Award of Contract - Construction of Six Passivhaus Homes at Coldeast Sarisbury

Approved Executive 1 paper

Executive approved this item on Monday 5 January 2015. Below is the council's own wording, with the papers it was decided on.

Item8(1)

Resolved

RESOLVED that the Executive: (a) notes the level of grant funding secured from the Homes and Communities Agency to support delivery of the project; (b) approves a revised budget of £1,000,000 in light of the funding secured and the costs of construction confirmed by the tender; and (c) authorises the Director of Community to enter into contract with Interserve Construction Limited to complete the proposed development.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Background papers

 Report to the Executive for Decision 7th April 2014 – Affordable Housing Programme 2015-18 Executive Briefing Paper Date: 05 January 2015

Subject: Award of Contract - Construction of Six Passivhaus Homes at Coldeast, Sarisbury

Briefing by: Director of Community

Portfolio: Environment and Health and Housing

INTRODUCTION

1. The purpose of this report is to secure approval from the Executive to award a contract to the recommended building contractor to construct 6 new Passivhaus homes at Coldeast Close, Sarisbury Green.

Background

2. Passivhaus is an approach to building design developed in Germany in the 1980’s that aims to achieve consistent internal ambient temperatures with minimum reliance on heating and cooling services. As such, Passivhaus homes have the potential to provide a high level of occupant comfort while significantly reducing utility bills. The Council has set a target that 10% of homes in Welborne will be Passivhaus Certified.

3. To achieve the standard, homes must be built with meticulous attention to detail ensuring specific requirements are achieved in terms of air tightness, air circulation, and solar gain. The build process will typically involve very high levels of insulation, extremely high performance windows with insulated frames, airtight building fabric, ‘thermal bridge free’ construction, and a mechanical ventilation system with highly efficient heat recovery. As the fabric of the building itself achieves high levels of energy efficiency the need for mechanical ‘bolt on’ technology such as solar panels is reduced.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Award of Contract: Construction of Six Passivhaus Homes at Coldeast SarisburyReport 117 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present
BB
Councillor Brian BayfordCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, present
LK
Councillor Leslie KeebleCommittee Member, present
LU
Leigh UsherCommittee Officer, in attendance
RI
Richard IvoryLead Officer, in attendance
SB
Councillor Susan BayfordGuest, in attendance
SB
Councillor Susan BellGuest, in attendance
PB
Councillor Pamela BryantGuest, in attendance
ME
Councillor Marian EllertonGuest, in attendance

All 16 on the meeting page

On this subject at Fareham

Search all
  1. Award of Contract - Construction of Six Passivhaus Homes at Coldeast SarisburyThis decision
  2. Contract Variation following award of contract for Concrete repairs Contract to 18 blocks of MaisonettesAgreed
  3. Award of contract for Airfield Operator and approval of pavement repairs at Solent Airport, DaedalusAgreed
  4. Award of Contract for Operator at Fareham Innovation Centre, DaedalusAgreed
  5. Fareham Park Play Area - Award of ContractDecided
  6. Fareham Town Centre Festive Lighting Scheme - Award of ContractAgreed

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies