IFA2 Technical Feasibility Update

Agreed Executive 6 papers

Executive agreed this item on Monday 4 December 2017. Below is the council's own wording, with the papers it was decided on.

Item9(2)

Resolved

RESOLVED that the Executive:- (a) notes the progress made in relation to the technical assessment and design of the IFA2 project, and the conclusions of the independent technical assessments undertaken; (b) agrees in principle that the necessary technical assurance has been obtained to enable National Grid to proceed to the next stage of construction, provided that extended arrangements are put in place to provide ongoing safeguards to the Council during and following the construction stage; (c) confirms that the Option can be exercised by National Grid, once legally binding amendments to the legal documentation are in place and the construction lease granted, to enable IFA2 to proceed to the construction stage in accordance with the target programme; and (d) delegates authority to the Director of Finance and Resources, following consultation with the Executive Leader, to conclude the revisions to the legal documentation.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Recommendation

It is recommended that the Executive;

a) notes the progress made in relation to the technical assessment and design of the IFA2 project, and the conclusions of the independent technical assessments undertaken;

b) agrees in principle that the necessary technical assurance has been obtained to enable National Grid to proceed to the next stage of construction, provided that extended arrangements are put in place to provide ongoing safeguards to the Council during and following the construction stage;

c) confirms that the Option can be exercised by National Grid, once legally binding amendments to the legal documentation are in place and the construction lease granted, to enable IFA2 to proceed to the construction stage in accordance with the target programme; and

d) delegates authority to the Director of Finance and Resources, following consultation with the Executive Leader, to conclude the revisions to the legal documentation;

Reason: To enable the IFA2 development to proceed to the construction stage and secure all necessary assurances on the technical compatibility of the development.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
App A Part 1 Arcadis Safety Justification Final (2)Appendix 2.3 MB Download
PDF
App A Part 2 Arcadis Hazard Log Final (2)Appendix 1.8 MB Download
PDF
App A Part 3 Arcadis Technical Assessment final (2)Appendix 5.2 MB Download
PDF
App A Part 4 Arcadis Wind Assessment Report_Final (2)Appendix 6.4 MB Download
PDF
App B Key Supporting Documents List (2)Appendix 203 KB Download
PDF
IFA2 Technical Feasibility UpdateReport 123 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 15 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present
KM
Councillor Kay MandryCommittee Member, present
SB
Councillor Susan BellCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
TH
Councillor Tiffany HarperCommittee Member, present
LU
Leigh UsherCommittee Officer, expected
SW
Samantha WightmanCommittee Officer, expected
RI
Richard IvoryOfficer, expected
SB
Councillor Susan BayfordGuest, in attendance
PB
Councillor Pamela BryantGuest, in attendance
PD
Paul DoranOfficer, expected

All 15 on the meeting page

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies