Health and Public Protection Policy Development and Review Panel agreed this item on Tuesday 17 January 2017. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

It was AGREED that Members :- (a) note the progress on the current Traffic Management Programme in Appendices A to D of the report; and (b) recommend to the Executive that this work, including progress on Traffic Regulation Orders and the work undertaken on the deployment of the Speed Limit Reminder signs, be noted.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Health and Public Protection Policy Development and Review Panel

Summary

The Council’s Executive agreed the 2016/17 Traffic Management Programme on 1st February 2016. This report updates Members on progress on the 2016/17 Traffic Management Programme, and informs Members of the general work undertaken by the Traffic Management Team.

Recommendation

Members are asked to:-

(a) note the progress on the current Traffic Management Programme in Appendices A to D and;

(b) recommend to the Executive that this work, including progress on Traffic Regulation Orders and the work undertaken on the deployment of the Speed Limit Reminder signs, be noted. INTRODUCTION

1. Traffic Management is undertaken on behalf of Hampshire County Council (HCC) through an Agency Agreement. An annual allocation of funding is provided for administration of the Agency Agreement and to fund the introduction of Traffic Regulation Orders (TROs) and associated signs and lines.

2. This report is presented to the Panel in order to provide an update on the progress of the current programme and seeks comment on the proposed way forward for the introduction of any new TRO’s for 2017/18, before being recommended to the Executive. The current programme was last reported to and agreed by the Executive on 1st February 2016.

3. The total allocation from HCC for 2016/17 for implementing TROs, including a small amount for the introduction of new signing and lining to address minor traffic management issues and the marking of disabled driver bays, was £15,500, a further £4000 is provided for advertising TRO’s. The Council has received notification that funding for the Traffic Management team will be reducing significantly for 2017/18 and 2018/19, this is further addressed under funding and resources.

TRAFFIC REGULATION ORDERS

4. The TRO Programme is a programme of investigations that are likely to result in the introduction of a legally enforceable TRO. Requests are received from many sources asking for the provision of restrictions, every one of which requires statutory consultation procedures including press advertisements and site notices. Without these processes, it would not be possible to provide the enforcement required after the order is introduced.

5. Where it is deemed necessary (at the discretion of the Traffic and Design Manager in consultation with the Head of Parking and Enforcement), a letter drop is carried out to all directly affected frontages where a TRO is proposed. This is done where a proposal is likely to be contentious, and where the scheme is likely to be modified if there are significant objections. This type of consultation is therefore less likely to take place where, for example, the proposal is a small scheme to provide something like or nothing more than junction protection for safety reasons.

FUNDING AND RESOURCES

6. In addition to the funding allocation from HCC as mentioned in paragraph 3, further TROs are at times required to be introduced as part of new developments or other highway schemes such as for casualty reduction. These TROs are funded separately, either by the developer or directly from the individual scheme budget and are scheduled in Appendix B Table 5.

7. The works and advertising costs for the introduction of a typical TRO involving double yellow lines are in the region of £1,500, as these do not require signing. Costs for single yellow line orders, limited waiting orders or speed limits will be more due to the regulatory signing requirements, particularly if there is a need for the signing to be illuminated. 8. Based on previous resource and funding levels, around 15 sites can be considered for implementation in each year; these are generally referred to as comprising the "internal programme". The amount which can be processed depends on the "external" programme, which is made up of those requests that come in from and are funded by HCC and developers.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Traffic Management Report Appendix AAppendix 85 KB Download
PDF
Traffic Management Report Appendix BAppendix 65 KB Download
PDF
Traffic Management Report Appendix CAppendix 258 KB Download
PDF
Traffic Management Report Appendix DAppendix 85 KB Download
PDF
Traffic Management ReportReport 161 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 16 attended
MF
Councillor Michael Ford, JPChairman, present
TE
Councillor Tina EllisVice-Chairman, present
KB
Councillor Keith BartonCommittee Member, present
FB
Councillor Fred BirkettCommittee Member, present
PB
Councillor Pamela BryantCommittee Member, present
JE
Councillor Jack EnglefieldCommittee Member, apologies
KT
Councillor Katrina TrottCommittee Member, present
MB
Melanie BettleyCommittee Officer, expected
TC
Councillor Trevor Cartwright, MBEGuest, in attendance
PD
Paul DoranOfficer, expected
CO
Chris OldhamOfficer, expected
IR
Ian RickmanOfficer, expected

All 16 on the meeting page

On this subject at Fareham

Search all
  1. Traffic Management ReportThis decision
  2. Call-In of Executive Decision No. 1855: Traffic ManagementApproved
  3. Traffic ManagementApproved
  4. Traffic ManagementAgreed
  5. Traffic Management ProgrammeAgreed
  6. Traffic Management ProgrammeAgreed

More from Fareham Health and Public Protection Policy Development and Review Panel

All decisions
MeetingDecisionOutcome
11 Sep 2018 Police and Crime Panel UpdateIt was AGREED that Councillor Cartwright be thanked for providing his verbal update. Agreed Open
11 Sep 2018 Annual Update on Fareham Parking Enforcement ServiceIt was AGREED that the Panel notes the content of the report. Agreed Open
11 Sep 2018 Health and Public Protection Policy Development and Review Panel Work ProgrammeIt was AGREED that the Health and Public Protection Policy Development and Review Panel:- (a) approves the programme ... Agreed Open
10 Jul 2018 Health and Public Protection Policy Development and Review Panel Work ProgrammeIt was AGREED that the Panel: - (a) approves the programme of items for 2018/19, as set out in Appendix A of the repo... Agreed Open
29 May 2018 Introduction to Health and Public Protection Portfolio ServicesIt was AGREED that the Panel note the contents of the presentation. Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies