RESOLVED that the Executive agrees: (a) the implementation of the 2024-2034; (b) to submit the Outline Business Case to the Environment Agency to secure funding; (c) the submission of planning and consenting for the proposed works in Fareham; and (d) that the Director of Planning and Regeneration be authorised to procure and subsequently enter into an agreement to enable delivery of these works.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 04 November 2024 Portfolio: Planning and Development
Hill Head to Portsmouth Harbour Beach Management Subject: Plan
Report of: Director of Planning and Regeneration
Corporate Priorities: Respond to Climate Change and Protect the Environment
Purpose: This report seeks approval for project delivery of the Hill Head to Portsmouth Harbour Beach Management Plan. The proposed works involve beach renourishment along the coastal frontage between Hill Head and Portsmouth Harbour Entrance. The approval for project delivery includes draw down of project funding, licencing and consents, procurement, and construction under the beach management plan.
Executive Summary: This paper seeks approval to implement the Hill Head to Portsmouth Harbour Beach Management Plan (BMP) 2024-2034, with construction works identified for financial year 2025/26 and 2026/27.
The BMP is derived from the adopted River Hamble to Portchester Strategy (2015) which recommended Beach Management as the preferred option to reduce coastal flooding and erosion risk to the communities between Hill Head and Portsmouth Harbour Entrance, whilst enhancing the environment and amenity value of the coastline over the next 10 years. The BMP also aligns with the adopted North Solent Shoreline Management Plan (2010), which recommends a policy of ‘Hold the Line’ for the entire frontage.
The BMP works will provide up to 10 years’ worth of benefits. These will be undertaken at different locations in priority order, up to the project funding available, depending on the assets at risk behind the beach. These will be categorised by considering the risk to property, key infrastructure, existing ‘hard’ defences (e.g. seawalls), and then amenity value.
The BMP has been developed from extensive coastal modelling and technical analysis to develop the beach recycling parameters. This will continue post works, to monitor performance and plan any further works. While the geographical extent of the BMP crosses the local authority boundaries of both Gosport Borough Council (GBC) and Fareham Borough Council (FBC), each authority will take responsibility for its own works delivery and consenting. These projects will be managed by Coastal Partners via an existing shared service agreement to ensure the overall BMP objectives are met.
Funding for the project has been allocated through the Environment Agency’s Flood Defence Grant in Aid, and Other Government Department funding, and will be approved should the Outline Business Case be successful. The project will seek additional funding where this can increase the outputs delivered under the project.
Recommendation/Recommended Option: It is recommended that the Executive agrees:
(a) the implementation of the Hill Head to Portsmouth Harbour Beach Management Plan 2024-2034;
(b) to submit the Outline Business Case to the Environment Agency to secure funding;
(c) the submission of planning and consenting for the proposed works in Fareham;
(d) that the Director of Planning and Regeneration be authorised to procure and subsequently enter into an agreement to enable delivery of these works.
Reason: Implementation of the BMP will provide a healthy beach at priority areas along the Hill Head to Portsmouth Harbour Entrance coastline, reducing coastal flood and erosion risk to properties and infrastructure for up to 10 years. Without the implementation of the BMP, beach levels are forecast to continue to lower, which increases flood and erosion risk for shoreline assets. If the beach management plan (BMP) was not to be implemented, the beach levels will likely continue to lower year on year, putting any coastal assets to the rear of the beach at increasing risk which may in turn lead to the requirement for financial investment in these assets by the council.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.