RESOLVED that the Executive approves: (a) the Final Regeneration Vision for the Portchester Village Centre as set out in Appendix A of the report for publication; (b) that the Director of Planning and Regulation be authorised to make any necessary minor changes to the Final Regeneration Vision for Portchester, providing that these do not change the overall direction, shape or emphasis of the document, prior to the document being published on the Council’s website; (c) that a further report be presented to a future meeting of the Executive giving details of opportunities to change parking arrangements in the Council’s car parks to the south of the village centre; and (d) that officers seek further updated advice on the existing retail health of the village centre and its future commercial prospects.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Portchester Village Centre: Final Regeneration Vision Subject: for Publication
Report of: Director of Planning and Regulation
Strategy/Policy: Local Plan Review Protecting and Enhancing our Environment Corporate Objective: Maintaining and Extending Prosperity A Balanced Housing Market
Purpose: To consider and approve the Final Regeneration Vision for Portchester Village Centre (set out in AppendixMaintaining A). and Extending Prosperity
Executive summary: The Report briefly outlines the public consultation undertaken as part of the Council’s Draft Regeneration Vision for Portchester Village Centre. This report sets out key changes to the Draft Vision which have emerged from this public consultation. The Final Vision therefore sets out the Council’s ambitions for regenerating the village centre of Portchester which takes on board the views and issues expressed by the local community, and how, working with key partners, the Authority and key parties we are able to improve the village centre.
Recommendation: It is recommended that the Executive approves:
(a) the Final Regeneration Vision for Portchester Village Centre as set out in Appendix A for publication; and
(b) approves that the Director of Planning and Regulation be authorised to make any necessary minor changes to the Final Regeneration Vision for Portchester, providing that these do not change the overall direction, shape or emphasis of the document, prior to the document being published on the Council’s website. Reason: To encourage and actively promote the regeneration of Portchester Village Centre, encouraging future investment and funding for its future prosperity.
Cost of proposals: The costs involved in producing the Final Vision are met from within existing operational budgets.
Potential capital costs for individual initiatives outlined in the Final Vision will be subject to future Executive Reports that will consider and recommend how these will be implemented and funded.
Appendices: A: Final Regeneration Vision for Portchester Village Centre entitled ‘Putting the Village Back in Portchester’.
B: Summary of Consultation.
Background papers: None.
Reference papers: None. Executive Briefing Paper
Date: 10 July 2017
Subject: Portchester Village Centre: Final Regeneration Vision for Publication
Briefing by: Director of Planning and Regulation
Portfolio: Planning and Development
INTRODUCTION
1. This Executive Report outlines the background to the attached document, the Final Regeneration Vision for Portchester Village Centre, which has been developed through the Portchester Regeneration Members’ Working Group and is based on the Draft Regeneration Vision for Portchester Village Centre. It also explains how in late January through to early March 2017 the Council undertook extensive public consultation on the Draft Regeneration Vision for Portchester Village Centre. The report also includes a brief summary of the key outcomes from this public consultation and how these have been incorporated into the Final Regeneration Vision for Portchester Village Centre. The main purpose of this Executive Report is to recommend that the Council agree the finalisation of this corporate document, the Final Regeneration Vision for Portchester.
DEVELOPMENT OF THE DRAFT REGENERATION VISION FOR PORTCHESTER
2. On 08 February 2016, an Executive report established the Portchester Regeneration Members’ Working Group to be chaired by the Executive Member for Planning and Development. The purpose of the Members’ Working Group was to develop a Corporate vision document which focused on opportunities to improve and enhance Portchester Village Centre.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.