Resolved
RESOLVED that the Executive approves an increased budget of £2.5 million.
Executive approved this item on Monday 18 September 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Executive approves an increased budget of £2.5 million.
1. On the 16th May 2023 the Executive considered a report on the regeneration of Fareham town centre including Fareham Live and Osborn Road multi storey car park.
2. A further report on the Osborn Road Multi Storey was considered at the Executive meeting on the 3 July 2023. Details of progress to date was noted and approval given for a delegated authority to award contracts for these works was provided for the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources.
3. This report further provides details of a revised scheme and budget for the demolition of the existing multi storey car park with the construction of a new surface car park on the site.
TENDER PROCESS
4. The previous approved budget £1.96 million was provided early in 2022 and based on information from similar schemes and details from our consultant team.
5. In the period between estimate costs being prepared and tenders being received it should be noted that construction costs have risen in excess of 12%.
6. Development of the scheme has included improved drainage which wasn’t originally included, in addition to extra highway requirements.
7. A further development of the design outside the original costings was the addition of solar photovoltaic (PV) canopies with associated battery storage with initial projections showing a short pay-back period.
8. Four tenders were received for this project from local and regional contractors. All provided costs that were above our projected costs for the demolition and construction works. 9. It was noted that the costs for the solar PV canopies were significantly above our expectations with the pay-back period being more than double the initial evaluation.
REVISED SCHEME
10. A review of the design for the new car park has been carried out. This retained most of the features required for the operation of a modern car park that supports the regeneration of the town centre and to serve Fareham Live.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Osborn Road Multi Storey car parkReport | 104 KB | DownloadRead as text |
Follow Executive at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... | Agreed | Open |
| 7 Sep 2026 | References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... | Agreed | Open |
| 7 Sep 2026 | Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... | Approved | Open |
| 7 Sep 2026 | Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... | Approved | Open |
| 7 Sep 2026 | Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.