Resolved
RESOLVED that the Housing Advisory Panel considered the content of the report and raised the questions, concerns and points for clarification as detailed above.
AI summaryFareham Housing Advisory Panel considers 30 September 2025 health and safety compliance data for the council's housing stock, with most areas at or near 100%.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED that the Housing Advisory Panel considered the content of the report and raised the questions, concerns and points for clarification as detailed above.
This report sets out the position for compliance with health and safety requirements within Fareham Borough Council housing stock. It is the third report of its type and details compliance at 30 September 2025.
It is recommended that the Housing Advisory Panel consider the content of the report, and raise any questions, concerns or points of clarification. INTRODUCTION
1. Fareham Housing undertakes ongoing assurance checks on its compliance on health and safety matters. These are undertaken by the Housing Management Team, and through quarterly fire safety meetings. The fire safety meetings include a variety of senior Officers from across the Housing service, the Corporate Property Manager, and the Council’s Corporate Health and Safety Officer.
2. This report is the third presented to the Panel. Updates are provided as a 6 monthly snapshot, the information below is of the compliance position on 30 September 2025.
TENANT SATISFACTION MEASURES
3. The Regulator of Social Housing Tenant Satisfaction Measures (TSMs) include compliance information relating to health and safety. These submissions are required annually. The 2024/25 measures were reported to the Housing Advisory Panel at its meeting of 10 July 2025. No further updates on the TSMs will be made until the submission for 25/26, calculated as of 31 March 2026.
ASBESTOS (BS03)
4. Regular asbestos surveys are carried out to 1,101 communal areas of our residential buildings. Asbestos management surveys are initially undertaken by a consultant and are managed thereafter internally by an appropriately qualified surveyor.
5. The position at 30 September 2025 is set out below.
Asbestos 30 Sept 2025 Sites with communal areas requiring inspection: 1101 Sites Inspected: 1101 Completion Rate: 100% Table 1 6. CARBON MONOXIDE DETECTION TESTING
7. Testing of any carbon monoxide equipment takes place alongside smoke alarm testing. However, in the event of any of the following, Fareham Housing will either fit, test and/or replace as appropriate: • In response to any report of a fault • As part of the void process for Council properties • During each EICR inspection (every five years)
DRY RISER TESTING
8. Dry Risers play a crucial role in fire safety by allowing water to be pumped quickly through a building by emergency services in the event of a fire. They must be subject to a visual inspection every 6 months, and an annual pressure test. There are 210 inspections that must be carried out across 6 sites.
9. These tests are carried out by a specialist contractor on behalf of Fareham Borough Council. 10. The position at 30 September 2025 is:
Dry Riser Testing 30 Sept 2025 Compliance Rate: 100% Table 2 ELETRICAL SAFETY
11. Fareham carries out Electrical Installation Condition Report (EICR) inspections every five years. This work is carried out on behalf of Fareham Housing by a contractor.
12. The position at 30 September 2025 is:
EICRs 30 Sept 2025 Compliance Rate - Properties: 98% Compliance Rate – Communal areas: 99% Table 3 13. The communal area out of target is at 15-22 Frosthole Close which is the only small block outstanding. There are seven separate blocks at Frosthole Close with all other blocks within this site completed. There was an issue with the order not releasing, therefore this caused it to be outside the target date. The order has now been sent to the contractor to carry out the EICR as a priority.
14. The term contract with Mountjoy includes electrical inspections which is managed to minimise non-access difficulties. Mountjoy are having an improved success rate of accessing dwellings for both undertaking the EICR and going back to undertake the remedial actions to ensure a satisfactory certificate can be issued when compared to the Council’s previous multiple contractor framework approach.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Fareham Housing Compliance & wider dataReport | 151 KB | DownloadRead as text |
Follow Housing Advisory Panel at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 15 Sep 2026 | Housing Development Sites UpdateRESOLVED that the Housing Advisory Panel notes the content of the presentation. | Decided | Open |
| 15 Sep 2026 | Consumer Standards UpdateRESOLVED that the Housing Advisory Panel: (a) agrees that the proposed updates (track changes) to the Action and Impr... | Agreed | Open |
| 15 Sep 2026 | Tenant Engagement & Insight UpdateRESOLVED that the Housing Advisory Panel: (a) reviewed the progress made against the Tenant Engagement Strategy; and ... | Decided | Open |
| 15 Sep 2026 | Competence & Conduct Standard: Fareham Housing Workforce Development PlanRESOLVED that the Housing Advisory Panel: (a) notes the requirements of the Regulator of Social Housing’s Competence ... | Agreed | Open |
| 23 Jul 2026 | Housing Development Sites UpdateRESOLVED that the Housing Advisory Panel notes the content of the presentation. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.