RESOLVED that the Executive: (a) approves the terms of the Memorandum of Understanding with Homes England to help secure the £42m Housing Investment Grant for Welborne Garden Village as attached at the Confidential Appendix A to this report; (b) delegates authority to complete the Memorandum of Understanding to the Director of Planning and Regeneration, following consultation with the Council’s s151 Officer and the Executive Leader of the Council; and (c) requests that the Head of Development Management incorporates these provisions in the legal agreement for Welborne pursuant to Section 106 of the Town and Country Planning Act 1990.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Purpose: To delegate authority to the Director of Planning and Regeneration to enter into a memorandum of understanding between the Council and Homes England in order to help secure £42m Housing Investment Grant (HIG) funding for the M27 Junction 10 Improvement Scheme and unlock 6,000 homes at Welborne Garden Village.
Executive summary: Housing Investment Grant (HIG) funding of £42m is being provided to Hampshire County Council (HCC) to enable the delivery of the M27 Junction 10 Improvement Scheme to unlock 6,000 homes at Welborne Garden Village. Hampshire County Council has agreed to delegate authority to its Director of Economy, Transport and Environment to complete the funding agreements associated with this grant, including a Grant Determination Agreement (GDA) with Homes England for the HIG funding. A simultaneous Memorandum of Understanding between Homes England and this Council is also required to secure the HIG funding. This sets out the obligations on the Council in relation to the monitoring of various s106 requirements on the Developer of Welborne Garden Village; the monitoring of housing outputs unlocked by the HIG-funded infrastructure works; and the recovery and reinvestment into affordable housing of the HIG funds. This report sets out those obligations and seeks Executive approval to enter into a Memorandum of Understanding with Homes England to help secure the £42m grant to HCC. On 23 July 2021, the Planning Committee agreed to delegate to the Head of Development Management the ability to secure a mechanism to recover and recycle HIG Funding in accordance with Homes England’s requirements in a legal agreement pursuant to Section 106 of the Town and Country Planning Act 1990. Recommendations: It is recommended that the Executive:
(a) approves the terms of the Memorandum of Understanding with Homes England to help secure the £42m Housing Investment Grant for Welborne Garden Village as attached at Confidential Appendix A to this report;
(b) delegates authority to complete the Memorandum of Understanding to the Director of Planning and Regeneration, following consultation with the Council’s s151 Officer and the Executive Leader of the Council; and
(c) requests that the Head of Development Management incorporates these provisions in the legal agreement for Welborne pursuant to Section 106 of the Town and Country Planning Act 1990.
Reason: To comply with certain requirements of the Council relating to the Housing Investment Grant (HIG) funding and to help secure the £42M HIG contribution to the M27 Junction 10 Improvement Scheme.
Cost of proposals: There are no additional costs to the Council of this recommendation. Some additional officer capacity may be required to comply with the monitoring, recovery and reinvestment obligations within the Memorandum of Understanding but there is provision in the Welborne Garden Village s106 planning agreement for these costs to be recovered from the Developer.
Confidential Appendix: A: Heads of Terms for Memorandum of Understanding between Homes England and Fareham Borough Council
Background papers: None
Reference papers: Hampshire County Council Cabinet Decision Report M27 Junction 10 Welborne 13 July 2021 Executive Briefing Paper Date: 09 August 2021 Subject: Welborne Garden Village Housing Infrastructure Grant
Briefing by: Director of Planning and Regeneration Portfolio: Policy and Resources
INTRODUCTION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.