This report provides the Policy and Resources Review Panel with an update on the financial outturn of the General Fund Capital Programme for 2018/19. Actual spend was £3,544,468 compared with the revised capital programme of £10,085,700. The overall variance was £6,541,232 and a detailed analysis of the variations is given in Appendix A to this report.
Total savings of £46,675 were achieved, additional expenditure of £342,178 was incurred and a total of £6,836,735 will be carried forward into 2019/20. Details of the various methods used to finance this expenditure are set out in this report.
That any comments from the Panel be referred to the Executive at its meeting on 1 July 2019. INTRODUCTION
1. This report provides the Policy and Resources Scrutiny Panel with details of the capital outturn for 2018/19.
CAPITAL OUTTURN REPORT 2018/19
2. The capital programme for 2018/19, approved in February this year for the General Fund was £10,085,700. The actual capital expenditure, detailed in Appendix A, was £3,544,468 giving an overall variation of £6,541,232. A summary, including savings and additional expenditure, is summarised in the table below.
Revised Additional Carry Budget Actual Savings Expenditure forward £ £ £ £ £ Health & Public Protection 100,000 48,516 41,484 0 10,000 Streetscene 107,000 110,056 0 0 (3,056) Planning & Development 63,300 71,966 0 27,580 18,914 Leisure & Community 348,000 315,356 114 15,942 48,472 Housing 1,097,600 854,646 0 6,934 249,888 Policy & Resources 8,369,800 2,143,928 5,077 291,722 6,512,517 Total 10,085,700 3,544,468 46,675 342,178 6,836,735
SAVINGS AND ADDITIONAL EXPENDITURE
3. Total savings of £46,675 were recognised. The main scheme saving was £41,484 for the Night Time Closure of Multi-Storey Car Parks as works to install shutters and barriers were lower than anticipated. It is proposed that a budget of £10,000 will be carried forward to fund works to deal with pigeon issues at Osborn Road Multi-Storey Car Park.
4. The main schemes where additional expenditure of £342,178 was incurred were:
Hill Head Coastal Protection Phase 2- increased spend of £27,580 for additional paving works funded by Community Infrastructure Levy contributions.
Westbury Manor Museum Remodelling- £7,351 additional costs for refurbishment of the toilet area.
Town Centre Christmas Lights - £8,575 installation costs which were budgeted in revenue and funded by town centre contributions.
Fareham Innovation Centre Phase 2 - additional fit out costs contributed to an overspend of £284,262 on this scheme.
5. In addition, £13,811 of expenditure was incurred ahead of budget and will be carried forward to reduce next year’s capital budget.
CARRY FORWARDS TO 2019/20
6. There are a number of schemes still in progress and a total budget of £6,826,735 will be carried forward to 2019/20.
7. The largest carry forward is for the Commercial Property Acquisition of £5,110,000 which was purchased in April 2019 along with £1,095,196 carry forwards for schemes at Solent Airport.
CAPITAL PROGRAMME 2019/20 TO 2023/24
8. The General Fund capital programme will be reviewed by officers in light of the slippage and re-phasing of works and an updated programme for 2019/20 to 2023/24 will be presented to the Executive as part of the Finance Strategy for 2020/21.
CAPITAL FINANCING
9. The various methods used to finance the capital expenditure in 2018/19 are set out in the chart below.
[CATEGORY Capital Financing NAME] [VALUE]m [CATEGORY [PERCENTAGE] NAME] [VALUE]m [PERCENTAGE]
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Capital Programme Outturn 2018/19Report | 322 KB | DownloadRead as text |
Follow Policy and Resources Scrutiny Panel at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 17 Mar 2025 | Update on the Council's Unreasonable Behaviour PolicyRESOLVED that the Panel: - (i) notes the content of the draft Unreasonable Complainant Behaviour Policy; and (ii) rec... | Decided | Open |
| 17 Mar 2025 | Recognising and Celebrating DiversityRESOLVED that the Panel note the content of the report. | Noted | Open |
| 12 Feb 2025 | Fareham Town Centre Regeneration StrategyRESOLVED that the Panel: - (i) notes the content of the report and presentation; and (ii) recommends that the Executi... | Decided | Open |
| 12 Feb 2025 | Updated Budgets & Council Tax 2025-26RESOLVED that the Panel: - (i) notes the content of the report; and (ii) recommends that the Executive endorses the r... | Decided | Open |
| 10 Jan 2025 | Capital Programme & Capital Strategy 2025-26RESOLVED that the Panel: - (a) notes the content of the report; (b) recommends that the Executive endorses the Capita... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.