RESOLVED that the Executive agrees: (a) to award a contract to Hampshire Partitioning Contracts for the sum of £464,270.76 for the extension and refurbishment of the sports changing rooms at the Bath Lane Recreation Ground; and (b) that the capital budget for the changing rooms element of the project be increased by £44,000 to a total of £444,000.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
5. The submitted tender from Hampshire Partitioning Contracts has been arithmetically checked and found to be correct.
6. An additional £20,000 is required to obtain the consent of Network Rail to erect scaffold on their land. The requirement for Network Rail consent was known at the time, but the actual fee is higher than anticipated.
7. Of the original £400,000 budget, £10,000 has been spent on fees, leaving a residual budget of £390,000. The full £50,000 allocated for the grounds maintenance store is available leaving a total available budget of £440,000.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.