RESOLVED that: - (i) Members of the Panel reviewed and noted the actions undertaken against the Council’s Action Plan; (ii) Officers were requested to; a) liaise with developers to understand the causes of slow build out rates and explore what changes the Council could implement to help improve build out rates; b) undertake a call for brownfield sites to supplement the existing Brownfield Sites register to identify potential suitable additional sites, particularly small sites.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Housing Delivery Test (HDT) Five Year Housing Land Supply (5YHLS) • What is it? • What is a 5YHLS? • What are the implications? • What does it mean? • Fareham’s HDT results • Explaining the 5YHLS – changes to requirements • Fareham’s HDT Action Plan • Fareham’s 5YHLS • Government Response • Panel Discussion • Panel Discussion Monitoring Delivery
Housing Delivery Test 5 Year Housing Land Supply Housing Delivery Test Housing Delivery Test • The Housing Delivery Test (HDT) was introduced by the Ministry of Housing, Communities and Local Government (MHCLG) in 2018. • It is an annual measurement of housing delivery that looks backward over time to hold local authorities accountable for ensuring new homes are delivered. • It assesses the number of homes delivered over the previous three financial years, on a rolling annual basis (2016-19, 2017-20, 2018-21 etc.) • It compares the delivery of housing against the housing requirements in either an up-to-date Local Plan (under 5 years old) or the standard method where a Plan is more than 5 years old. • Local authorities that fail to meet delivery targets are required to take action to address under- delivery. Housing Delivery Test • The test is carried out by MHCLG. Whilst results are meant to be published annually (in November) for the preceding financial year, there has been some delays in publishing results. • For example, the most recent publication was December 2024 and was the 2023 result for the years 2020-2023. • Results are measure in a %. Falling below results in the following penalties:
HDT result Consequence 95% of requirement or lower Housing Delivery Action Plan must be published 85% of requirement or lower 20% buffer applied to 5-year housing requirement 75% of requirement or lower Apply presumption in favour of Sustainable Development Implications of the HDT Results • The consequences apply concurrently. • When falling below 85%, a 20% buffer to be applied to the housing requirement in the 5 Year Housing Land Supply. This will be covered in the next section. • When falling below 75%, the ‘presumption in favour of sustainable development’ must be applied. • This means approving development proposals that accord with an up-to-date development plan without delay. • And for those that do not accord with the development plan policies, granting permission unless there are strong reasons for refusing development (such as protected and irreplaceable habitats such as ancient woodland, designated heritage assets such as scheduled monuments/Listed buildings or areas at risk of flooding or coastal change) Fareham’s HDT Results 2016-2019 2017-2020 2018-2021 2019-2022 2020-2023
Requirement 944 1102 1117 1028 762 Delivery 937 866 692 568 421 % 99% 79% 62% 55% 55% HDT Result Passed • Action Plan • Action Plan • Action Plan • Action Plan • 20% Buffer • 20% Buffer • 20% Buffer • 20% Buffer • Presumption • Presumption • Presumption in favour of in favour of in favour of Sustainable Sustainable Sustainable Development Development Development What is the relationship between delivery and the adopted Local Plan? • The Local Plan Trajectory identified anticipated site delivery as of 2022.
• It's called a ‘Stepped Trajectory’ to recognise anticipated low delivery levels in the first two years of the Plan (210 pa) followed by (653 pa) for the remainder of the plan period.
• This demonstrated a 5YHLS on adoption of the Plan based on evidence from landowners and promoters, with each site being examined during the Local Plan hearings.
• As of 2025 the nature of housebuilding is different : • Increased complexity of planning & delivery • Economic uncertainty • Availability & costs of materials
• The majority of sites allocated in the Local Plan are progressing at a slower rate than anticipated. Local Plan Delivery Dwelling Requirement vs Annual Year Requirement Completions Completions 2018/19 347 290 800 600 2019/20 428* 285
400 2020/21 342* 117
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
The Call for Sites ConsultationRESOLVED that Members considered the contents of the presentation and received clarification on the Call for Sites co...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.