Fareham Park Vision - Phase 2 Concept Design Options and Funding Proposals
ApprovedExecutive4 papers
AI summaryFareham Borough Council's Executive has approved the Design and Construction tender for a new 1,000 square metre community centre in Fareham Park and set aside up to £2.4 million from capital receipts or CIL to cover the funding shortfall.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedProceed with tender, delegated award, £2.4m allocated
MoneyUp to £2.4 millionFrom capital receipts or CIL, to cover shortfall
What happens nextEvaluate tenders March 2026Contract award planned for April 2026
Who it affectsFareham Park residents and community groupsReplaces existing 150 sqm community centre
What was decided
Officers are to proceed with the Design and Construction tender for the new Fareham Park Community Centre, with a tender already issued in January 2026. Report P43
Delegated authority to award the Design and Construction contract is given to the Director of Community and Corporate Services, after consultation with the Executive Member for Leisure and Community. Report P43
A maximum of £2.4 million is allocated from unallocated capital receipts and/or Community Infrastructure Levy contributions to cover the Phase 2 funding shortfall. Report P49, P50
Why
Fareham Park Ward is the most deprived area in the Borough, and the existing 150 square metre community centre is too small to serve local groups including a Community Pantry, an older person's social group and a pétanque group. Report P1, P2, P3
Phase 1 of the Fareham Park Vision was completed in March 2025 using a £700,000 UK Shared Prosperity Fund allocation, leaving the Section 106 funds of £1.75 million available for Phase 2. Report P6, P12, P46
The total Phase 2 cost, including surveys, landscaping and a 10 percent contingency, is projected at around £4.2 million, with external funding applications to be submitted once Full Planning Consent is in place. Report P45, P47, P48
What happens next
Tender responses for Design and Construction are to be evaluated in March 2026, with the contract awarded in April 2026. Report P62, P63
External funding applications will be submitted from September 2026, with the Reserved Matters Planning Application following in November 2026. Report P64, P65
Construction of the new community centre is scheduled to begin in Spring 2027, with the centre opening in Spring 2028 alongside demolition of the old building and landscaping works. Report P67, P68
The money
£2.4 million Maximum allocation from capital receipts or CIL to cover Phase 2 shortfall Report P49, P50
circa £4.2 million Total projected cost of the new facility including surveys, landscaping and 10% contingency Report P45
£1.75 million Section 106 developers' contributions carried forward from the Cams Alders Vision Report P6, P46
£50,000 Additional UK Shared Prosperity Fund allocation for 2025/26 survey and design costs Report P46
£700,000 UK Shared Prosperity Fund allocation that fully funded Phase 1 Report P5, P12
£1m Total UK Shared Prosperity Fund allocation to Fareham Borough Council Report P5
£2.6 billion Total UK Government UK Shared Prosperity Fund announced in 2022 Report P4
Options considered
Chosen: Progress with the Design and Construction tender and award via delegated authority. Avoids delay and allows the project to move through planning in time to meet external funding requirements Report P43, P48, P58
Chosen: Allocate up to £2.4 million from capital receipts and/or CIL as a funding backstop. External funding outcomes will not be known until late 2026 and the project needs a confirmed funding route to proceed Report P48, P49, P50
Implications
Financial: Up to £2.4 million of unallocated capital receipts and/or CIL contributions is committed to Phase 2, reducing as alternative external funding is secured. Report P49, P50
Equalities: The project targets the Borough's most deprived Ward, aiming to address identified inequalities in community, leisure and support facilities. Report P1, P5, P77
Climate: The new centre will use carbon reduction technology such as photo voltaic cells and air source heat pumps, and must deliver at least 10 percent Biodiversity Net Gain. Report P31, P34, P70
Risk: A project Risk Assessment is maintained and updated, covering drainage, car parking, biodiversity, energy supply and external funding uncertainty. Report P29, P30, P31, P33, P47, P74, P75
Other: Car park arrangements with Hampshire County Council are being converted to a Licence Agreement ahead of the school relocation to Whiteley in Summer 2027. Report P26, P27
Who and where
Residents of Fareham Park Ward, identified as the most deprived area in the Borough Report P1
Users of the existing Fareham North-West Community Centre, including the Community Pantry, an older person's social group and a pétanque group Report P3
Hampshire County Council, as current leaseholder of 1.5 of the 3 on-site car parks linked to Henry Cort Community College Report P26, P27
Local community groups, via the Fareham Park Community Advisory Committee chaired by a Ward Councillor Report P19, P40
Timeline
2022: Government launches the UK Shared Prosperity Fund as part of the Levelling Up agenda Report P4
March 2025: Phase 1 of the Fareham Park Vision completed, including new play area, football pitch improvements and Outline Planning consent Report P12, P21
21 January: Leisure and Safer Communities Advisory Panel endorses the design proposals Report P53
January 2026: Tender issued for the Design and Construction contract Report P43
March 2026: Design and Construction tender responses to be evaluated Report P62
April 2026: Contract award planned Report P63
September 2026: External funding applications to be submitted Report P64
November 2026: Reserved Matters Planning Application to be submitted Report P65
December 2026: Disposal of Open Space planned Report P66
Summer 2027: Hampshire County Council lease linked to Henry Cort Community College expected to terminate as the school relocates to Whiteley Report P26
Spring 2027: Construction of the new community centre to begin Report P67
Spring 2028: New community centre opens, old centre demolished and landscaping and car park improvements delivered Report P68
Plain English for the jargon
BNG: Biodiversity Net Gain, a planning requirement for development to deliver a measured improvement in biodiversity, here set at a minimum 10 percent
CIL: Community Infrastructure Levy, a charge that local authorities can collect from developers to fund infrastructure
UKSPF: UK Shared Prosperity Fund, a Government fund launched in 2022 to reduce inequalities between communities
Section 106: Planning obligations under Section 106 of the Town and Country Planning Act used to secure developer contributions, here redirected from the Cams Alders Vision
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10(1)
Resolved
RESOLVED that the Executive approves that: (a) officers proceed with the tender for the Design and Construction stage of the new Fareham Park Community Centre; (b) delegated authority is designated to the Director of Community and Corporate Services, following consultation with the Executive Member for Leisure and Community, for the award of the contract for the Design and Construction works; and (c) a maximum of £2.4 million is allocated from unallocated capital receipts and/or Community Infrastructure Levy (CIL) contributions to cover the financial shortfall (once known following the funding application results as set out in Confidential Appendix C) and to ensure the successful completion of Phase 2 of the Vision.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 2 February 2026
Portfolio: Leisure and Community Fareham Park Vision – Phase 2 Concept Design Subject: Options and Funding Proposals Report of: Director of Corporate and Community Services Leisure opportunities for wellbeing and fun Corporate Priorities: Strong, Safe and Healthy Communities
Purpose: The purpose of this report is to provide an update on progress with the Fareham Park Vision, outline the next steps in awarding the tender for the Design and Construction stage of the new community facilities, and propose delegated authority for awarding this tender.
The report also reviews the funding allocated towards this corporate priority and recommends options for addressing the predicted financial shortfall, while setting out the anticipated timescale for the project’s completion.
Executive summary: In 2022, the Government launched the £2.6 billion UK Shared Prosperity Fund as part of its Levelling Up agenda, with the intention of reducing inequalities between communities.
Following a successful application and the submission of a detailed proposal, Fareham Borough Council was allocated £1 million of the Fund. Of the Council’s allocation, £700,000 was to be used on the creation of a community-led Masterplan for much needed affordable housing alongside first phase works on improved community and leisure facilities for Fareham Park.
This allocation was to be combined with £1.75 million in Section 106 contributions to provide a substantial budget to kick start the ‘Fareham Park Vision’.
Initial works to install a new children’s play area that is suitable for all ages and abilities, improve the sports pitches on site, engage with the local community regarding their requirements for community facilities and the subsequent submission of an Outline Planning Application for these facilities have all been successfully completed.
The Outline Planning consent identified several factors that require further consideration in the Reserved Matters stage of the Planning Application. These were:
• lighting, particularly in relation to the pétanque terrain; • final designs of the internal layout and external appearance of the new community centre; • confirmation of car parking availability due to the lack of clarity regarding the timeframe within which the Henry Cort College car parks will be returned to the Council; • a comprehensive drainage strategy due to the inherently poor drainage in this area; and • confirmation of the Biodiversity Net Gain from the alterations / consideration of the quantity of Biodiversity Credits required to be purchased from a registered site.
All of these matters are being progressed, alongside the consideration of the energy supply requirements of both the new community centre (Phase 2) and the affordable housing scheme (Phase 3) that will follow.
The draft internal layout and external appearance designs are marked Appendix A and B.
This report seeks the Executive’s approval to progress with the tender for the Design and Construction stage of the project. The successful contractor will work with the Council on the details for the final design, which will provide the final key information required for the Reserved Matters stage of Planning and ultimately enable the construction of the new Community Centre.
This report also requests approval to delegate authority to the Director of Community and Corporate Services, following consultation with the Executive Member for Leisure and Community, to award this contract. The delegation ensures there are no unnecessary delays to the completion of this phase of the project, which is scheduled for Spring 2028.
Phase 2 of the Fareham Park Vision, which will see the final design and construction of the new Community Centre, has been identified as requiring a budget of £4.2 million.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.