RESOLVED that the Executive: (a) agrees the provision of pre-application planning advice based on the service specification set out in Appendix C; (b) notes that the proposed charges for providing pre-application planning advice are exclusive of VAT; (c) recommends the proposed increased charges for providing pre-application planning advice set out at Appendix D to Council for approval as part of the Council’s budget; (d) notes that, subject to the approval of Council as set out in (b) above, the charges will come into effect for all pre-application planning advice requests received on or after the 1 st April 2020; and (e) notes that a further report addressing charges in relation to listed building and heritage assets advice, planning performance agreements and design coding work (as set out within Paragraphs 37 and 46-50 of the Briefing Paper) will be presented to a future meeting of the Executive.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 03 February 2020 Portfolio: Planning and Development Review of the Council’s Pre-Application Planning Subject: Advice Service and Charges Report of: Director of Planning and Regeneration
Corporate Priorities: A dynamic, prudent, progressive and best practice Council
Purpose: To advise the Executive of the outcome of a recent review of the Council’s pre- application planning advice service and charges.
Executive summary: A review of the Council’s pre-application planning advice service has recently been undertaken and found that it was broadly meeting the requirements of customers. The review also established that the Council’s current charges for providing pre- application planning advice, represent only partial recovery of the costs of delivering the service. A proposal is therefore being bought to the Executive to increase the level of charging to provide pre-application planning advice.
Recommendation: It is recommended that the Executive:
(a) agrees the provision of pre-application planning advice based on the service specification set out in Appendix C;
(b) recommends the proposed increased charges for providing pre-application planning advice set out at Appendix D to Council for approval as part of the Council’s budget;
(c) notes that, subject to the approval of Council as set out in (b) above, the charges will come into effect for all pre-application planning advice requests received on or after the 1st April 2020;
(d) notes that a further report addressing charges in relation to listed building and heritage assets advice, planning performance agreements and design coding work (as set out within Paragraphs 37 and 46-50 of the Briefing Paper) will be presented to a future meeting of the Executive. Reason: To ensure that the pre-application service meets the needs of customers. To ensure that a greater proportion of the cost of delivering the pre-application planning advice service is recovered from users of the service, reflecting the Council’s Medium-term Financial Strategy.
Cost of proposals: If the increased charges proposed in the report are implemented in full, the Council will receive additional income and recover a greater proportion of the cost of delivering the pre-application planning advice service.
Appendices: A: Fareham’s current pre-application planning advice charges
B: Comparison of pre-application planning advice charges across Hampshire
C: Proposed pre-application planning advice service specification
D: Proposed pre-application planning advice charges Executive Briefing Paper Date: 03 February 2020 Subject: Review of the Council’s Pre-Application Planning Advice Service and Charges Briefing by: Director of Planning and Regeneration Portfolio: Planning and Development
INTRODUCTION
1. Fareham Borough Council introduced pre-application planning charges in April 2009 for providing advice on many types of development.
2. Providing pre-application planning advice is a discretionary service, but one strongly encouraged by the Government and welcomed by many applicants. Local planning authorities may charge for providing discretionary services under Section 93 of the Local Government Act 2003. Where charges are made, they must not exceed the cost of providing the service.
3. The pre-application charges introduced in 2009 represented partial recovery of the costs associated with the Council providing the advice, rather than full recovery. Annual increases of 5% have been made to the pre-application charges in recent years, but the current charges still do not reflect full cost recovery.
4. Members will be well aware of the considerable spending pressures this Council faces and therefore the importance of recovering costs where it is appropriate and reasonable to do so.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.