RESOLVED that the Executive recommends that the Council: (a) approves the Community Infrastructure Levy Draft Charging Schedule as set out in Appendix A to the report for public consultation for a period of 6 weeks; (b) agrees that the Director of Planning and Regeneration be authorised to make any necessary minor amendments, following consultation with the Executive Member for Planning and Development, and delegates to him the authority to submit the draft Charging Schedule for Examination; and (c) delegates to the Director of Planning and Regeneration, following consultation with the Executive Member for Planning and Development the authority to procure and appoint an independent examiner to conduct the examination on the draft Charging Schedule.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 06 March 2023 Portfolio: Planning and Development
Subject: Community Infrastructure Levy - Consultation
Report of: Director of Planning and Regeneration
Providing Housing Choices Corporate Protect and Enhance the Environment Priorities: Dynamic, Prudent and Progressive Council
Purpose: To seek approval to the content of a consultation on the Borough’s Community Infrastructure Levy (CIL) draft Charging Schedule.
Executive summary: The Council commissioned Three Dragons to undertake a CIL Review Viability Assessment for the Borough, to determine whether a new CIL rate could be applied without negatively impacting on the delivery of housing and other forms of development associated with the emerging Fareham Local Plan 2037.
Following the conclusion of the assessment, the report recommends new rates for residential and some non-residential uses that align to the evidence collected through the CIL Review Viability Assessment.
This report seeks Executive approval to consult on the attached draft Charging Schedule and the proposed rates therein. Secondly, the report seeks delegated authority to commence the examination process following the consultation.
Recommendation: It is recommended that the Executive recommends that the Council:
(a) approves the Community Infrastructure Levy Draft Charging Schedule as set out in Appendix A to this report for public consultation for a period of 6 weeks; (b) agrees that the Director of Planning and Regeneration be authorised to make any necessary minor amendments, following consultation with the Executive Member for Planning and Development, and delegates to him the authority to submit the draft Charging Schedule for Examination; and
(c) delegates to the Director of Planning and Regeneration, following consultation with the Executive Member for Planning and Development, the authority to procure and appoint an independent examiner to conduct the examination on the draft Charging Schedule.
Reason: To consult on a revised Community Infrastructure Levy Draft Charging Schedule that is considered to meet the requirements of the Community Infrastructure Levy Regulations 2010 (as amended) including setting an appropriate rate in relation to Regulation 14.
Cost of proposals: There will be a cost to the Council to undertake the examination. This will be mainly focused on the cost of the independent Examiner. Depending on the number of days that the Examiner has to work (which depends on the number and depth of comments that are received from the consultation) an estimate of £30,000 for the 2023/24 financial year has been included in the budget.
Appendices: A: Draft Charging Schedule for Consultation
B: Three Dragons Fareham CIL Review
Background papers: None
Reference papers:
Fareham Community Infrastructure Levy Review – Viability Assessment 2023
Infrastructure Delivery Plan
Fareham Borough Council Local Plan 2037 Executive Briefing Paper Date: 06 March 2023 Subject: Community Infrastructure Levy - Consultation
Briefing Director of Planning and Regeneration by: Portfolio: Planning and Development
INTRODUCTION
1. The Community Infrastructure Levy (CIL) is a planning charge on new development that involves a net increase in building floorspace, to fund infrastructure. The ability for a local planning authority to charge the levy came into effect from April 2010.
2. In April 2013, following two periods of consultation and an independent examination, the Council approved its Charging Schedule, effective from 1 May 2013. The Charging Schedule set a rate of £105 per square metre, applicable to all residential development across the borough, with a different rate applied to out-of-town retail developments. These rates are index linked using the RICS CIL index applied each November.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.