Resolved
RESOLVED that the Executive agrees that this item be deferred to a later meeting of the Executive.
Report to the Executive for Decision 20 April 2015 Portfolio: Policy and Resources Subject: Internal Audit Services Supplier 2015/16 Report of: Director of Finance and Resources Strategy/Policy: Internal Audit Strategy Corporate A dynamic, prudent, progressive and best practice Council Objective:
Purpose: To seek approval to use the Croydon Framework to procure Internal Audit services for 2015/16 and potentially 2 further years.
Executive summary: The Council uses an external contractor to deliver its internal audit “opinion work”. The contract in place with the current contractor expires in April 2015. However, services can continue to be purchased through the Croydon Framework at a slightly reduced cost until March 2018.
Recommendation/Recommended Option: That the Council continues to use Mazars Public Sector Internal Audit Limited for the delivery of internal audit “opinion work” over the next 1 to 3 years; and that this service is procured through the Croydon Framework.
Reason: To allow continuity of the service provision at a reduced cost, and to save the Council the cost of running its own European Union tender exercise.
Cost of proposals: These are commercially sensitive so are laid out in Appendix B.
Appendices: A: Legal advice provided by Croydon Borough Council B: Confidential paper – Financial Implications
Background papers: Report to the Executive 8 March 2010- Internal Audit Supplier. Report to the Audit and Governance Committee 16 April 2015 – Internal Audit Strategy and Annual Plan Executive Briefing Paper Date: 20 April 2015
Subject: Proposals for the Provision of Internal Audit Services
Briefing by: Director of Finance and Resources
Portfolio: Policy and Resources
INTRODUCTION
1. The Council has a statutory requirement under the Accounts and Audit Regulations ‘to maintain an adequate and effective system of internal audit of its accounting records and of its system of internal control in accordance with the proper internal audit practices’.
2. Since July 2005 the internal audit service has been provided jointly by a small in-house team and an external contractor. The current contractor is Mazars Public Sector Internal Audit Limited who acquired Deloitte and Touche Public Sector Internal Audit Limited in 2014. The latter were awarded the contract in 2010 following a Fareham Borough Council-only tender carried out in accordance with the Public Contracts Regulations. This contract expires in April 2015.
3. The Internal Audit Strategy has recently been updated and approved by the Audit and Governance Committee. This proposes continuing with the use of an external contractor to deliver the opinion work which feeds directly into the Annual Head of Audit Opinion, in order to maintain independence. However, the amount of opinion work is to be reduced and the resources moved to the in-house team to deliver more of the wider audit services.
4. This report sets out the proposals for procuring the contractor work from 2015/16.
PROPOSAL
5. In 2014/15, changes were introduced to the specification that the contractor was working to, that better reflected the new ways of working at the Council. There are therefore advantages with continuing with the current contractor due to the learning curve involved in understanding the Council’s culture and processes and the new way that the audit service needs to be delivered.
6. It is therefore proposed that the Council continues to use Mazars Public Sector Internal Audit Limited for the next 1 to 3 years by becoming part of the Croydon Audit Framework. 7. The Croydon Audit Framework was set up in 2008. It was initially designed for the joint procurement of internal audit and counter fraud services for the London Borough Councils but has since been expanded such that there are currently 30 Councils who purchase services through the framework.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Proposals for the Provision of Internal AuditReport | 211 KB | DownloadRead as text |
Follow Executive at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... | Agreed | Open |
| 7 Sep 2026 | References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... | Agreed | Open |
| 7 Sep 2026 | Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... | Approved | Open |
| 7 Sep 2026 | Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... | Approved | Open |
| 7 Sep 2026 | Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.