Resolved
RESOLVED that the Housing Scrutiny Panel notes the content of the report.
Housing Scrutiny Panel decided this item on Thursday 28 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Housing Scrutiny Panel notes the content of the report.
This report provides an update on the current and emerging Fareham Housing development sites.
It is recommended that the Panel note and consider the content of this report and make any comments or raise any questions for clarification. INTRODUCTION
1. The purpose of this report is to the provide Members of the Panel with an overview and update on the position with the Fareham Housing development sites.
2. The report focuses on sites that have been progressing since 2018, when a Strategic Housing function returned to the Fareham Housing department. An overview of each site is provided.
3. There are 17 sites referred to in this report. The sites vary in scale, property type and tenure. It includes regeneration and redevelopment opportunities as well as smaller schemes designed to meet some of the more bespoke need from the Council’s Housing Register. The sites are listed in approximate order as to their progress/stage toward development.
COMPLETED SITES
4. Oak Tree Close (land at 123 Bridge Road)
5No. houses (2No. 3-bed and 3No. 2-bed) Mix of Social and Affordable Rent Contractor: Ascia Construction Completed in summer 2020 Main funding source: HRA Capital Development Fund & Homes England grant Homes England grant met approximately 25% of the project costs
5. Rose Court (Highlands Road)
18No. flats (8No. 2-bed and 10No. 1-bed) All flats as Social Rent Contractor: FE Chase Ltd. Completed in summer 2021 (6No. flats completed earlier) Main funding source: HRA Capital Development Fund & Homes England grant Homes England grant met approximately 35% of the project costs
IMMINENT STARTS ON SITE
6. The following sites are those where planning permission is in place and a contractor is appointed for the construction. Both sites listed below have been delayed due to the complexity of the process surrounding securing a Section 278 agreement with Hampshire County Council Highways. A Section 278 concerns the alterations and improvements to the public highway. For example kerb positioning; footpath gradients; drainage details, etc.
7. Capella Close (Stubbington Lane)
11No. Houses (2No. 3-bed, 7No. 2-bed and 2No. 1-bed) All houses as Shared Ownership Contractor appointed: FE Chase Ltd. Estimated Start on Site: Nov/Dec 2021 (tbc) Estimated Completion: Spring 2023 Main funding source: Borrowing & Homes England grant Homes England grant to fund 15-20% of the project costs 8. Sir Randal Cremer House (Station Road)
16No. Sheltered Flats (4No. 2-bed, 12No. 1-bed) All flats Sheltered Housing (Affordable Rent) Contractor appointed: Ascia Construction Estimated Start on Site: tbc, subject to S278 agreement with HCC Build Programme: 12-18 months Main funding source: 1-4-1 receipts & charitable contribution Includes a financial contribution from The Randal Cremer Cottages Trust
FORTHCOMING SITES
9. The following sites are being actively worked on. Some are close to a development start and others are at the design stage.
10. Former Coldeast Scout Hut site
9No. flats (4No. 2-bed, 5No. 1-bed) All flats for Shared Ownership Planning Permission granted Main funding source: Borrowing & Home England grant Overview of Progress: Technical/detailed plans have now largely been completed following the grant of planning consent. A Homes England grant application for £387,000 has been submitted. Subject to the tender process development should commence in 2022 with a build programme of 12-18 months.
11. Queens Road (former St Johns Ambulance site)
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Fareham Housing Development Sites UpdateReport | 166 KB | DownloadRead as text |
Follow Housing Scrutiny Panel at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Apr 2025 | Fareham Housing Development Sites UpdateRESOLVED that the Housing Scrutiny Panel notes the content of the presentation. | Decided | Open |
| 3 Apr 2025 | Greener Measures and InstallationsRESOLVED that the Panel notes the content of the report. | Decided | Open |
| 3 Apr 2025 | Analysis of Council Housing Waiting ListRESOLVED that the Housing Scrutiny Panel notes the content of the report. | Decided | Open |
| 3 Apr 2025 | Draft Fareham Housing Battery Powered Mobility Aids PolicyRESOLVED that the Housing Scrutiny Panel: (a) considered the Draft Fareham Housing Battery Powered Mobility Aids Poli... | Approved | Open |
| 3 Apr 2025 | Tenant Satisfaction MeasuresRESOLVED that the Housing Scrutiny Panel notes the content of the report and the performance of Fareham Housing in th... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.