RESOLVED that the Executive: (a) agrees in principle to proceed with Fareham Innovation Centre Phase 2, with provision of £6.6m being made for the scheme within the Capital Programme; (b) notes that if the application for grant funding from the Solent Local Growth Deal is unsuccessful, the business case will be reviewed by the Director of Finance and Resources to consider scheme viability, who will make recommendations to the Executive; (c) grants delegated authority to the Director of Finance and Resources to appoint a design team to complete that pre-construction phase of work; (d) grants delegated authority to the Director of Finance and Resources in consultation with the Executive Leader, to accept a tender for the construction of the scheme provided it is within the capital budget and funding is secured; and (e) notes the membership of the Members Daedalus Working Group as Councillors J E Butts, T Cartwright, M J Ford and [name removed] and an opposition group member, to be advised.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Owing to the remarkable success of Fareham Innovation Centre, it is now being proposed to build a second phase, immediately adjacent to the existing building.
The purpose of this second phase is twofold. First of all it will provide some larger space to enable businesses within the first phase to grow and move on, thus retaining their jobs and skills within the immediate area. Secondly it will provide more small office and workshop space to enable new start-up businesses to move into the Centre and be supported to prosper and grow in their early years.
The total estimated cost of the scheme is £6.6m and authority is sought to add this to the Capital Programme. However, a bid for a grant of £1.980m has been submitted to the Solent LEP under the Solent Local Growth Deal. If successful, this will reduce the Council's borrowing requirement, although the outcome of the submission will not be known until later in 2016.
Recommendations
That the Executive:
(a) agrees in principle to proceed with Fareham Innovation Centre Phase 2, with provision of £6.6m being made for the scheme within the Capital Programme; (b) notes that if the application for grant funding from the Solent Local Growth Deal is unsuccessful, the business case will be reviewed by the Director of Finance and Resources to consider scheme viability, who will make recommendations to the Executive;
(c) grants delegated authority to the Director of Finance and Resources to appoint a design team to complete the pre-construction phases of work; and
(d) grants delegated authority to the Director of Finance and Resources in consultation with the Executive Leader, to accept a tender for the construction of the scheme provided it is within the capital budget and funding is secured.
Reason:
To enable the Fareham Innovation Centre Phase 2 to proceed, building on the success of the first phase and continuing to provide support to enable new businesses to prosper and grow within the Solent Enterprise Zone at Daedalus.
Cost of proposals:
The total capital cost of the scheme is estimated to be £6.6m. It is anticipated that this will be partly be funded through prudential borrowing and partly through a grant from the Solent Local Growth Fund, if the latter is successful.
Appendices: A: Confidential - Detailed financial analysis of proposal B: Confidential - Outline Business Case - submission to the Solent LEP
Background papers: File of Correspondence and Funding Bid Application.
Reference papers: Executive Briefing Paper Date: 06 June 2016 Subject: Fareham Innovation Centre - Phase 2 Briefing by: Director of Finance and Resources Portfolio: Policy and Resources
INTRODUCTION
1. As Members will be aware from previous reports on the subject, Fareham Innovation Centre has been a remarkable success. It has fulfilled its principal objective of providing an environment in which new innovative businesses, predominantly within the marine, aviation, aerospace and advanced manufacturing businesses can prosper and grow. It has exceeded all expectations by achieving 100% occupation within its first year of operation, a target which was not expected to be reached until its third year.
2. A key element of its success has been the provision of on-site business support. This has been crucial in providing advice, support and access to networking and professional opportunities. This has helped new businesses survive their crucial formative first year and begin to grow.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.