Health and Public Protection Policy Development and Review Panel agreed this item on Tuesday 17 January 2017. Below is the council's own wording, with the papers it was decided on.
It was AGREED that Members :- (a) note the progress on the current Traffic Management Programme in Appendices A to D of the report; and (b) recommend to the Executive that this work, including progress on Traffic Regulation Orders and the work undertaken on the deployment of the Speed Limit Reminder signs, be noted.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to Health and Public Protection Policy Development and Review Panel
Summary
The Council’s Executive agreed the 2016/17 Traffic Management Programme on 1st February 2016. This report updates Members on progress on the 2016/17 Traffic Management Programme, and informs Members of the general work undertaken by the Traffic Management Team.
Recommendation
Members are asked to:-
(a) note the progress on the current Traffic Management Programme in Appendices A to D and;
(b) recommend to the Executive that this work, including progress on Traffic Regulation Orders and the work undertaken on the deployment of the Speed Limit Reminder signs, be noted. INTRODUCTION
1. Traffic Management is undertaken on behalf of Hampshire County Council (HCC) through an Agency Agreement. An annual allocation of funding is provided for administration of the Agency Agreement and to fund the introduction of Traffic Regulation Orders (TROs) and associated signs and lines.
2. This report is presented to the Panel in order to provide an update on the progress of the current programme and seeks comment on the proposed way forward for the introduction of any new TRO’s for 2017/18, before being recommended to the Executive. The current programme was last reported to and agreed by the Executive on 1st February 2016.
3. The total allocation from HCC for 2016/17 for implementing TROs, including a small amount for the introduction of new signing and lining to address minor traffic management issues and the marking of disabled driver bays, was £15,500, a further £4000 is provided for advertising TRO’s. The Council has received notification that funding for the Traffic Management team will be reducing significantly for 2017/18 and 2018/19, this is further addressed under funding and resources.
TRAFFIC REGULATION ORDERS
4. The TRO Programme is a programme of investigations that are likely to result in the introduction of a legally enforceable TRO. Requests are received from many sources asking for the provision of restrictions, every one of which requires statutory consultation procedures including press advertisements and site notices. Without these processes, it would not be possible to provide the enforcement required after the order is introduced.
5. Where it is deemed necessary (at the discretion of the Traffic and Design Manager in consultation with the Head of Parking and Enforcement), a letter drop is carried out to all directly affected frontages where a TRO is proposed. This is done where a proposal is likely to be contentious, and where the scheme is likely to be modified if there are significant objections. This type of consultation is therefore less likely to take place where, for example, the proposal is a small scheme to provide something like or nothing more than junction protection for safety reasons.
FUNDING AND RESOURCES
6. In addition to the funding allocation from HCC as mentioned in paragraph 3, further TROs are at times required to be introduced as part of new developments or other highway schemes such as for casualty reduction. These TROs are funded separately, either by the developer or directly from the individual scheme budget and are scheduled in Appendix B Table 5.
7. The works and advertising costs for the introduction of a typical TRO involving double yellow lines are in the region of £1,500, as these do not require signing. Costs for single yellow line orders, limited waiting orders or speed limits will be more due to the regulatory signing requirements, particularly if there is a need for the signing to be illuminated. 8. Based on previous resource and funding levels, around 15 sites can be considered for implementation in each year; these are generally referred to as comprising the "internal programme". The amount which can be processed depends on the "external" programme, which is made up of those requests that come in from and are funded by HCC and developers.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Health and Public Protection Policy Development and Review Panel at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.