Planning and Development Policy Development and Review Panel agreed this item on Tuesday 13 March 2018. Below is the council's own wording, with the papers it was decided on.
It was AGREED that the Panel: - (a) review the AMR for 2016/17, as set out in Appendix A; following which the Council will publish the report on the Council’s website; and (b) give authorisation to the Director of Planning and Regulation to make any necessary minor changes to the AMR 2016/17, prior to publication, providing that these do not change the overall direction, shape or emphasis of the document, and do not raise any significant issues.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to Planning and Development Policy Development and Review Panel
Fareham Borough Council
Authority Monitoring Report 2016/17
b Overview 1 - Provides information on the 2016/17 monitoring period
2 - More recent data and information included where relevant and appropriate
3 - Key contents of the AMR (Section 1 – Introduction)
4 - AMR doesn’t alter any of the Council’s policies or strategies
b Section 2 - Delivery and Implementation 1 - Local Development Scheme Updated in July 2017
2 - Draft Local Plan published in October 2017 – milestone within July 2017 LDS met
3 - Future milestone targets for the July 2017 LDS also set out
4 - Transition from current to future Local Plan
5 - Planning Obligations SPD adopted in April 2016
b Section 3 - Local Plan Policy Analysis 1 - No changes or nullifications to existing Local Plan policies since last AMR
2 - Preparation and publication of the Draft Local Plan has enabled Officers to review the effectiveness of existing policies
3 - Further review of Draft Local Plan policies to be undertaken as the Plan is further progressed
b Section 4 - Housing Delivery 1 - 349 net housing completions in 2016/17 (1,859 net completions since 2011/12)
2 - 98 out of 349 net housing completions were for affordable housing
3 – Housing figures currently based on Objectively Assessed Need (OAN)*
4 - Five Year Housing Land Supply (5YHLS)
5 - Council’s Self-build (Custom) Register
b Section 4 – Housing Delivery
b Section 5 - Neighbourhood Planning
1 - Titchfield Neighbourhood Area and Forum designated on 20th March 2017
2 - Titchfield Neighbourhood Forum is gathering evidence towards drafting a Neighbourhood Plan
3 - Council will continue to support and give advice to the Forum in progressing the Neighbourhood Plan
b Section 6 - Community Infrastructure Levy (CIL) 1 - Council required to report on the following on CIL
- Amount of CIL receipts collected over 2016/17 – £1,062,835 - Amount of CIL expenditure for 2016/17 – £370,476
- Items of infrastructure to which CIL has been applied in 2016/17 – Hill Head Coastal Protection works (£258,075) / installation of new bus shelters (£112,401)
- Total amount of CIL receipts retained at the end of the financial year - £692,359
- CIL balance as at 31 March 2017 - £1,687,364
b Section 7 - Duty to Cooperate 1 - Very important part of the Plan making process
2 - Council involved in collaborative working on the PUSH Spatial Position Statement (June 2016)
3 - PUSH Spatial Position Statement subsequently informed the Council’s proposed development strategy within the Fareham Draft Local Plan 2036 (October 2017)
4 - Engagement undertaken with a range of statutory bodies and organisations in preparing the development strategy of the Draft Local Plan 2036 (October 2017) 5 - Further information on Duty to Cooperate is included in the Council’s Duty to Cooperate Interim Statement (October 2017)
b 8 – Employment Floorspace Delivery 1 - 7,295 sq.m of net employment floorspace completions in 2016/17
2 - No employment floorspace losses over the 2016/17 monitoring period
3 - 70,378 sq.m of employment floorspace with outstanding planning permission
4 - Employment floorspace requirement currently based on PUSH objectively assessed need
b 8 – Employment Floorspace Delivery
b 9 – Retail and Leisure Floorspace Delivery 1 - 2,811 square metres of net retail floorspace completions in 2016/17
2 - Small loss in retail completions 3 - Retail health check shows a 5.5% vacancy rate in Fareham Town Centre in June 2017 (up 2.6% year on year from June 2016)
4 - Small increase in vacancies recorded for Portchester Local Centre and Park Gate Local Centre in June 2017
5 - No vacancies recorded for Locks Heath District Centre in June 2017
6 - 4,078 square metres of leisure floorspace completions in 2016/17
b 9 - Retail and Leisure Floorspace Delivery
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Planning and Development Policy Development and Review Panel at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
Introduction to Portfolio ServicesIt was AGREED that: (a) the Director of Planning and Regulation and three members of his team; Adam Collier - Princip...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.