This report considers the potential to develop a railway station at Welborne Garden Village and the Council’s role in that process.
It is recommended that the Panel consider the report and make any comments or raise any questions for clarification. INTRODUCTION
1. The Welborne Plan (2015) encourages the development of a railway station to serve the planned new community.
2. The Portsmouth to Eastleigh railway line passes the western edge of the Welborne site with the nearest station at Fareham, some 2 miles to the south of Welborne by the existing road network. This route is currently single track and the opportunities to develop a new station on this line to serve Welborne directly were considered to be limited at the time of the Welborne Plan, due to line access, single track operation, level changes and proximity to the existing Fareham Station. However, the potential and benefits for a railway station serving Welborne were recognised in the Welborne Plan and, as a result, the concept masterplan allows for it and Policy WEL42 states:
“Outline planning applications for the west of the site (north of Funtley) will need to accommodate the future provision of a new rail halt on the Fareham to Eastleigh rail line unless it is demonstrated that it is not technically feasible or viable to deliver this before the end of the Plan period.”
3. The Outline Planning Application P/17/0266/OA, submitted in March 2017 and refreshed in December 2018, makes provision for a site for a new railway station. In addition, a key feature of the applicant’s Transport Strategy for Welborne is to encourage sustainable transport choices, reflecting the aspirations of the Welborne Plan.
DEMONSTRATING FEASIBILITY
4. A railway station at Welborne is part of the Council’s vision for a well-connected thriving new community and could deliver strong employment and social benefits to the new community. In November 2017, the Council commissioned an initial feasibility study on a new railway station at Welborne, which was carried out by Network Rail.
5. The key aim of the study was to investigate the feasibility of providing a new railway station on the Eastleigh to Fareham line (also known as the Botley line) to identify potential locations that enable the Welborne development to be connected to the railway network.
6. The Eastleigh to Fareham line is approximately 9 miles long and it is proposed that a new station could be located on a 4 mile stretch of single line. It is anticipated that the proposed station would be implemented in two phases as demand is generated by the new community:
Phase 1 would include a single station platform serving the current single line.
In Phase 2 the single line section would be double tracked and two platforms would serve the station
7. The station would be a category F station in accordance with written guidance from the Department for Transport. This is classified as a non-staffed station and, as there is no mandatory requirement for a station building, a platform shelter, seating and information helpline facilities are proposed.
8. Initial stage cost estimates are between £19M for Phase 1 and £78M for both Phases. These costs are loaded with 66% risk to create a worst-case financial scenario. Network Rail has a prescribed 8-stage GRIP (Governance for Railway Investment Projects) process. As the project progresses through each stage, risk is reduced and a more refined assessment of the costs will be possible. The final cost of the Phase One station at Welborne has been estimated at between £12M and £15M once risk is eliminated through the GRIP process.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Welborne Railway StationReport | 167 KB | DownloadRead as text |
Follow Planning and Development Scrutiny Panel at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 4 Mar 2025 | Opportunities Plan UpdateRESOLVED that the Policy and Development Scrutiny Panel: (a) notes the contents of the verbal update; and (b) request... | Decided | Open |
| 4 Mar 2025 | Local Development SchemeRESOLVED that the Planning and Development Scrutiny Panel: - a) notes the contents of the Executive report and draft ... | Decided | Open |
| 4 Mar 2025 | Planning and Development Scrutiny Panel PrioritiesRESOLVED that the Panel considered the scrutiny priorities. | Decided | Open |
| 6 Nov 2024 | Infrastructure Funding StatementRESOLVED that the Planning and Development Scrutiny Panel note the contents of the at Appendix A | Noted | Open |
| 6 Nov 2024 | Authority Monitoring ReportRESOLVED that the Planning and Development Scrutiny Panel note the contents of the at Appendix A | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.