Fareham Borough Council
Executive, Monday 7 September 2020 at 6.00pm

Covid 19 Impact on Daedalus Faraday Business Park Investment Project

Agreed Executive 2 papers

Executive agreed this item on Monday 7 September 2020. Below is the council's own wording, with the papers it was decided on.

Item12(3)

Resolved

RESOLVED that following consideration of the potential impact(s) of Covid-19, the Executive agrees: (a) to continue funding of £5 million, as agreed by the Executive on 07 January 2019, to construct new industrial/business units at Faraday Business Park; and (b) the appointment of a contractor for the development is delegated to the Director of Planning and regeneration following consultation with the Executive Member for Policy and Resources.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Executive summary

At the 7 January 2019 Executive it was agreed to fund the construction of new industrial / business units at Faraday Business Park and the appointment of a contractor for the development to be delegated to the relevant Director following consultation with the Executive Member for Policy and Resources.

Recommendation: Following consideration of the potential impact(s) of Covid-19, it is recommended that the Executive agrees:

(a) to continue funding of £5 million, as agreed by the Executive on the 07 January 2019, to construct new industrial/ business units at Faraday Business Park, and

(b) the appointment of a contractor for the development is delegated to the Director of Planning and Regeneration following consultation with the Executive Member for Policy and Resources.

Reason: To fund the further development of Daedalus in line with the adopted Vision generating a positive revenue for the Council.

Cost of proposals: The capital budget for the proposed scheme is as approved on 7 January 2019. Appendices: A: Architect perspective view of development. B: Confidential – Lambert Smith Hampton update addendum to November 2018 report.

Background papers

Reference papers: Daedalus Vision and Outline Strategy. Review of the Council’s Vision and Strategy for Daedalus. Executive Briefing Paper Date: 07 September 2020 Subject: Covid-19 Impact on Daedalus Investment Projects - Faraday Industrial / Business Units Briefing by: Director of Planning and Regeneration Portfolio: Policy and Resources

INTRODUCTION

1. At the 7 January 2019 Executive it was agreed to fund the construction of new industrial / business units at Faraday Business Park and the appointment of a contractor for the development to be delegated to the Director of Finance and Resources following consultation with the Executive Member for Policy and Resources.

2. This proposal was and remains in accordance with the Council’s Vision for Daedalus – to provide a thriving employment led development.

3. Positive revenue generating schemes are required to cross subsidise airside operations and contribute to the Councils revenue income.

4. Since the Executive of the 7 January 2019 the project has been designed, obtained planning consent and the construction contract tendered.

5. It is forecast that the project continues to be deliverable within the original capital budget approved at Executive on 7 January 2019.

6. As a result of the Covid-19 pandemic this paper assesses any implications of Covid-19 on this proposal.

COVID-19 IMPLICATIONS

7. Covid-19 has impacted upon the global economy. The recovery will differ by sector and vary by region.

8. A dedicated report on Covid-19 impact and recovery proposals within the Borough is to be considered at this Executive meeting.

9. In accordance with the August Executive report on Covid -19 recovery Plan Objectives and Framework all major capital schemes are being reviewed. COVID-19 IMPACT ON TENANT MARKET AND DEMAND

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(3)Appendix A 1.8 MB Download
PDF
Covid 19 Impact on Daedalus Faraday Business Park Investment ProjectReport 139 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 20 attended
SW
Councillor Seán WoodwardCommittee Member, present
TC
Councillor Trevor Cartwright, MBECommittee Member, present
FB
Councillor Fred BirkettCommittee Member, present
SB
Councillor Susan BellCommittee Member, present
KE
Councillor Keith EvansCommittee Member, present
SM
Councillor Simon MartinCommittee Member, present
PG
Peter GrimwoodOfficer, expected
RI
Richard IvoryOfficer, expected
RJ
Richard JolleyOfficer, expected
AW
Andrew WannellOfficer, expected
LA
Lindsey AnsellOfficer, expected
SR
Sarah RobinsonOfficer, expected

All 20 on the meeting page

On this subject at Fareham

Search all
  1. Covid 19 Impact on Daedalus Faraday Business Park Investment ProjectThis decision
  2. Impact of Covid-19 Pandemic on the hire of sports pitchesDecided
  3. Update of Covid Impact on Council Finances, including Financial Support to BusinessesNoted
  4. Covid-19 Impact on Housing & Homelessness ServicesDecided
  5. Covid-19 Impact on new Arts and Entertainment Venue ProjectApproved
  6. Community Centres - Covid-19 ImpactDecided

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies