Local Development Scheme

Agreed Planning 2 papers

Planning and Development Policy Development and Review Panel agreed this item on Tuesday 19 July 2016. Below is the council's own wording, with the papers it was decided on.

Item6

Resolved

It was AGREED that the Panel, (a) subject to the amendments being made to add clarity to the dates in the tables on pages 18 and 26 of the report, support the timetables as set out in the Local Plan Review; and (b) approve the Director of Planning and Regulation to make any necessary minor changes to the , prior to the document being considered by the Executive in September 2016.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Planning and Development Policy Development and Review Panel

Summary

This report summarises the revised Fareham Borough Local Development Scheme (LDS). The purpose of the LDS is to set out the work programme timetable for producing the Fareham Borough Local Plan Review, as well as the Statement of Community Involvement (SCI) and the Authority Monitoring Report (AMR).

Recommendation

The Panel is invited to support the Local Development Scheme and make any comments they wish in terms of the timetables set out for the Local Plan Review, Statement of Community Involvement and Authority Monitoring Report.

The Panel approves the Director of Planning and Regulation to be authorised to make any necessary minor changes to the Local Development Scheme, providing that these do not change the overall direction, shape or emphasis of the document, prior to the document being considered by the Fareham Borough Executive in September 2016. INTRODUCTION

1. This report provides a summary of the key revisions made to the Fareham Borough Local Development Scheme.

2. The existing Fareham Borough Local Development Scheme (LDS) was adopted in September 2014 and provided the timetable for the completion of the Fareham Borough Local Plan Part 2 (Development Sites and Policies) and Local Plan Part 3 (Welborne Plan), which were both subsequently adopted in June 2015.

3. The adopted LDS set out a simple timetable for the preparation, examination and adoption of the Local Plan Review. The purpose of this LDS is to update that timetable and to provide further information on the work programme for the Local Plan Review.

REQUIREMENT FOR A LOCAL DEVELOPMENT SCHEME

4. Local planning authorities are required by legislation to prepare and maintain a Local Development Scheme (LDS). A LDS provides a timetable for the preparation of a Local Plan and any other Local Development Documents, such as the Authority Monitoring Report, by a Local Planning Authority. The purpose of the LDS is to ensure that the community is aware of the programme for preparing the Local Plan and importantly when there will opportunities to respond to consultations on it.

NEED TO UPDATE CURRENT LOCAL DEVELOPMENT SCHEME

5. During the examinations of Local Plan Part 2 & Local Plan Part 3, the Council made a commitment to commence an early review of the Local Plan, following the commencement of a review of the South Hampshire Strategy by the Partnership for Urban South Hampshire (PUSH). A timetable that was considered to be achievable to undertake a review of the Local Plan at that time was agreed to by the Planning Inspector and published in the existing Local Development Scheme (2014).

6. That timetable was based on the PUSH review timeline for the South Hampshire Strategy (now known as PUSH Spatial Position Statement). Due to the complexity of the PUSH review, the timetable for completion of that Strategy was subsequently increased by PUSH by approximately three months from March 2016 until June 2016.

7. In order for the Local Plan Review to be informed by, and be in consistency with, the PUSH Spatial Position Statement and its supporting evidence, it is considered necessary to revise the timetable for the development of the Fareham Borough Local Plan Review through this Local Development Scheme. The revised timetable will still enable the Council to meet the Government’s target for having a NPPF compliant Local Plan submitted for examination by March 2018, with submission scheduled for late 2017.

8. The revised timetable for the Fareham Local Plan Review is set out as the following:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 365 KB Download
PDF
Local Development SchemeReport 90 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 15 attended
KB
Councillor Keith BartonCommittee Member, present
SC
Councillor Shaun CunninghamCommittee Member, present
JB
Councillor Jonathan ButtsVice-Chairman, present
GF
Councillor Geoff FazackarleyCommittee Member, present
CW
Councillor Christopher WoodCommittee Member, present
AM
Councillor Arthur MandryChairman, present
NW
Councillor Nick WalkerCommittee Member, present
KE
Councillor Keith EvansExecutive Member, in attendance
MB
Melanie BettleyCommittee Officer, expected
AC
Astra CleifeCommittee Officer, expected
RJ
Richard JolleyOfficer, expected
OS
Oli SeebohmOfficer, expected

All 15 on the meeting page

On this subject at Fareham

Search all
  1. Local Development SchemeThis decision
  2. Fareham Borough Local Development SchemeApproved
  3. Local Development SchemeDecided
  4. Local Development SchemeAgreed
  5. Local Development SchemeAgreed
  6. Local Development SchemeDecided

More from Fareham Planning and Development Policy Development and Review Panel

All decisions
MeetingDecisionOutcome
4 Sep 2018 Welborne Delivery UpdateIt was AGREED that the Welborne Strategic Lead, Sarah Ward, be thanked for her informative presentation. Agreed Open
4 Sep 2018 Planning and Development Policy and Development Review Panel Work ProgrammeIt was AGREED that the Panel: - (a) reviewed and agreed the proposed Work Programme for 2018/19; and (b) reviewed the... Agreed Open
17 Jul 2018 Neighbourhood PlanningIt was AGREED that the Senior Planner (Strategy and Regeneration) - Emma Betteridge be thanked for her very informati... Agreed Open
17 Jul 2018 Planning and Development Policy and Development Review Panel Work ProgrammeIt was AGREED that the Panel: - (a) review and agree the proposed Work Programme for 2018/19; and (b) review the outc... Agreed Open
15 May 2018 Introduction to Portfolio ServicesIt was AGREED that: (a) the Director of Planning and Regulation and three members of his team; Adam Collier - Princip... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies