It was AGREED that the Board recommends to Executive that:- (a) individual rent increases be approved for Council Dwellings with effect from 6 April 20415; (b) rents for Council garages be increased by 5% with effect from 6 April 2015; (c) discretionary fees & charges be increased to provide an increase of 5% where possible, with effect from 6 April 2015; (d) the revised budget for 2014/15 be approved; (e) the base budget for 2015/16 be approved; (f) the capital programme and financing for 2014/15 to 2018/19 be approved; and (g) annual budgets and assumptions are set with aim of ensuring sufficient surpluses are held to repay debt on the maturity of each loan.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
The Board is asked to consider the proposed spending plans for the housing revenue account services, so that the Board’s comments can be forwarded to the Executive for consideration at its meeting on 2 February 2015.
Recommendation
That the Board recommend to the Executive that:-
a) Individual rents increases be approved for Council Dwellings with effect from 6 April 2015; b) Rents for Council garages to be increased by 5% with effect from 6 April 2015; c) Discretionary fees & charges to be increased to provide an increase of 5%, where possible, with effect from 6 April 2015; d) The revised budget for 2014/15 be approved; e) The base budget for 2015/16 be approved; f) The capital programme and financing for 2014/15 to 2018/19 be approved; and g) Annual budgets and assumptions are set with the aim of ensuring sufficient surpluses are held to repay debt on the maturity of each loan. INTRODUCTION
1. This report brings together the revenue and capital spending plans for 2014/15 and 2015/16 for the Board to consider. On 6 October 2014, the Executive approved the Council’s Finance Strategy for 2015/16 and later years. The budget guidelines contained within the Strategy have been used as a basis for the Housing Revenue Account (HRA) spending plans.
CAPITAL PROGRAMME - APPENDIX A
2. The five year capital programme has been updated and is summarised in the following table. More details of the capital schemes and its financing can be found in Appendix A.
3. The financing of the capital programme is mainly from the Major Repairs Reserve, Revenue Contributions to Capital, external grants, and 1:4:1 receipts from Right-to-Buy (RTB) sales.
4. The major schemes in 2015/16 and 2016/17 are the construction of 16 flats in Palmerston Avenue, 6 houses in Coldeast Close and a new sheltered scheme at the former Coldeast site plus improvements to existing stock.
5. Following the changes to the Right-to-Buy scheme, we are required to utilise retained 1:4:1 RTB receipts to increase our housing stock. Such proceeds must represent no more than 30% of the cost of acquisition or new build with the balance being met from revenue reserves or borrowing and to use the monies within three years of being received. It is intended not to borrow for this purpose.
6. Now that we are using our own staff for building repairs, there is a requirement to purchase vehicles for the team. It is anticipated that these will be replaced on a rolling five year programme.
REVENUE BUDGETS
7. The following tables summarise the base and revised budgets for 2014/15 and the base budget for 2015/16, of the HRA and its Repairs Account.
8. Until this year, we have maintained a fixed year-end balance on the Repairs Account of £1,800,000. This balance has existed for many years and has not been called upon. The purpose of the reserve was to protect the revenue account from fluctuations in the level of repairs. It is now intended to reduce the year-end balance to £1,000,000 at the end of 2014/15 and £500,000 at the end of 2015/16 which will have the effect of a reduced transfer from the Housing Revenue Account for the next three years. Base Revised Base Budget Budget Budget 2014/15 2014/15 2015/16 £000s £000s £000s Housing Revenue Account Income from service -12,120 -11,983 -12,268 Expenditure on service 6,962 4,881 5,086 Net cost of service -5,158 -7,102 -7,182
Interest paid and received 1,721 1,735 1,702 Revenue contribution to capital expenditure etc. 3,852 4,776 5,836 Surplus (-ve) / deficit 415 -591 356
Estate Improvement Programme for 2015/16It was AGREED the Board:- (a) notes the content of the report; and (b) supports and endorses the schemes identified w...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.