RESOLVED that the Executive: (a) approves the allocation of up to £433,000 from the General Fund Revenue Reserve to establish a capital budget for the urgent significant repair works to the Council’s community buildings, as identified by the Condition Surveys; (b) notes the potential works required to the X- perience building, which will be subject to a separate report; and (c) notes the smaller necessary repairs, totalling £117,000, identified that are the Council’s responsibility as detailed with the Leases held.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 01 November 2021 Portfolio: Leisure and Community
Subject: Review of Community Buildings
Report of: Director of Leisure and Community
Corporate Priorities: Leisure opportunities for health and fun
Purpose: To note the findings of the condition surveys of the Council’s community buildings, understand the costs of necessary maintenance works identified in this process and consider the most appropriate allocation of resources to ensure the long-term maintenance of these important community assets.
Executive summary: The Council owns 16 community buildings that act as a hub for its communities and are well-used for leisure and social activities.
In 2020 each building was surveyed to identify the maintenance to that facility that would be required over the following 5-year period. The findings of the surveys were refined to understand which works were necessary and the responsibility of the Council as detailed in the individual Leases.
The urgent works individually costing over £10,000 that were identified as the responsibility of the Council came to a total of £466,500. In addition, many smaller repairs were also identified that would be required to be carried out over the next 5- year period. These were identified as costing the Council £117,000 in total.
The Executive is asked to allocate funds from the Council’s budget to enable the scheduling of the necessary significant repairs and the smaller revenue works to enable the Council to meet its maintenance responsibilities for its community buildings. Recommendation/Recommended Option: It is recommended that the Executive:
(a) approves the allocation of up to £433,000 from the General Fund Revenue Reserve to establish a capital budget for the urgent significant repair works to the Council’s community buildings, as identified by the Condition Surveys;
(b) notes the potential works required to X-perience building, which will be subject to a separate report; and
(c) notes the smaller necessary repairs, totalling £117,000, identified that are the Council’s responsibility as detailed within the Leases held.
Reason: To ensure the long-term sustainability of the Councils community buildings and to prevent excessive future costly repairs resulting from delayed maintenance.
Cost of proposals: The capital cost of this proposal amounts to £433,000, to be met from the General Fund Revenue Reserve. Smaller repairs and maintenance will be contained within existing budgets.
Appendices: Confidential Appendix A - Summary of Community Buildings Condition Surveys
Background papers: None Executive Briefing Paper Date: 01 November 2021 Subject: Review of Community Buildings
Briefing by: Director of Leisure and Community Portfolio: Leisure and Community
INTRODUCTION
1. The Council owns 16 community buildings, comprising of 10 community centres, 3 youth centres, a scout hut, a scrap store and a museum. Each of these is leased to a charity, trust or community association which oversees how each is run with the help of a committee.
2. The facilities are all unique, with variations in the following factors:
3. Age of the building – Three of the Council’s community facilities originate from buildings first constructed in the 17th century; Crofton Community Centre (originally a school), Westbury Manor Museum (formerly the Council offices) and the Frosthole Scrap Store (designed as an isolation hospital). In comparison, the newest of the community facilities is Portchester Community Centre, which opened in 2012. This building was designed specifically for modern community use, containing a variety of rooms to accommodate the needs of any hirers.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.