Fareham Innovation Centre Phase 2 - Acceptance of Stage 2 Tender

Agreed Executive 1 paper

Executive agreed this item on Monday 5 June 2017. Below is the council's own wording, with the papers it was decided on.

Item10(1)

Resolved

RESOLVED that the Executive agrees:- (a) that the second stage tender submitted by Morgan Sindall Construction in the sum of £6,913,157 be accepted; and (b) that the capital budget for the scheme be increased to £7,072,000.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Report to the Executive for Decision 05 June 2017 Portfolio: Policy and Resources

Subject: Fareham Innovation Centre Phase 2 - Acceptance of Stage 2 Tender Report of: Director of Finance and Resources

Strategy/Policy: Corporate Strategy To maintain and extend prosperity Corporate Objective: A dynamic, prudent and progressive Council

Purpose: To award the contract for Stage 2 of a Design And Build scheme for the construction of Fareham Innovation Centre Phase 2

Executive summary: Due to the success of Fareham Innovation Centre, in June 2016, the Executive agreed to develop a second phase. A new scheme adjacent to and linked with the existing building was designed, planning consent was granted and tenders were invited using the Southern Construction Framework.

Under this Framework, the tender process is in two stages and in February 2017 a Stage 1 tender was accepted for the pre-construction phase from Morgan Sindall Construction.

Since then, Morgan Sindall has progressed through the detailed technical design stage and carried out pre-construction enabling works on the site and have now submitted a Stage 2 tender for the construction work.

When the extension was originally considered, a budget was agreed for a building of 3,000m2, and authority was granted to the Director of Finance and Resources to accept a tender if it was within the capital budget. The detailed design has been completed and this has resulted in the building totalling 3,400m2, some 13% larger than envisaged at the time of the Executive report, and consequently the total project costs have risen by 7% from £6.6m to £7.071m. These costs are still within the Cost Plan developed by the Council's cost consultants as the design progressed.

The scheme was the subject of a funding bid to the Solent Local Enterprise Partnership under the Government's Local Growth Deals scheme. This was successful and has resulted in a funding contribution of £2m towards the total cost. Accordingly, the authority of the Executive is sought to accept the tender.

Recommendation: That the Executive agrees:

(a) that the second stage tender submitted by Morgan Sindall Construction in the sum of £6,913,157 be accepted; and

(b) that the capital budget for the scheme be increased to £7,072,000.

Reason: This represents good value for money and is within the Cost Plan developed by the Council's cost consultants at the time tenders were invited.

Cost of proposals: The total cost of the scheme is £7.071m which can be met from within the revised capital budget and is defrayed in part by a funding contribution of £2m from the Solent Local Enterprise Partnership under the Local Growth Deals scheme.

Confidential Appendix A: Tender report from cost consultants, Baqus

Background papers: None

Reference papers: Report to the Executive 6th June 2016

Confidential report to Director of Finance and Resources for decision - 15th February 2017

Full Business Case in support of a funding application to the Solent Local Enterprise Partnership Executive Briefing Paper Date: 05 June 2017 Subject: Fareham Innovation Centre Phase 2 - Acceptance of Stage 2 Tender Briefing by: Director of Finance and Resources Portfolio: Policy and Resources

INTRODUCTION

1. Fareham Innovation Centre has been remarkably successful. It was fully occupied well ahead of schedule and within 10 months of completion and there is now a waiting list of 20 businesses requesting space within the Centre, together with a number of existing businesses needing space to expand.

2. Due to this success, the Executive agreed on 6 th June 2016 to develop a second phase at an estimated cost of £6.6m and granted authority to proceed with pre-construction design works. Accordingly, architects, M&E consultants, Structural and Civil Engineering consultants, Construction Project Management and Cost consultants were appointed to develop the scheme up to tender stage.

INNOVATION CENTRE PHASE 2

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Fareham Innovation Centre Phase 2: Acceptance of Stage 2 TenderReport 47 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present
KM
Councillor Kay MandryCommittee Member, present
SB
Councillor Susan BellCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
TH
Councillor Tiffany HarperCommittee Member, present
LU
Leigh UsherCommittee Officer, expected
SW
Samantha WightmanCommittee Officer, expected
RI
Richard IvoryOfficer, expected
SB
Councillor Susan BayfordGuest, in attendance
PB
Councillor Pamela BryantGuest, in attendance
MF
Councillor Michael Ford, JPGuest, in attendance

All 19 on the meeting page

On this subject at Fareham

Search all
  1. Fareham Innovation Centre Phase 2 - Acceptance of Stage 2 TenderThis decision
  2. Fareham Innovation Centre - Electric Vehicle Charging InfrastructureApproved
  3. Award of Contract for Operator at Fareham Innovation Centre, DaedalusAgreed
  4. Fareham Innovation Centre - Annual Operator ReportNoted
  5. Presentation - Fareham Innovation Centre - Procurement of Future OperatorDecided
  6. Fareham Innovation Centre: 2022-2023 Annual ReportDecided

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies