CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Fareham Borough Council
Executive, Monday 11 April 2016 at 6.00pm

Daedalus Programme Update

Noted Executive 1 paper

Executive noted this item on Monday 11 April 2016. Below is the council's own wording, with the papers it was decided on.

Item9(1)

Resolved

RESOLVED that the Executive: (a) note the progress on Daedalus to date and the progress towards implementing the Vision in future years; (b) agrees to the inclusion of the following schemes in the 2016/17 capital programme; · Development of a new hanger and associated office space for existing airfield tenant at the indicative cost of £4.3m · Development of six new hangers suitable for relocation of existing businesses and attracting new businesses at an indicative cost of £3m. · Development of five new existing general aviation tenants and attracting new locally based aircraft an indicative cost of £1.5m; (c) agree to delegate authority to the Director of Finance and Resources to award the tenders to build the new hangers, subject to the cost being within the allocated budget; and (d) appoints members to a new Daedalus Asset Development Members Working Group.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 11 April 2016

Portfolio: Policy and Resources

Subject: Daedalus Programme Update

Report of: Director of Finance and Resources

Strategy/Policy: Corporate Strategy To maintain and extend prosperity Corporate Objective: A Dynamic, Prudent and Progressive Council

Purpose: The purpose of this report is to review progress on the Council’s £8.3m investment project at Daedalus, to update the Executive on proposals to be implemented in order to achieve the Council’s published Vision in the future and to make recommendations for investment to deliver elements of this.

Executive summary: Prior to its acquisition of the site, the Executive agreed to undertake three projects on the Daedalus site. These were the construction of the Innovation Centre, improvements to the runway and the construction of new hangar space. Two of these projects, the Innovation Centre and the runway improvements have now been completed and have been operational for a year. This report reviews their achievements against the original objectives and the lessons learned.

The Innovation Centre has been a great success and at the end of March was fully occupied, greatly in excess of its original target. The runway improvements have also been successful and have enabled the airfield operator to gain a CAA license.

Subsequent to the Borough Council’s acquisition of the airfield, the Executive agreed a Vision for Daedalus. This report also summarises progress on the various projects needed to realise the Vision. In particular it seeks approval to include within the capital programme the cost of developing new hangars and the appointment of a Members Working Group to oversee the delivery of the projects. Recommendation/Recommended Option: That the Executive:

(a) notes the progress on Daedalus to date and the progress towards implementing the Vision in future years;

(b) agrees to the inclusion of the following schemes in the 2016/17 capital programme;  Development of a new hangar and associated office space for an existing airfield tenant at an indicative cost of £4.3m  Development of six new hangars suitable for relocation of existing businesses and attracting new business at an indicative cost of £3m.  Development of five new hangars and associated communal facilities suitable for relocation of existing general aviation tenants and attracting new locally based aircraft an indicative cost of £1.5m;

(c) agrees to delegate authority to the Director of Finance and Resources to award the tenders to build the new hangars, subject to the cost being within the allocated budget; and

(d) appoints Members to a new Daedalus Asset Development Members Working Group.

Reason: To enable the delivery of the Vision for Daedalus to continue.

Cost of proposals: The estimated cost of the development of new hangars in 2016/17 is £8.8m. The cost of other capital projects associated with the delivery of the Vision for Daedalus will be the subject of individual business cases which will be brought to the Executive at the appropriate time. Some capital costs, including the delivery of infrastructure on Daedalus West, are already partly or fully funded, but the full costs will be reported to the Executive as plans become firmly established.

Background papers: File of working papers

Reference papers: Fareham Borough Council’s Vision for Daedalus Executive Briefing Paper Date: 11 April 2016 Subject: Daedalus Programme Update Briefing by: Director of Finance and Resources Portfolio: Policy and Resources

INTRODUCTION

1. At its meeting on 4th November 2013, the Executive agreed to move forward with the development of three investment projects on the Daedalus site and set up a Member Working Group to oversee them. These three projects were:

 Development of a new Innovation Centre;  Improvements to the runway;  The development of new hangar space.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Daedalus Programme UpdateReport 207 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present as substitute
SB
Councillor Susan BellCommittee Member, present as substitute
KE
Councillor Keith EvansCommittee Member, present as substitute
TH
Councillor Tiffany HarperCommittee Member, present as substitute
KM
Councillor Kay MandryCommittee Member, present as substitute
LU
Leigh UsherCommittee Officer, in attendance
SW
Samantha WightmanCommittee Officer, in attendance
RI
Richard IvoryOfficer, in attendance
BB
Councillor Brian BayfordGuest, in attendance
LK
Councillor Leslie KeebleGuest, in attendance
DS
Councillor David SwanbrowGuest, in attendance

All 19 on the meeting page

On this subject at Fareham

Search all
  1. Daedalus Programme UpdateThis decision
  2. Presentation - Daedalus Delivery and Work Programme UpdateNoted
  3. Investment Programme for Solent Airport, DaedalusAgreed
  4. Investment Programme for Solent Airport, DaedalusNoted
  5. Daedalus Revenue Budget and Capital ProgrammeNoted

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies