns Promenade as a long term solution to the deterioration of the timber kerbing on the seaward edge of the promenade.
2. A capital budget of £213,000 has been allocated to this project to cover all works and fees.
3. Separate to the project to repair the Promenade, Hampshire County Council have been pursuing a project to construct a cycleway to the north of the existing sea wall to become part of the National Cycleway Network (NCN).
4. With the aim of minimising disruption to users of the promenade the opportunity has been taken to jointly tender the promenade and cycleway project together with the option to issue one contract to construct both elements.
TENDERS
5. Following the completion of the detailed design and specification for the works, tender documents were issued to three building contractors on an existing procurement framework with the East Solent Coastal Partnership (ESCP).
6. The tenders were spilt into three work packages:
Promenade timber replacement. Cycleway construction as a rural footpath. Cycleway with an asphalt surface.
7. The evaluation of the tenders is included as Appendix A to this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.