RESOLVED that the Executive: (a) agrees that the contract award and appointment of contractor(s) for the Hampshire Rose and Bridge Road development sites be delegated to the Director of Finance and Resources, following consultation with the Executive Member for Housing. (b) notes the on-going progress with Fareham Housing led potential development opportunities; and (c) notes the funding mechanisms available for the delivery of further sites.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 03 December 2018
Housing/ Portfolio: Policy and Resources
Subject: Fareham Housing Development Sites
Managing Director of Fareham Housing/ Report of: Director of Finance & Resources
Corporate Priorities: Providing housing choices
Purpose: To seek approval of the process toward appointment of contractors for the construction of new affordable homes at the Bridge Road and Hampshire Rose sites. To also advise the Executive of the envisaged funding arrangements for these sites and other Fareham Housing led potential development opportunities.
Executive summary: The attached report provides Members with an update on eight potential development sites either to be used for, or currently being considered for, affordable housing provision.
It seeks Executive approval for delegated authority that will allow a time efficient appointment of an appropriate contractor to build out the Hampshire Rose (i.e. 96 Highlands Road) and Bridge Road sites.
The report also seeks to update Members on the current position with other potential development sites and to provide an overview of the funding available. This includes matters relating to the removal of the borrowing cap on the Housing Revenue Account. Recommendation/Recommended Option: It is recommended that the Executive:
(a) agrees that the contract award and appointment of contractor(s) for the Hampshire Rose and Bridge Road development sites be delegated to the Director of Finance and Resources, following consultation with the Executive Member for Housing;
(b) notes the on-going progress with Fareham Housing led potential development opportunities; and
(c) notes the funding mechanisms available for the delivery of further sites.
Reason: To enable the time efficient delivery of affordable housing at the Hampshire Rose (96 Highlands Road) and Bridge Road sites and to update Members of progress with other sites, including the funding mechanisms available.
Cost of proposals: The total estimated cost of the Hampshire Rose and Bridge Road sites is £4.6million. Grant funding from Homes England could cover approximately £800,000 of the costs (subject to bid approval). The remaining cost to deliver these two sites will be met through funds available in the Housing Revenue Account Capital Development Fund.
The further sites (Tranche 2 and Tranche 3) are expected to cost in the region of £13million combined. This will be funded through a varied combination of (a) Housing Revenue Account Capital Development Fund; (b) relevant Section 106 monies; (c) Right to Buy receipts; (d) Homes England grant funding; and/or (e) additional borrowing on the Housing Revenue Account.
Appendices: A: Site Location Plans for Hampshire Rose and Bridge Road B: Site Location Plans for other potential development sites
Background papers: None.
Reference papers: Corporate Strategy 2017-2023 Executive Briefing Paper Date: 03 December 2018 Subject: Fareham Housing Development Sites Briefing by: Managing Director of Fareham Housing/ Director of Finance and Resources Portfolio: Housing/ Policy and Resources
INTRODUCTION
1. During 2018 and since the creation of Fareham Housing in 2017 there has been increased cross-department focus on progressing several potential development sites for affordable housing purposes. This will contribute to the Corporate Strategy 2017- 2023 of ‘Providing Housing Choices’.
2. There are currently eight individual sites that Fareham Housing are progressing or considering. The principal objective is to increase the provision of affordable homes, particularly for those in greatest need.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.