Resolved
It was AGREED that the Panel notes the content of the report.
Health and Housing Policy Development and Review Panel agreed this item on Thursday 23 July 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
It was AGREED that the Panel notes the content of the report.
This report sets out a summary of the performance for Building Services covering all aspects of the service delivered to the residents for the first quarter of 2015/16.
That the panel notes and scrutinises the information contained in the report. INTRODUCTION
1. This report sets out performance information for the responsive repairs service and an update on the delivery of the capital programme by the planned maintenance team.
2. In addition to the performance information, assurance statements relating to the significant health and safety risks associated with the housing stock are also provided.
RESPONSIVE REPAIRS SERVICE
3. The Housing Repairs service has applied the ‘system thinking’ approach across all of the Council housing stock. From 1st April 2015 this system operated in 100% of the borough. The service is primarily delivered with directly employed operatives; supporting contractors worked for the Council where necessary to allow for the mobilisation of the Direct Service Organisation (DSO) and the new system of work.
4. A van stock system and materials delivery service has been introduced to enable efficiency in the delivery of repairs. This has been working successfully and data is being collected on materials used on repairs to continuously improve the intelligence and efficiency of the service.
5. The new approach to the work has enabled us to deliver the five key steps that are of value to our customers when they need a repair to their home. These are:
i. Collect “Clean information” – Name, address, contact number, brief detail of the problem, date and time when it is convenient for us to attend ii. Allocate the work – at the right time, allocate the job to an operative with the right skills iii. Access – attend at the right time, be polite, courteous and presentable iv. Diagnose – identify the root cause of the problem, understand the individual needs of the customer and tailor a solution that is necessary and proportionate v. Repair – use the right skills and have access to the right materials to fix the problem 6. The performance of the new system is demonstrated by measures that reflect what matters to our customers:
(a) Did we turn up when we said we would (at the time convenient to the customer)? (b) Did we get the operative with the right skills to visit the customer first time? (c) Did we do the right repair? (d) How long did we take?
7. The performance levels are consistent with expectations during the current transitional period. The mobilisation is anticipated to take 6 months to fully incorporate 100% repairs demand by the in-house service. Tenant Forums and panel members will be consulted to ensure the Council are providing performance measures that matter. The performance measures will be presented annually to the panel. PLANNED MAINTENANCE SERVICE
8. The current planned maintenance projects are being progressed generally by tender opportunities or utilising existing long term agreements. Detailed below are both the current and proposed projects:-
a) Kitchen and bathroom modernisation continue to be undertaken using an existing contract arrangement with MITIE Property Services with works being identified via the responsive repairs service or customer requests.
b) Quotes are currently being sought to provide a new bin store at Garden Court with works expected to start later this summer.
c) After a number of arson attacks on the bin store at Langstone House, Redlands Lane, an access control system is being provided to improve security and access for the residents of the block.
d) Replacement gas boilers and central heating systems are being provided through an existing arrangement with Liberty Gas.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Council Housing: Repairs and Maintenance ReportReport | 101 KB | DownloadRead as text |
Follow Health and Housing Policy Development and Review Panel at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Sep 2018 | Affordable Housing UpdateIt was AGREED that: (a) the Panel notes the content of the presentation; and (b) the Panel’s thanks to Officers be pl... | Agreed | Open |
| 20 Sep 2018 | Tenancy Management ReportIt was AGREED that: (a) the Panel notes the content of the report; and (b) the Panel’s thanks to Officers be placed o... | Agreed | Open |
| 20 Sep 2018 | Empty Properties ReportIt was AGREED that: (a) the Panel notes the content of the report; and (b) the Panel’s thanks to Officers be placed o... | Agreed | Open |
| 19 Jul 2018 | Affordable Housing UpdateIt was AGREED that the Panel notes the information contained in the report and the Affordable Housing Strategic Lead ... | Agreed | Open |
| 19 Jul 2018 | Council Housing Repairs and Maintenance ReportIt was AGREED that the Panel notes the content of the report. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.