Leisure and Community Scrutiny Panel decided this item on Monday 23 September 2019. Below is the council's own wording, with the papers it was decided on.
RESOLVED that the Leisure and Community Scrutiny Panel considered the contents of the presentation and pass to the Executive their comments that the design should: - (a) have disabled access throughout; (b) ensure carbon neutrality wherever possible; and (c) adequate space and facilities be made available for use by the community.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
The development of a concept design and budget cost that best matches the Council’s agreed vision has been one of the main strands of work in the project to remodel Ferneham Hall into a new community arts venue. A presentation will be given to the Scrutiny Panel on 23 September outlining in detail the concept design and budget cost. The Scrutiny Panel will be asked to comment on the concept design, budget cost and funding arrangements. Their comments will be tabled when the ‘Concept Design and Budget Costs for remodelling Ferneham Hall’ report is presented to the 26 September Executive. At this meeting, the Executive will be asked to approve the concept design, budget cost and the funding of the project through current and future CIL receipts, supplemented by prudential borrowing and external grant funding where available.
Recommendation
Members are now invited to consider the contents of the presentation and pass any comments to the Executive. Leisure and Community Scrutiny Panel Briefing Paper Date: 23 September 2019 Subject: Design and costs for remodelling Ferneham Hall Briefing by: Director of Leisure and Community Portfolio: Leisure and Community
INTRODUCTION
1. This briefing paper presents the background on the ‘Concept Designs and Budget Costs for remodelled Entertainment Venue’ agenda item that will be presented at the Leisure and Community Scrutiny Panel meeting on Monday 23 September.
Background
2. An initial vision to create a new community arts and entertainment venue to replace Ferneham Hall was approved by the Executive in July 2018 and subsequently updated in December 2018 following a consultation. The vision identified a number of design priorities for the venue including
A main auditorium with around A flexible studio space 800 seats to attract better quality shows Improved accessibility
Improved cast/crew areas Community meeting rooms including the stage and backstage, to support high Improved foyer area and box office quality performances Improved audience facilities A secondary performance space of around 100 seats
Concept Design and Budget Costs for remodelling Ferneham Hall
3. Overseen by the Ferneham Hall Project Member Working Group, the development of a concept design and budget cost that best matches the Council’s agreed vision has been one of the main strands of work of the project. 4. Following extensive work, a concept design which best matches the Council’s vision has been developed. The Member Working Group will be asked to approve both the concept design and budget costs on 16 September 2019.
5. If approved, a report regarding the concept design and budget costs will be presented to a special meeting of the Executive on 26 September. The report will:
Give an update on the progress of the project, including an overview of the development of the concept design and budget cost;
Present both the concept design and budget cost for approval; and
Outline the next steps of the project.
6. The Executive will be asked to:
Approve the concept design of the remodelled Ferneham Hall and that this be submitted as part of a planning application;
Approve the budget cost for the remodelling project; and
Approve the funding of the project through current and future CIL receipts, supplemented by prudential borrowing and external grant funding where available.
7. The agenda and accompanying report for the Executive Meeting will be published on Wednesday 18 September.
Leisure and Community Scrutiny Panel
8. At the Scrutiny Panel meeting, Members will receive a presentation providing an overview of the contents of the Executive report, including details of the concept design, budget cost and proposed funding arrangements.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Leisure and Community Projects UpdateRESOLVED that the Leisure and Community Scrutiny Panel note the contents of the report and supporting presentation.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.