RESOLVED that in accordance with the Local Government Act 1972 the public and Press be excluded from this section of the meeting on the grounds that the matters to be dealt with involve the likely disclosure of exempt information, as defined in Paragraph 1 and 3 of Part 1 of Schedule 12A of the Local Government Act 1972. Following discussion of the information contained in the confidential Appendix to the report, the meeting moved back into public session. RESOLVED that the Executive awards a contract to the contractor achieving the highest scoring tender based on cost/quality/service as detailed in the confidential Appendix to the report.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 04 February 2019
Portfolio: Housing Void Property Works and Component Improvement Subject: Package Works Contract 2019 to 2022 Report of: Managing Director of Fareham Housing
Corporate Priority: Dynamic, prudent and progressive Council
Purpose: To consider the tenders received and to award a contract for the provision of void property works and component improvement package works to council properties.
Executive summary: This report provides the Executive with information on the Council’s obligation to maintain its properties to a lettable standard and provide improvements. It provides details on a new contract to provide void property maintenance and component improvement works on a 3-year term, with option to extend for a further 2 years.
Recommendation: It is recommended that the Executive awards a contract to the contractor achieving the highest scoring tender based on cost/quality/service as detailed in confidential Appendix A to this report.
Reason: To ensure void repair works are delivered to the lettable standard effectively and efficiently. To provide improvements and disabled adaptations to occupied properties effectively and efficiently. To provide additional support to deliver responsive repairs. Cost of proposals: The costs of these proposals are outlined in confidential Appendix A to this report. They will be met from existing Housing Revenue Account budgets
Appendices: Confidential Appendix A: Summary of tender evaluation Confidential Appendix B: Detailed tender evaluation process Executive Briefing Paper
Date: 04 February 2019 Subject: Void Property Works and Component Improvement Package Works Contract 2019 to 2022 Briefing by: Managing Director of Fareham Housing Portfolio: Housing
INTRODUCTION
1. Fareham Borough Council’s Housing stock will have an average of 215 empty properties a year, these are referred to as voids. The reasons for properties becoming void are due to terminations of tenancy, death of tenants and repossessions. As a landlord, the Council has a legal responsibility to maintain the properties to a lettable standard prior to re-occupation.
2. Void works are delivered in conjunction with the incoming tenants to ensure the property is right for the person. This bespoke approach to the works statistically show that it prevents future demand on the maintenance service.
3. Fareham Housing also provides kitchen and bathroom modernisations to its stock. The demand comes either direct from tenants who feel that an upgrade is due or via the Responsive Repairs operatives who determine that components are beyond economical repair.
4. Fareham Housing provide disabled adaptations to its stock. The demand comes either direct from tenants or via Hampshire County Council’s Occupational Therapy Departments. Minor adaptations are undertaken by Responsive Repairs operatives.
5. The works on this contract include:
All aspects of void repairs and improvements.
Component improvement package works and disabled adaptations to occupied properties, which include kitchens, bathroom, wet-rooms, over the bath showers, ramps, handrails, etc.
Occasional responsive repairs.
6. This new contract will be for an initial period of three years with the option to extend the contract by a further two years subject to satisfactory performance. TENDER PROCESS
7. A ’contract notice’ was issued on the 4th July 2018 in accordance with Publication of Supplement to the Official Journal of the European Union (OJEU) and available on the Tenders Electronic Daily website (TED).
8. A Restricted OJEU procurement process was used that included a two-stage process; Stage 1 is the pre-qualification section whereby eligible candidates are invited to tender in Stage 2. Those candidates who fail the Stage 1 are rejected from the process. 21 expressions of interest were received and assessed for suitability. A select list of 6 contractors were chosen to be invited to tender.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.