RESOLVED that the Panel: - (i) Note the content of the presentation; and (ii) request that their congratulations be passed on to all who have been involved in making this site such a success. They acknowledged the hard work that has been put into this project, not just by Officers of the Council, but all who are involved with the site.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
‘to become a premier location for aviation, aerospace engineering and advanced manufacturing businesses, creating many skilled employment opportunities for local people…..’ 2013 Outline Planning Consent:
‘Use of Airfield for Employment based development (Up to 50,202 sq m of Floor space) in new and existing buildings (Class B1, B2 and B8)….’
Current Local Plan Allocation:
Overall: 128,000 sq m (Largest allocation in Borough)
Faraday and Skills/Innovation Cluster: 93,000 sq m
Swordfish Business Park: 35,000 sq m Faraday/Innovation and Skills Building Cluster: 93,000 sq m Area Building Building Area Building (Running Area (Running Area (m2) Total) m2 (m2) Total) m2 DEVELOPMENT TO DATE DEALS IN HAND 2013/14 2025/26 CEMAST (Core Land) 4,003 4,003 Aerospace Company 16,380 65,846 2015/16 Existing Tenant 2,154 68,000 Innovation Centre (Phase 1) 2,404 6,407 TOTAL (TO DATE) 68,000 2017/18 Proptech 2,297 8,704 GA Hangars 3,042 11,746 2018/19 UTP 2,828 14,574 Innovation Centre (Phase 2) 3,334 17,908 Business Hangars 3,396 21,304 CETC (Option Land) 1,008 22,312 2020/21 HC Coils 3,287 25,599 2021/22 Units 15-17 Spitfire Way 4,280 29,879 Unit 14 1,123 31,002 2022/23 IFA 2 14,775 45,777 2024/25 Bristow Helicopters 3,689 49,466 TOTAL (TO DATE) 49,466 Search and Rescue Training Facility
Facilities Swordfish Business Park: 35,000 sq m Swordfish Business Park: 35,000 sq m 50 acre site (planning allocation)
Core Area: developable plots totalling 27 acres
Taxiway B
Phased delivery likely
Retained business rates will help fund
Weeks Months End of Activity Masterplanning: 30 7.00 Planning: 31 7.00 Tender: 31 7.00 Q1 2027 Construction: 28 8.00 Q3 2027 High impact Challenges Taxiway routes (Swordfish development) HCA obligations No build and 10.5m build zones on sections of the site (MCA) BNG requirements for development Bird mitigation Power Road/Infrastructure Obligation to remain as airfield Ageing Parts of estate
Medium impact 40,000 Movement Cap and daylight restrictions Radiation and unexploded devices National Grid easement
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.