Resolved
RESOLVED that the Housing Scrutiny Panel notes the content of the report.
Housing Scrutiny Panel decided this item on Thursday 24 October 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Housing Scrutiny Panel notes the content of the report.
Following budget overspend on void works during 2023/24, and with that overspend pattern continuing into 2024/25, interventions are now being delivered by Officers to ensure the impacts and costs of void properties to the Housing Revenue Account are sustainable. This report provides an update for the Housing Scrutiny Panel on the operational adjustment to the ‘void standard’ which is intended to reduce costs, whilst still providing safe and compliant housing.
It is recommended that the Housing Scrutiny Panel notes the content of the report and raises any questions or queries with Officers. INTRODUCTION
1. ‘Voids’ refers to those properties that are not subject to a tenancy. When a property becomes empty (through tenants moving, passing away, tenancy end, or other reasons) works will typically be required to the home. These are termed as ‘void works’. They can vary from compliance/legal requirements (such as electrics or EPC certification), right through to substantial and costly voids works (kitchen/bathroom replacement, remedial building work, electrical works etc.).
2. A previous Vanguard/systems thinking intervention at Fareham Housing put quality and customer service at the core. This in turn led to a ‘void standard’ that was well above the industry norm and went beyond legal/compliance expectations.
3. Although a high quality and extensive ‘void standard’ had been achieved in a financial and practical sense for many years, several factors mean this is no longer sustainable.
4. This report is not intended to provide a wider overview of the voids process, or wider improvements to the void process undertaken or planned. For example, the overall speed of voids is a separate matter (albeit the extent of void works is one contributor to speed, e.g. less void works will reduce the void turnaround period). A further report to the Housing Scrutiny Panel is anticipated in 2024/25 on wider void matters.
THE RISING VOID SPEND
5. The overall expenditure on voids has increased significantly in recent years. This is reflected in both capital and revenue expenditure.
2021/22 2022/23 2023/24
Void Costs £179,738 £537,003 £1,101,484 (Revenue)
Void Costs £1,398,393 £1,590,578 £2,328,506 (Capital)
Total Voids Costs £1,578,131 £2,127,581 £3,429,990
Figure 1
6. Several factors have contributed to the overall ‘void costs’ increasing. This includes: -
• Increased material costs in recent years (inflation linked). • Increased labour costs. • Increased number of void properties processed per annum. • Further mould/damp preventative measures introduced. • Maximising opportunities to make appropriate homes adaptable for those with disabilities. • Increasing prevalence of void properties that require significant works (including those left in a poor condition from outgoing tenants).
7. In a budget sense these increasing demands have not been offset by a corresponding increase in rental income (rent income for 2023/24 was capped below inflation), and wider financial pressures on the HRA mean it is not possible to direct funds from other areas of the HRA to offset the increased costs. 8. Limited historical data is available on the number of voids processed per annum. Based on data used when the current voids work contract was entered into (in 2018), circa 100-120 voids were historically processed per annum. In comparison over 200 properties become void in the first five months of 2024/25.
9. There are no clear definitive explanations for the increasing number of voids processed per annum, and historical trends are hard to derive due to limited historical quantitative or qualitative data being captured/held. In a positive sense it can indicate increased churn in our stock (i.e. more homes becoming available for those that need them).
INTERVENTIONS
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Revised Void StandardReport | 119 KB | DownloadRead as text |
Follow Housing Scrutiny Panel at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Apr 2025 | Fareham Housing Development Sites UpdateRESOLVED that the Housing Scrutiny Panel notes the content of the presentation. | Decided | Open |
| 3 Apr 2025 | Greener Measures and InstallationsRESOLVED that the Panel notes the content of the report. | Decided | Open |
| 3 Apr 2025 | Analysis of Council Housing Waiting ListRESOLVED that the Housing Scrutiny Panel notes the content of the report. | Decided | Open |
| 3 Apr 2025 | Draft Fareham Housing Battery Powered Mobility Aids PolicyRESOLVED that the Housing Scrutiny Panel: (a) considered the Draft Fareham Housing Battery Powered Mobility Aids Poli... | Approved | Open |
| 3 Apr 2025 | Tenant Satisfaction MeasuresRESOLVED that the Housing Scrutiny Panel notes the content of the report and the performance of Fareham Housing in th... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.