The purpose of this report is to provide a summary of the Council’s Street Cleansing Service. RECOMMENDATION
That the Panel notes the content of this report. INTRODUCTION
1. Local authorities have a statutory duty under the Environmental Protection Act (EPA) 1990 to ensure public spaces and highways are kept free from litter and refuse as far as reasonably practicable, as detailed in the Code of Practice on Litter & Refuse (Nov 2006).
2. To comply with the legislation the Council provides a service that is responsible for the following operations:
Cleaning of all streets, footways and open spaces that are in public ownership.
Graffiti removal
Removal of fly-tipping on public land
Emptying of litter & dog bins
Collection of dead animals from public land (domestic & wild)
A chargeable service to collect domestic bulky waste
FINANCIAL INFORMATION
3. The Street Cleansing service operates on an annual revenue budget of £983,000. An income of £2,100 is generated from small works contracts to empty bins on Hampshire County Council land and the domestic bulky waste collection service provided an income of £20,000 in 2013/14 (£18,000 2012/13).
STREET CLEANSING
4. Streets are cleaned following a schedule which is set to reflect the amount of use an area receives on a frequency that varies from daily 7 days per week in the town centre to 6 weekly on footpaths in suburban areas. The vast majority of the Borough’s roads are swept by a mechanical sweeper on a three week schedule.
LITTER BINS
5. There are 606 litter bins located throughout the Borough. The bins are emptied on a frequency that varies from three times a day, in the busy pedestrian shopping areas, through to weekly in some suburban streets and greenways.
6. The Council receive a number of requests for new installations each year (52 in 2013/14). The area operatives working within the street cleansing team monitor their use and patrol the known litter/dog fouling hotspots. It is from their experience and departmental records of complaints and enquiries that inform if the service is adequately resourced in terms of number of bins in use and number of operatives employed to empty and dispose of the contents. This helps to ensure the Council provide a service that is both affordable and can offer value for money to our customers.
7. Individual requests for a new litter bin at a specific site will be given careful consideration before proceeding with an installation. An assessment is made of how far away the nearest litter bins are to the site which has been suggested, whether it is close to a school route, a bus stop, a popular thoroughfare or a seating bench and if there is a history of complaints for the area. It is also necessary to consider who owns the land, if an installation would interfere with underground services or restrict a footway. Finally, the site is monitored for a six week period to see if the reported problem is an on-going issue. This assessment helps the Council to maintain the optimum number of litter bins and keep the service costs to an acceptable level.
8. Of the 52 requests received in the last financial year 7 have been approved and a new bin has been installed at the agreed locations. The new installation figure is low because during the six week period of monitoring it is often discovered that litter is not a regular problem at the requested location or that the issue can be resolved by the re- location of a nearby bin to a more suitable location. This is why a number of the requests are refused and in most cases an alternative and more appropriate measure can be put in place.
FLY TIPPING
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Annual Review of Street Cleansing ServiceReport | 115 KB | DownloadRead as text |
Follow Streetscene Policy Development and Review Panel at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 6 Sep 2018 | Discussion on Issues Emerging from Depot TourIt was AGREED that the Head of Streetscene pass on the Panel’s thanks to the Streetscene team who took part in the tour. | Agreed | Open |
| 6 Sep 2018 | Review of Work Programme 2018/19It was AGREED that the work programme for 2018/19 be confirmed. | Agreed | Open |
| 6 Sep 2018 | Review of Textiles RecyclingIt was AGREED that the content of the report be noted. | Agreed | Open |
| 6 Sep 2018 | Exclusion of Press and PublicIt was AGREED that in accordance with Section 100 A( 4) of the Local Government Act 1972, the public and representati... | Agreed | Open |
| 12 Jul 2018 | Review of RecyclingIt was AGREED that the Panel note the content of the report. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.