Resolved
RESOLVED that the Executive approves a budget of £130,000 for a grid connection application and for a deposit to secure the connection should an acceptable offer be received.
Executive approved this item on Monday 18 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Executive approves a budget of £130,000 for a grid connection application and for a deposit to secure the connection should an acceptable offer be received.
Report to the Executive for Decision 18 March 2024 Portfolio: Policy and Resources
Renewable Energy Scheme: Hook Recreation Ground Subject: Solar Photovoltaic (PV) Development Feasibility
Report of: Director of Planning and Regeneration
Respond to Climate Change and Protect the Environment; Corporate Priorities: Promote Economic Development; Responsive, Inclusive, and Innovative Council
Purpose: To brief the Executive on the potential for a solar photovoltaic (PV) scheme at Hook Recreation Ground and to seek funding for the next feasibility stage of the project.
Executive summary: Hook Recreation Ground is a former landfill site currently used as an informal recreation ground, mainly by dog walkers and model plane flyers. This report advises the Executive on the potential to develop a 3.5MW solar PV scheme on the site. There are two main benefits of a solar PV scheme:
• Financial: From the financial modelling undertaken thus far a solar PV scheme has significant revenue generating potential and could also be used to reduce the Council’s electricity bills. • Environmental: The Council would produce renewable electricity. As a minimum it would generate enough electricity to power the Civic Offices, Depot, and Housing communal areas which would in turn reduce the Council’s carbon footprint. Renewable electricity would also be returned to the wider electricity network, contributing toward ‘greening of the grid.’
Understanding if and when a solar PV scheme could connect into the grid network is essential to progressing to the next feasibility stage of the project and associated business case. The project cannot progress to further stages without securing a viable grid connection, and overall scheme viability would be questionable if this could not be obtained for some time. Accordingly, there is a time imperative to making the grid application.
To make an application for a grid connection and secure the offer should it be received, this report seeks a budget of £130,000. Between £25,000 - £30,000 would be used to make an application and commission associated studies. This is non- refundable. The remaining £50,000 - £100,000 would be required as a deposit to accept a grid connection if an acceptable offer is received. The money would be refundable if the Council did not proceed with the solar PV scheme. It would not be committed without a further Executive approval.
It is acknowledged this type of development on Hook Recreation Ground would result in the loss of open space, albeit of poor quality. This will be addressed during later stages of the project once the initial feasibility work around a grid connection has been undertaken. The project is dependent on a viable grid connection and therefore, it is not worthwhile undertaking further work until this has been assessed.
Furthermore, development of this type involves risks. This is being carefully considered against the benefits, a process that will continue into the next stages of the project.
Recommendation: It is recommended that the Executive approves a budget of £130,000 for a grid connection application and for a deposit to secure the connection should an acceptable offer be received.
Reason: To be able to progress with the next feasibility stage of the project and associated business case.
Cost of proposals: The budget required to secure a grid connection offer is £130,000, incorporating a £25,000 - £30,000 non-refundable element. If the connection offer was accepted a £50,000 - £100,000 deposit would be required. This would be refundable if the project did not eventually proceed.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Plan of Hook Recreation Ground (1)Appendix A | 85 KB | Download |
PDF |
Renewable Energy Scheme: Hook Recreation Ground Solar Photovoltaic (PV) Development FeasibilityReport | 157 KB | DownloadRead as text |
Follow Executive at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 7 Sep 2026 | Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... | Agreed | Open |
| 7 Sep 2026 | References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... | Agreed | Open |
| 7 Sep 2026 | Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... | Approved | Open |
| 7 Sep 2026 | Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... | Approved | Open |
| 7 Sep 2026 | Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.