RESOLVED that the Executive agrees that: (a) the Capital Programme allocation for Taxiway Maintenance of £2,700,000 be reduced to £1,700,000; (b) the Capital Programme allocation for £1,100,000 for the Aeronautical Ground Lighting System be increased to £2,800,000; (c) the Capital Programme allocation of £25,000 for installation of self-fuelling facilities be removed; (d) the Capital Programme allocation of £400,000 for aircraft parking be removed; (e) £25,000 be added to the Capital Programme for essential repairs to bring Hangar P back into use; (f) £165,000 be added to the Capital Programme for new airport fuel supply assets; (g) £380,000 be added to the Capital Programme for immediate improvements to the Visual Control Room at the Control Tower on safety grounds; and (h) the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources, be delegated authority to award contracts for each of the above Schemes.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 19 June 2023 Portfolio: Policy and Resources
Subject: Solent Airport Investment Programme
Report of: Director of Planning and Regeneration
Corporate Priorities: Maintain and extend prosperity
Purpose: To review the existing programme of investment at Solent Airport, Daedalus and to consider further investment to address safety and compliance issues and extend the services that the airport offers to its customers.
Executive summary: The existing programme of investment at Solent Airport, Daedalus was approved on 7 March 2022. Much of this work is now in progress, however some elements require review.
Further investment in the airport is required to enable its continued safe operation and to continue to deliver the Council’s Vision to develop a vibrant and sustainable airfield. The proposed programme of investment in the control tower, fuelling facilities and hangarage is required to support existing airside activities.
Recommendation: It is recommended that the Executive agrees that:
(a) the Capital Programme allocation for Taxiway Maintenance of £2,700,000 be reduced to £1,700,000;
(b) the Capital Programme allocation of £1,100,000 for the Aeronautical Ground Lighting System be increased to £2,800,000;
(c) the Capital Programme allocation of £25,000 for installation of self-fuelling facilities be removed;
(d) the Capital Programme allocation of £400,000 for aircraft parking be removed;
(e) £25,000 be added to the Capital Programme for essential repairs to bring Hangar P back into use; (f) £165,000 be added to the Capital Programme for new airport fuel supply assets;
(g) £380,000 be added to the Capital Programme for immediate improvements to the Visual Control Room at the Control Tower on safety grounds; and
(h) the Director of Planning and Regeneration, following consultation with the Executive Member for Policy & Resources, be delegated authority to award contracts for each of the above Schemes.
Reason: Investment is required both to ensure the continued safe operation of the airport and to maintain and grow the airport’s competitive position by removing some of the identified operational constraints. Proposals for investment in the airport are regularly reviewed to ensure that they remain valid and continue to offer appropriate returns.
Cost of proposals: The total additional cost of the updated Airport Investment Programme is estimated at £5,523,700, an increase of £833,700 on the previously agreed £4,690,000 programme.
In accordance with the Daedalus Financial Strategy, there are sufficient Daedalus- related capital receipts to fund the increase.
By virtue of paragraph 3 of Part 1 of Schedule 12A of the Local Government Act 1972 - Information relating to the financial or business affairs of any particular person - and category 7A - Information which is subject to an obligation of confidentiality - of Schedule 12A Local Government Act 2972 and the Council’s Access to Information Procedure Rules.
It is not in the public interest to publish this information as it would harm the Council’s ability to achieve best value on both contracts and rental income in the future, as well as give unfair financial advantage to potential investors in respect of any future competitive bids thus removing the necessary element of market competition that drives best value principles.
Background papers: CONFIDENTIAL Solent Airport Strategic Review Report 2 – Investment Plan Egis, July 2021
Reference papers: None Executive Briefing Paper Date: 19 June 2023 Subject: Solent Airport Investment Programme
Briefing by: Director of Planning and Regeneration Portfolio: Policy and Resources
INTRODUCTION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.