RESOLVED that the Executive: (a) approves the draft Heads of Terms, as set out in confidential Appendix A to this report; (b) delegates authority to the Director of Finance and Resources in consultation with the Executive Member for Policy and Resources to agree the detailed terms, as appropriate; and (c) agrees to reinvest the proceeds of the disposal of land under this agreement into the delivery of actions that support the Vision for Daedalus, including the airport, the business park and the open space.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
National Grid is planning a major new energy infrastructure project linking the United Kingdom's electricity transmission network to France, with its UK connection point being located in Fareham.
The project requires a large area of land to construct a converter station, which is a facility that converts alternating (AC) current to direct current (DC), and a site at Daedalus has been identified for this facility.
The report sets out commercial Heads of Terms for the disposal of land to enable this project to progress to the next stage of technical feasibility and detailed design. If the technical feasibility and suitable environmental evidence can be demonstrated, then the Council would grant an option to National Grid to enter into a lease for land at Daedalus. The option would be exercisable by them upon certain conditions being met, and the lease would be completed once the facility was constructed.
Assuming that the lease is completed, the premium paid by National Grid for the interest in the land would be reinvested in Daedalus, to provide funding for some of the improvements identified in the Council’s approved Vision for the site. Recommendations:
That the Executive: (a) approves the draft Heads of Terms, as set out in confidential Appendix A to this report; (b) delegates authority to the Director of Finance and Resources in consultation with the Executive Member for Policy and Resources to agree the detailed terms, as appropriate; and (c) agrees to reinvest the proceeds of the disposal of land under this agreement into the delivery of actions that support the Vision for Daedalus.
Reason:
To enable the disposal of land to National Grid to progress further.
Cost of proposals:
The legal and surveyors costs associated with the disposal of land will be met from the proceeds of the disposal. The premium payable, should a lease be entered into, will be made available to fund the improvements in the Vision for Daedalus.
Appendices: A: Draft Heads of Terms (CONFIDENTIAL) B: Illustrative Map of the Site
Background papers: Executive Briefing Paper Date: 7 December 2015 Subject: Disposal of Land at Daedalus Briefing by: Director of Finance and Resources Portfolio: Policy and Resources
INTRODUCTION
1. National Grid is planning a major new energy infrastructure project linking the United Kingdom's electricity transmission network to France, with its UK connection point being located in Fareham.
2. The project requires a large area of land to construct a converter station and land at Daedalus has been identified as a potential location for this facility. The report sets out commercial Heads of Terms for the disposal of land to enable this project to progress to the next stage of technical feasibility and detailed design.
Background
3. The National Grid project, known as Interconnexion France Angleterre 2 (IFA2), is a major piece of new energy infrastructure linking the United Kingdom's electricity transmission network to France, with its UK connection point being located in Fareham.
4. The project will provide a high voltage direct current (HVDC) electricity interconnector between Fareham (at Daedalus) and Caen in Normandy, France. The interconnector is made up of undersea cables running for more than 100 miles between the two countries which would connect at either end to a converter station. The converter station in Fareham is proposed to be based at Daedalus in Stubbington.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.