Fareham Borough Council
Executive, Monday 6 February 2017 at 6.00pm

Solent Airport - Refurbishment of Control Tower/Provision of Corporate Facilities

Agreed Executive 1 paper

Executive agreed this item on Monday 6 February 2017. Below is the council's own wording, with the papers it was decided on.

Item10(3)

Resolved

RESOLVED that the Executive:- (a) agrees to the inclusion of the following schemes in the 2017/18 capital programme: · Refurbishment of the control tower at an indicative cost of £333,000; and · Provision of fuelling equipment and infrastructure at an indicative cost of £250,000; (b) delegates authority to the Director of Finance and Resources, following consultation with the Executive Leader, to award the contracts for the refurbishment of the control tower, subject to the cost being within the allocated budget. (c) delegates authority to the Director of Finance and Resources, following consultation with the Deputy Leader, to finalise detailed arrangements for the procurement of fuelling equipment, subject to the cost being within allocated budget; and (d) agrees that the north end of the building be painted white in order to improve its appearance.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 06 February 2017

Portfolio: Policy and Resources

Subject: Solent Airport – Refurbishment of the Control Tower and Provision of Fuelling Facilities Report of: Director of Finance and Resources

Strategy/Policy: Corporate Strategy To maintain and extend prosperity. Corporate Objective: A dynamic, Prudent and Progressive Council.

Purpose: The purpose of this report is to seek approval to undertake improvements to the internal element of the Control Tower at Solent Airport Daedalus, and to improve the provision of fuelling facilities.

Executive summary: The control tower at Daedalus is an important piece of infrastructure, providing air traffic facilities for the operational team, office space for commercial tenants, meeting facilities and being adjacent to the parking apron for visiting aircraft. However, parts of the tower are in a poor state of repair and consequently it is significantly under-utilised.

A survey has identified the works that are required to bring large parts of the tower back into use, and to bring other elements, such as heating systems, up to a modern standard.

It is proposed to carry out the refurbishment of the control tower in two phases with phase one aimed at providing an open plan seating area and operational WCs prior to the Daedalus 100 anniversary celebrations, with phase two providing a complete refurbishment of the ground floor, installation of a gas supply and heating system and an enlarged car park for completion by Spring 2018.

The report also sets out proposals to install equipment for aviation fuel supplies at the airport. Fuel arrangements are an essential part of airfield infrastructure, and are required to support business continuity and short to long term growth plans for the airfield. Recommendation: That the Executive:

(a) agrees to the inclusion of the following schemes in the 2017/18 capital programme:  Refurbishment of the control tower at an indicative cost of £330,000; and  Provision of fuelling equipment and infrastructure at an indicative cost of £250,000;

(b) delegates authority to the Director of Finance and Resources, following consultation with the Executive Leader, to award the contracts for the refurbishment of the control tower, subject to the cost being within the allocated budget. (c) delegates authority to the Director of Finance and Resources, following consultation with the Deputy Leader, to finalise detailed arrangements for the procurement of fuelling equipment, subject to the cost being within the allocated budget.

Reason: To enable the delivery of the Vision for Daedalus to continue.

Cost of proposals: The estimated cost of the projects is £580,000, to be funded from capital receipts arising from the plot disposals at Daedalus.

Appendices: None

Background papers: None

Reference papers: “Daedalus: A Vision and Outline Strategy” document Executive Briefing Paper Date: 06 February 2017 Subject: Solent Airport – Refurbishment of the Control Tower/Provision of Corporate Facilities Briefing by: Director of Finance and Resources Portfolio: Policy and Resources

INTRODUCTION

1. In April 2016, the Executive considered a report providing an update on the Council’s capital investment project at Daedalus. In addition to providing an update on three approved capital projects, the Executive was advised of a number of other projects that were planned for the future to further implement the Councils vision for the airfield.

2. This report presents the plans to improve the provision of facilities for visitors and to help attract more corporate aviation and recommends that the capital budget for these works be approved.

PROVISION OF FACILITIES FOR VISITORS

3. The current facilities for visitors to the airport are limited to an outside catering concession with an external seating area and limited access to the WC facilities within the control tower.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Solent Airport: Refurbishment of Control Tower/Provision of Corporate FacilitiesReport 182 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 23 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present
SB
Councillor Susan BellCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
TH
Councillor Tiffany HarperCommittee Member, present
KM
Councillor Kay MandryCommittee Member, present
BB
Councillor Brian BayfordGuest, in attendance
SB
Councillor Susan BayfordGuest, in attendance
MF
Councillor Michael Ford, JPGuest, in attendance
AM
Councillor Arthur MandryGuest, in attendance
SP
Councillor Sarah PankhurstGuest, in attendance
NW
Councillor Nick WalkerGuest, in attendance

All 23 on the meeting page

On this subject at Fareham

Search all
  1. Solent Airport - Refurbishment of Control Tower/Provision of Corporate FacilitiesThis decision
  2. Award of contract for Airfield Operator and approval of pavement repairs at Solent Airport, DaedalusAgreed
  3. Operator Contract - Solent AirportDecided
  4. Capital Investment at Solent Airport - PVC aeroplane storage unitsAgreed
  5. Solent Airport Annual Operator ReportNoted
  6. Presentation - Solent Airport Carbon Reduction PlanNoted

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies