AI summaryFareham Executive approves extra Warm Homes retrofit works for 2026/27 and extends the LivGreen contract, with £240,000 of matched council co-funding conditional on a grant award.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedWarm Homes Social Housing Fund, 2026/27
Money£240,000 co-funding (matched by grant)Only spent if DESNZ grant awarded
What happens nextAwait DESNZ funding decisionThen extend LivGreen contract and deliver works
Who it affectsNot stated
What was decided
The Executive approved supplementary works under the Warm Homes Social Housing Fund for the 2026/27 financial year. Report P2, P3
The Executive approved extending the contract with LivGreen to deliver the additional works, subject to the funding application being approved. Report P10
Why
The Warm Homes: Social Housing Fund Wave 3 project is retrofitting social housing stock, improving energy performance, tenant comfort and affordability, and cutting carbon. Report P7, P9
The Council applied to DESNZ for additional grant funding before the 29 April deadline and has confirmed it can match fund the extra amount if the bid succeeds. Report P1, P2
What happens next
If the grant is awarded, the Council will incur £240,000 of additional co-funding and extend the LivGreen contract to carry out the extra works. Report P2, P10
The additional funding will be spent during 2026/27 and managed within the Housing Revenue Account capital programme. Report P2, P3
The revised budget will be reflected in the updated HRA capital programme and reported as part of the HRA Outturn later this year. Report P4
The money
£240,000.00 Additional co-funding, matched to the extra grant and only incurred if the DESNZ application is approved Report P2
£240,000.00 Additional grant funding applied for from DESNZ for 2026/27 Report P4
£215,157.00 Co-funding underspend carried forward from 2025/26 to support 2026/27 delivery Report P4
£1,746,849.25 Revised total 2026/27 programme budget after extra grant and co-funding Report P4
£3,339,742.25 Revised total project budget across all years Report P4
Options considered
Chosen: Approve supplementary works and extend the LivGreen contract subject to funding approval. Lets the Council maximise external grant funding and meet climate and housing objectives without committing funds until the award is confirmed Report P9, P10
Implications
Financial: The £240,000 council co-funding will only be spent if DESNZ approves the extra grant, and will sit inside the Housing Revenue Account capital programme. Report P2, P4
Climate: Retrofitting measures are expected to improve the Energy Performance Certificate ratings of many Council properties, cutting carbon emissions and improving comfort for tenants. Report P7
Risk: All the additional work and spending depend on the DESNZ funding application being successful; if it fails, the supplementary works and extra co-funding will not proceed. Report P2, P10
Other: Future improvement programmes are already being considered, focusing on maximising energy performance and longer-term asset planning where grant funding alone is not enough. Report P5
Who and where
Tenants in Fareham Borough Council social housing whose homes are retrofitted under the Warm Homes scheme Report P7
Fareham Borough Council, as landlord and as the body providing matched co-funding from the Housing Revenue Account Report P2, P4
LivGreen, the existing contractor whose contract would be extended to deliver the extra works
Timeline
Before 29 April: Supporting evidence for the DESNZ application was submitted and the Council confirmed it could match fund the extra amount Report P1
2026/27: Additional grant and co-funding will be spent on the supplementary Warm Homes works Report P3
Later this year: Revised programme budget will be reported formally as part of the Housing Revenue Account Outturn Report P4
Plain English for the jargon
WH:SHF: Warm Homes Social Housing Fund, a government grant scheme for retrofitting social housing stock
DESNZ: The government department to which the additional funding application was submitted
EPC: Energy Performance Certificate, the rating that the retrofitting works are expected to improve
HRA: Housing Revenue Account, the ringfenced account that funds council housing and the co-funding for this programme
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10(2)
Resolved
RESOLVED that the Executive approves: (a) the supplementary works to the Warm Homes Social Housing Fund for the 2026/27 financial year; and (b) the extension of the contract with LivGreen to deliver the additional works subject to approval of the Council’s funding application.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
Report to the Executive for Decision 18 May 2026 Portfolio: Housing
Subject: Warm Homes – Additional Funding
Report of: Director of Housing and Health Provide Housing Choices Corporate Priorities: Respond to Climate Change and Protect the Environment
Purpose: To provide an update on the Warm Homes: Social Housing Fund Wave 3 project. Approval is also sought for the supplementary works under this scheme.
Executive summary: The Warm Homes: Social Housing Fund (WH) Wave 3 is a government initiative aimed at improving the energy efficiency of social housing across England. The scheme provides funding to social housing landlords to retrofit existing properties. The fund focuses on upgrading homes with an Energy Performance Certificate (EPC) below band C.
This report provides an update on the Council’s Warm Homes project and sets out the opportunity to apply for additional grant funding totalling £240,000 during the 2026/27 financial year. Co-funding of the same amount is required and has been confirmed under delegated powers by the Chief Finance and Technology Officer to the Department of Energy Security and Net Zero (DESNZ).
Recommendation/Recommended Option: It is recommended that the Executive approves:
(a) the supplementary works to the Warm Homes Social Housing Fund for the 2026/27 financial year; and
(b) the extension of the contract with LivGreen to deliver the additional works subject to approval of the Council's funding application.
Reason: To meet the commitments in the Housing Greener Policy and the Fareham Borough Council Climate Change Action Plan. Cost of proposals: The Council is required to co-fund the equivalent amount applied for. Therefore, this cost totalling £240,000 will be added to the existing programme of improvements within the Housing Revenue Budget.
Appendices: None.
Background papers: None.
Reference papers: 11 March 2025 Executive Report: Warm Homes Social Housing Fund, Wave 3
15 May 2023 Report to Executive: Housing Stock Condition Survey.
Fareham Borough Council Climate Change Action Plan
Fareham Housing Greener Policy Executive Briefing Paper Date: 18 May 2026 Subject: Warm Homes – Additional Funding
Briefing by: Director of Housing and Health Portfolio: Housing
INTRODUCTION
1. The Warm Homes Social Housing Fund Wave 3 is a government initiative aimed at improving the energy efficiency of social housing across England to EPC C or above. On 11 March 2025, the Executive approved the Council’s participation in the Warm Homes: Social Housing Fund Wave 3 scheme. This included approval of the required match funding to deliver energy efficiency and low‑carbon improvement works to Council housing stock.
2. This report updates the Executive on the progress made on the scheme and advises of the opportunity for additional funding in the 2026/27 year.
PHASE 1 AND FUTURE CONSIDERATIONS
3. The Warm Homes project is separated into three phases. This is to simplify the delivery process and ensure governance processes are followed. Phase 1 started in September 2025, targeting 45 of the Council’s social housing properties. It will complete in June 2026. To date, 38 properties have had works completed. Overall, the first phase has been a success, despite some challenges resulting in valuable lessons learnt. These challenges are further explained in paragraphs 4 to 6 of this report.
Tenant Engagement 4. The value of tenant engagement in a project such as Warm Homes cannot be understated. The Council has no powers to undertake works where tenants refuse access. Refusals were experienced at some properties during the project and even with further discussions some tenants still declined.
5. Engagement has therefore been brought forward for phase 2 to allow time to address access issues and tenant concerns. Those tenants that refused the works will be contacted again to confirm whether they wish to participate in phase 2 or 3.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.