Resolved
RESOLVED that the Housing Scrutiny Panel notes the content of the report, including the changes undertaken and underway, and the intention to see ongoing improvements moving forward.
Housing Scrutiny Panel decided this item on Thursday 9 January 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the Housing Scrutiny Panel notes the content of the report, including the changes undertaken and underway, and the intention to see ongoing improvements moving forward.
This report provides the Housing Scrutiny Panel with an update on the changes, and improvement thus far, in how Fareham Housing address the ‘voids’ process. The report focuses on the process, efficiency, and the timeliness of voids.
It is recommended that the Panel note the content of the report, including the changes undertaken and underway, and the intention to see ongoing improvements moving forward. INTRODUCTION
1. The Housing Scrutiny Panel have previously received reports relating to ‘void’ properties in Fareham Housing. Most recently this included a report to the Panel in October 2024 which focused on the costs of voids, and an operational change to the level of works undertaken in void properties.
2. This report looks at the wider void process in the context of opportunities already taken, and recognised for the future, to improve void speed and efficiency.
3. The changes so far have sought to ensure that any attention given to the speed/timeliness of void works, does not detrimentally draw the focus from other important factors, such as seeking to increase the provision of disabled adapted properties.
4. For clarity, the term ‘void’ is used in the context of the period between when one tenancy at a property ends, and another begins. This report relates to Council owned homes, predominately owned and managed through the Council’s Housing Revenue Account (HRA).
5. There will on occasions be Fareham Housing properties that remain intentionally vacant but are not subject to the void process. This might include properties where a tenant has passed away, or is in hospital for long periods, but the home remains subject to a tenancy. On these occasions the property would not be classed as ‘void’. There will also be occasions where homes are intentionally held vacant due to a planned regeneration or redevelopment project. In this latter example the property is ‘void’ but will be removed from any data analysis as no void works, nor a new tenancy, is anticipated.
6. In 2023 it was recognised that the average time taken to process void properties in Fareham Housing was too long. Detrimental impacts arising from prolonged void periods include the following: -
• Delays in properties becoming available for new tenants. • Loss of potential rental income to the HRA. • Increased Council Tax payment liability for vacant homes, a cost met by the Housing Revenue Account.
7. A starting challenge in 2023 was the lack of reliable data or analysis on the overall void times, including the time taken at individual void stages.
8. Stages of the void process include: -
• Tenancy end to void ‘scope’ (i.e. identifying and specifying the void works required) • Void works (i.e. the period from when the keys are handed to a void contractor, until keys are returned, with all void works completed) • Property void works complete to new tenancy start (i.e. the period from contractor returning keys until new tenancy start date). 9. These elements of the void process combined, give the overall void period.
PREVIOUS DATA AND APPROACH
10. As mentioned in paragraph 7, a starting challenge was the lack of easily available data on void times. Detailed analysis in November 2023 indicated that the average void period was 110 days. Approximately 55 days was spent with the property in the hands of the contractor (undertaking works), and 55 days was spent with in-house procedures before and after the home was with the contractor. On this latter point, that included the time before the property was cleared, scoped and made available to the contractor, and (post void works) the period to then have a new tenancy begin.
11. The 2023 analysis also included qualitative work to understand key issues contributing to the void periods. Aspects of this are reflected in paragraph 14 of this report.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Management and Performance of the Void ProcessReport | 149 KB | DownloadRead as text |
Follow Housing Scrutiny Panel at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Apr 2025 | Fareham Housing Development Sites UpdateRESOLVED that the Housing Scrutiny Panel notes the content of the presentation. | Decided | Open |
| 3 Apr 2025 | Greener Measures and InstallationsRESOLVED that the Panel notes the content of the report. | Decided | Open |
| 3 Apr 2025 | Analysis of Council Housing Waiting ListRESOLVED that the Housing Scrutiny Panel notes the content of the report. | Decided | Open |
| 3 Apr 2025 | Draft Fareham Housing Battery Powered Mobility Aids PolicyRESOLVED that the Housing Scrutiny Panel: (a) considered the Draft Fareham Housing Battery Powered Mobility Aids Poli... | Approved | Open |
| 3 Apr 2025 | Tenant Satisfaction MeasuresRESOLVED that the Housing Scrutiny Panel notes the content of the report and the performance of Fareham Housing in th... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.