RESOLVED that the Executive approves: (a) the proposed programme of works as detailed in Appendix A; and (b) a budget of up to £50,000 to enable the works to be carried out to ensure the items of equipment are brought up to standard, funded from Section 106 contributions for the maintenance of play and recreational facilities.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 7 March 2016 Portfolio: Leisure and Community
Subject: Play and Recreational Improvement Programme
Report of: Director of Operations
Strategy/Policy: Leisure Strategy
Corporate Objective: Leisure for Health and For Fun
Purpose: To agree improvement works and a refurbishment programme for the Council’s outdoor play and recreational equipment.
Executive summary: The Council has 63 items of outdoor play and recreational equipment located across the Borough that are provided predominantly for young people aged 13 and over.
A strategic review of all play and recreational equipment has been undertaken to determine what works needed to be completed to help bring all items of equipment up to a good standard and to establish a programme of works required.
Appended to the report is a proposed programme of works which can be funded from the Section 106 Developer Contributions collected for the maintenance of play and recreational facilities.
The review findings and a draft programme were presented to the January meeting of the Leisure and Community Policy Development and Review Panel and members endorsed the programme without any amendment.
Recommendation/Recommended Option: That the Executive approves:
(a) the proposed programme of works as detailed in Appendix A; and
(b) a budget of up to £50,000 to enable the works to be carried out to ensure the items of equipment are brought up to standard, funded from Section 106 contributions for the maintenance of play and recreational facilities. Reason: To facilitate the improvement of the Borough’s outdoor play and recreational equipment in order to maintain a good standard of play provision and to ensure the equipment remains safe, attractive and accessible to young people.
Cost of proposals: The total cost to undertake all of the improvements identified is £70,000.
The proposal is to redirect the funds remaining from the previously agreed mini makeover play area programme, which is £20,000 and the remaining amount of £50,000 be funded from the Section 106 maintenance of play and recreational facilities.
Appendix: A: Complete schedule of improvement works.
Background papers: Presentation to the Leisure and Community Policy Development and Review Panel – Review of Outdoor Play and Recreational Equipment – January 2016
Report to the Leisure and Community Policy Development and Review Panel – Open Spaces Improvements Programme – September 2014
Reference papers: Executive Briefing Paper Date: 7 March 2016 Subject: Play and Recreational Improvement Programme Briefing by: Director of Operations Portfolio: Leisure and Community
INTRODUCTION
1. In September 2014 the responsibility for delivering the programme of play area improvements was transferred to the Leisure team. In 2014/15 a strategic review was undertaken of all 43 play areas and a priority programme of improvements identified. At the time of undertaking that review it was also considered important to carry out a review of the Council’s outdoor play and recreational facilities.
2. The Council has 63 items of outdoor play and recreational equipment, predominantly used by children aged 13 and over. This includes skate parks, multi use games areas (MUGA’s), teen shelters, football goals, basketball hoops and outdoor fitness equipment. These are managed and maintained by the Councils Streetscene team who undertake weekly inspections to ensure the equipment is safe and to address any repairs required.
3. The purpose of undertaking the play and recreational review was exactly the same as the children’s play area review; to determine what works were needed to bring all items of equipment up to a good standard and to establish a programme of works.
STRATEGIC REVIEW
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.