Approved Executive 1 paper

AI summaryFareham Executive approves revised 2025/26 revenue budget of £15,282,400 and base 2026/27 budget of £16,327,500, with £0.4m funding gap projected by 2027/28 and Pay Policy sent to Full Council.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRevised 2025/26 and base 2026/27 budgets approved
Money£15,282,400 and £16,327,500Revised 2025/26 and base 2026/27 revenue budgets
What happens nextSubmit Pay Policy to Full CouncilFull Council approval needed before 1 April
Who it affectsFareham Borough Council services and residentsAll general fund services and council taxpayers

What was decided

Approved the revised 2025/26 general fund revenue budget of £15,282,400, as set out in Appendices A to C. Report P17, P93

Approved the base 2026/27 general fund revenue budget of £16,327,500, as set out in Appendices A to C. Report P48, P93

Noted the five-year projections in the Medium-Term Finance Strategy, accepted the Budget Setting Principles and Fundamental Principles of FBC Financial Management, and agreed use of reserves to address the future funding gap. Agreed to submit the updated Pay Policy in Appendix F to Full Council for approval. Report P62, P64, P78

Why

The revised 2025/26 budget shows a £56,000 shortfall against the original base of £15,050,100, with changes driven by lower business rates income, increased National Insurance costs, and pressure on Streetscene fleet repairs and Local Government Reorganisation implementation costs. Report P17, P21, P24, P39, P40

Savings were found through the Opportunities Plan (almost £271,000), reduced bed and breakfast homelessness costs, higher planning application fees, and improved trade and garden waste income. The 2026/27 budget is balanced without drawing from unallocated reserves. Report P28, P29, P32, P36, P49

What happens next

Submit the updated Pay Policy 2026/27 (Appendix F) to Full Council for approval before 1 April each year, as required under the Localism Act 2011. Report P78, P141

Continue developing the Opportunities Plan, with 24 high priority and 7 medium priority projects totalling £1,182,947 in potential savings, to manage future funding gaps. Report P72, P73, P76

Receive a further report to the Executive in February 2026 on the £55,000 increase built into the Council Tax Support Fund. Report P56

The money

  • £15,282,400 Revised 2025/26 general fund net revenue budget Report P17, P93
  • £16,327,500 Base 2026/27 general fund net revenue budget Report P48, P93
  • £15,050,100 Original 2025/26 base net revenue budget set earlier in the year Report P16, P93
  • £56,000 Shortfall on revised 2025/26 budget, likely met from savings or unallocated reserves Report P17
  • £1,666,000 Revised pEPR (Extended Producer Responsibility) allocation for 2025/26, up from £704,000 Report P22
  • £155,000 Government funding received for increased National Insurance in 2025/26 (34% of increased cost) Report P21
  • £400,000 Annual reduction in bed and breakfast homelessness service costs following service review Report P29
  • £500,000 Annual allocation from 2025/26 for 3 years to cover Local Government Reorganisation implementation costs Report P39
  • £607,000 Increase in 2025/26 Streetscene vehicle repairs and hire budget due to ageing fleet Report P40
  • £18.6 million Estimated cost of the Council's Corporate Strategy, of which £18.0 million expected to come from capital funds Report P46
  • £0.4 million Projected funding gap by 2027/28 even with 2.99% annual council tax rises Report P64
  • £1,182,947 Total potential savings from 31 Opportunities Plan projects Report P72, P73
  • £270,947 Opportunities Plan savings built into the 2026/27 budget across 7 projects Report P58, P72, P75
  • £300,000 Forecast general fund saving from April 2026 reduction in employer pension contributions from 18.0% to 15.9% Report P57
  • £132,982 to £153,584 Chief Executive Officer salary grade range Report P196, P225
  • £31,537 Median taxable earnings across the workforce used in the pay multiple calculation Report P222

Options considered

  • Chosen: Approve revised 2025/26 budget of £15,282,400. Reflects updated funding, savings and pressures identified through monitoring Report P17
  • Chosen: Approve base 2026/27 budget of £16,327,500. Balanced budget achievable without drawing from unallocated reserves, incorporating pension contribution savings and Opportunities Plan items Report P48, P49
  • Chosen: Submit Pay Policy 2026/27 to Full Council. Required under the Localism Act 2011; must be approved by Full Council before 1 April each year Report P78, P141

Implications

  • Financial: A drawdown from unallocated reserves is required in 2025/26 to cover the £56,000 shortfall if savings are not achieved by year end. The spending reserve is expected to fall no lower than 5% of gross expenditure, below the 7.5% policy minimum. Report P17, P30
  • Financial: A projected funding gap of £0.4 million is forecast for 2027/28, with a further small gap of £120,000 in 2028/29, before a small surplus in the final year of the strategy. Report P64, P125
  • Financial: The budget assumes council tax increases of 2.99% per year and incorporates a £338,026 increase in draft council tax for 2026/27. Report P59, P94
  • Risk: A finance risk register has been developed with over 50 risks; the highest level risks include LGR funding requirements exceeding provision, reductions in service specific grants, business rates income drops, and reduced investment property income. Report P29, P85
  • Staffing: The establishment has increased to deliver priorities in Regeneration, Housing and Environment Strategy, with additional People Strategy costs of £60,000 in both 2025/26 and 2026/27 to prepare staff for Local Government Reorganisation in 2028. Report P43, P44, P68
  • Equalities: The pay multiple ratio of highest paid employee to median earnings is 4.87; the lowest spinal column point currently sits below the new National Minimum Wage and will be adjusted once the next pay award is agreed, with no appointments made on this point in the meantime. Report P79, P191, P223
  • Climate: Officers judge the subject matter of this report is not anticipated to impact the Council's carbon footprint or have detrimental or beneficial impact on the wider environment. Report P26, P81

Who and where

  • Fareham Borough Council taxpayers, who would face a 2.99% council tax rise in 2026/27 if approved at Full Council Report P59, P94
  • Council staff, with a 3.2% pay award for 2025/26 already agreed and a further award under negotiation for April 2026 Report P34, P57, 3.4
  • Households using Trade Waste, Garden Waste, Car Parking, Planning and Hackney Carriage services, where fees and charges have been revised Report P28, P30, P31, P32, P33
  • Users of the Solent Airport at Daedalus, where a new operator is due to commence in 2026/27 Report P55

Timeline

  • 2025/26: Current financial year: revised budget of £15,282,400 with £56,000 shortfall to be contained from savings or unallocated reserves Report P17
  • February 2026: Further Executive report expected on the £55,000 increase in the Council Tax Support Fund Report P56
  • April 2026: Start of 2026/27 financial year; base budget of £16,327,500 takes effect; employer pension contributions reduce from 18.0% to 15.9% Report P48, P57
  • Before 1 April 2026: Updated Pay Policy 2026/27 to be approved by Full Council Report P78
  • 2027/28: Projected funding gap of £0.4 million even with 2.99% annual council tax rises Report P64
  • 2028: Local Government Reorganisation implementation anticipated Report P39, P44, P68
  • 2028/29: Further small projected gap of £120,000 in the Medium-Term Finance Strategy Report P64, P125

Plain English for the jargon

  • Medium-Term Finance Strategy: The Council's five-year financial planning document covering revenue budgets, capital programme and reserves policy, set out in Appendix D.
  • Opportunities Plan: A list of projects generated by officers and members aimed at reducing expenditure or increasing income; 31 projects totalling £1,182,947 in potential savings.
  • pEPR (Extended Producer Responsibility Payment): Government funding paid to councils to cover waste disposal costs, allocated to Fareham at £1,666,000 for 2025/26.
  • Local Government Reorganisation (LGR): Government-led restructuring of local authorities, with Fareham having submitted a case for change; £500,000 per year has been allocated for implementation costs.
  • Pay Multiple: The ratio of the highest paid employee's salary to the median earnings of the rest of the workforce; reported as 4.87 for 2025/26.
  • Spending Reserve: An unallocated reserve maintained to cover unplanned changes in revenue expenditure or income, with a minimum policy of 7.5% of gross expenditure.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10(1)

Resolved

RESOLVED that the Executive: (a) approves the revised 2025/26 general fund revenue budget, amounting to £15,282,400, as set out in Appendices A to C to the report; (b) approves the base 2026/27 general fund revenue budget amounting to £16,327,500, as set out in Appendices A to C to the report; (c) notes the five-year projections from the Medium-Term Finance Strategy in Appendices D and E, accepts the Budget Setting Principles, Fundamental Principles of FBC Financial Management and the use of reserves to address the future funding gap; and (d) agrees to submit the updated Pay Policy in Appendix F to Full Council for approval.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Executive

Appendices

A: Top Level Summary – Revised Budget 2025/26 and Base Budget for 2026/27

B: Summary by Committee and Portfolio - Revised Budget 2025/26 and Base Budget for 2026/76

C: Detailed Service Budgets by Committee and Portfolio - Revised Budget 2025/26 and Base Budget for 2026/27

D: Five-year Projections in the Medium-Term Finance Strategy 2025/26 to 2029/30 and Budget Setting Principles

E: Fundamental Principles of FBC Financial Management, Budget Setting Principles and Budget Responsibilities F: Pay Policy 2026/27

Background papers: None

Reference papers:

Report to the Executive - November 2025 General Fund Revenue Monitoring 2025/26

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
General Fund Revenue Budgets & Finance StrategyReport 313 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 16 attended
SM
Councillor Simon MartinCommittee Member, apologies
IB
Councillor Ian BastableCommittee Member, present
FB
Councillor Fred BirkettCommittee Member, present
JB
Councillor Joanne BurtonCommittee Member, present
MD
Councillor Malcolm DaniellsCommittee Member, present
CH
Councillor Connie HockleyCommittee Member, present
DH
Councillor David HamiltonGuest, in attendance
IC
Ian CollinsOfficer, expected
RI
Richard IvoryOfficer, expected
RJ
Richard JolleyOfficer, expected
AW
Andrew WannellOfficer, expected
SW
Sarah WardOfficer, expected

All 16 on the meeting page

On this subject at Fareham

Search all
  1. General Fund Revenue Budgets & Finance StrategyThis decision
  2. General Fund Revenue Outturn 2025/26Agreed
  3. General Fund Fees and ChargesApproved
  4. General Fund Finance StrategyDecided
  5. General Fund Fees and ChargesNoted
  6. General Fund Revenue MonitoringDecided

More from Fareham Executive

All decisions
MeetingDecisionOutcome
7 Sep 2026 Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor... Agreed Open
7 Sep 2026 References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu... Agreed Open
7 Sep 2026 Fareham Housing Tenancy Policy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Housing Tenancy Policy to move forward for a period of pu... Approved Open
7 Sep 2026 Homelessness and Rough Sleeping Strategy - ConsultationRESOLVED that the Executive: (a) approves the draft Fareham Homelessness and Rough Sleeping Strategy to move forward ... Approved Open
7 Sep 2026 Fareham Freedom March and Heritage CelebrationRESOLVED that in order to celebrate Fareham Borough’s heritage, the Executive approves that: (a) a public event be or... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies