Resolved
RESOLVED that the Audit and Governance Committee approved the work programme for the rest of the municipal year, as shown in Appendix A to the report.
Audit and Governance Committee approved this item on Monday 22 November 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Audit and Governance Committee approved the work programme for the rest of the municipal year, as shown in Appendix A to the report.
This report reviews the current work programme for the Committee.
It is recommended that the Audit and Governance Committee approve the work programme for the rest of the municipal year, as shown in Appendix A to this report. INTRODUCTION
1. This report brings the latest work programme for review by the Committee.
WORK PROGRAMME 2021/22
2. The progress on the work programme for the year is shown in Appendix A. This shows the reports expected in relation to each of the functions of the Committee along with an update on the delivery of the programme.
3. There have been a number of changes to the programme approved in the September 2021 meeting.
4. The main change is a delay to the External Audit Results report being ready for publication; albeit the field work has been delivered to the timetable that had been proposed. In order to accommodate the delay, we are planning to have an additional Committee meeting in January and will use this meeting to deal with some slippage and extra items to reduce the workload for the March Committee as follows:
The Annual External Audit Report (including commentary on Value for Money) from Ernst and Young should also be ready for the same meeting.
An additional item will be included to cover the review of the current procedures for investigating Member Code of Conduct complaints.
We have not yet received our 3-yearly RIPA (Regulation of Investigatory Powers Act) inspection report although a virtual inspection by the Investigatory Powers Commissioner’s Office was carried out in November. This report should therefore be available for the January Committee meeting.
Officers have been continuing to review parts of the Constitution as time allowed but the work has not yet been completed. This report should, however, be ready for the January Committee meeting.
5. The last change relates to a delayed piece of work updating the Anti-Bribery Policy, Work on this review has not yet commenced and is unlikely to start any time soon. This item will therefore be postponed until the March Committee.
RISK ASSESSMENT
6. There are no significant risk considerations in relation to this report
CONCLUSION
7. The work programme in place is appropriate to meet the responsibilities of the Committee.
Background Papers: None Reference Papers: Report to the Audit and Governance Committee – 15 March 2021 - Annual Report of the Committee
Enquiries: For further information on this report please contact Elaine Hammell. (Ext 4344) APPENDIX A WORK PROGRAMME FOR 2021/22
Last July Sept Nov Jan March Committee Function and Report Subject Frequency Covered 2021 2021 2021 2022 2022 OVERALL PURPOSE AND ACCOUNTABILITY YES, and Review of Work Programme and training plan Quarterly 2021-22 Completed Completed Completed Annual Report Review of the Functions of the Committee 3 yearly 2019-20
GOVERNANCE, RISK AND CONTROL
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Review of Work ProgrammeReport | 293 KB | DownloadRead as text |
Follow Audit and Governance Committee at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. | Noted | Open |
| 8 Sep 2026 | Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... | Noted | Open |
| 8 Sep 2026 | Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. | Decided | Open |
| 8 Sep 2026 | Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... | Approved | Open |
| 27 Jul 2026 | External Audit - Annual Plan and Fee 2026/27RESOLVED that the Audit and Governance Committee: a) approves the 2025/26 Audit Plan, attached as Appendix A to this ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.