Resolved
RESOLVED that the Executive notes the report.
Executive decided this item on Monday 16 May 2016. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Executive notes the report.
Report to the Executive for Decision 16 MAY 2016 Portfolio: Policy and Resources Update to completed Council Car Park and Pedestrian Subject: Highways Works Report of: Director of Finance
Strategy/Policy: Finance Strategy
Corporate Objective:
Purpose: To advise the Executive of the outturn cost for the Council car park and pedestrian highway works and to detail the key reasons behind the overspend on this project.
Executive summary: In September 2013 the Executive approved the award of contract for the resurfacing and repairs of numerous car parks and footways around the Borough. The contract was awarded to Colas Limited in the sum of £329,460.93
The final account for the project has been agreed at £511,268 which is 55% over the approved contract sum.
This report details the main reasons for this overspend and advises the Executive that this has been funded from within existing budgets.
Recommendation/Recommended Option: That the Executive notes the report.
Reason: To comply with the Council’s Financial Regulation 15: Contracts and Procurement Procedures.
Cost of proposals: The overspend has been financed from within existing budgets and no further funding is required.
Background papers: File of Correspondence Executive Briefing Paper Date: 16 May 2016 Subject: Update to completed Council Car Park and Pedestrian Highways Works Briefing by: Director or Finance Portfolio: Policy and Resources
INTRODUCTION
1. In September 2013 the Executive approved the award of contract for the resurfacing and repairs of numerous car parks and footways around the Borough. The contract was awarded to Colas Limited in the sum of £329,460.93
2. The final account for the project has been agreed at £511,268 which is 55% over the approved contract sum. The Councils procurement rules require that whenever the settled amount of a contract exceeds the tender price by more than 10% or £20,000 the matter should be reported to the Executive, with reconciliation to the tender sum.
3. This report outlines the key reasons behind the overspend on this project.
SCOPE OF WORKS
4. The corporate resurfacing contract was an extensive project which covered works to 40 sites around the borough and ranged from, for example, drain clearance to the car park at Blackbrook Park Recreation Ground to creating an additional 30 spaces at the site of the new Portchester Community Centre.
FINAL ACCOUNT
5. The final account was £182,000 over the tender sum. The main reasons for this overspend are:
(a) Portchester Community Centre 6. The construction of the additional 30 car parking bays at the site of the former Portchester Community Centre was considerably more complicated than envisaged, partly due to the adverse weather conditions that were encountered and partly due to the need to landscape a wider area of the land than the car park itself.
7. Work started to construct the car park in December 2013, but following the initial groundworks where the land was excavated and the base level of stone imported, a period of heavy and prolonged rainfall was encountered which negated the works that had been carried out and required additional excavation, additional material to be imported and an enhancement to the drainage system. The net result of these works which resulted from the adverse weather was £38,600.
8. During the works to construct the new Portchester Community Centre, the excess top soil arising from the site was placed on the location of the former community centre following its demolition. A consequence of this was that the levels of the land on the northern and eastern areas surrounding the car park where not compatible with the use of the land as a car park. Extensive landscaping works were therefore required to excavate and dispose of the poor quality arisings and then to import and grade the required natural top soil for the planting areas. The cost of these additional works was £52,600.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Update to completed Council Car Park and Pedestrian Highways WorksReport | 97 KB | DownloadRead as text |
Follow Executive at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... | Agreed | Open |
| 7 Sep 2026 | References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... | Agreed | Open |
| 7 Sep 2026 | Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... | Approved | Open |
| 7 Sep 2026 | Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... | Approved | Open |
| 7 Sep 2026 | Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.