Resolved
RESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work.
AI summaryFareham's Audit and Governance Committee has noted the Chief Internal Auditor's quarterly report covering 22 audits in the 2025/26 plan, with three audits receiving limited or minimal assurance opinions, including vehicle management.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work.
This report is a standard item on the Audit and Governance Committee agenda with the aim of providing Members with the assurances arising from the latest Internal Audit work.
It is RECOMMENDED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. INTRODUCTION
1. This report provides the assurances arising from the latest internal audit work and gives an update on the progress being made with setting and delivering the audit plans.
PROGRESS OF THE 2025/26 AUDIT PLAN
2. The original plan for the year contained 22 audit assignments. 18 of these assignments were to produce an audit opinion (Appendix One). One of the opinion audits in the plan was deferred, ICT Data Governance, and subsequently replaced by a review of Housing Rents VAT Invoicing. In addition, to the opinion audits, four “wider work” reviews were part of the audit plan for 2025/26 (22 items in total).
3. Work has commenced on all 22 audits in the 2025/26 internal audit plan, this includes 21 audits which have been finalised, as noted in Appendix One. The remaining one ‘wider work’ audit is currently at Stage 4 (the Auditor has started to deliver the agreed scope of work).
FINALISING PREVIOUS PLANS
4. There were three outstanding audits from the previous Audit Plans, which have now been completed.
5. The review of all outstanding recommendations from the 2024/25 Housing Procurement review found that they have been implemented.
6. Testing for the Code of Corporate Governance has now been completed, with a ‘strong’ opinion report issued, as a result of this review, no amendments to the Local Code of Corporate Governance were deemed necessary.
7. The 2025/26 Vehicle Management audit has been finalised and incorporated a follow up of the outstanding fleet management actions. A total of seven actions from the fleet management review have been superseded per new actions from the 2025/26 Vehicle Management review.
FINDINGS FROM COMPLETED AUDITS
8. Twelve audits have been completed since the last report as highlighted in the table below.
Recommendations Audit Plan Assurance Audit New New Outstanding Type Opinion New Essential Previous Essential Important Necessary or Important Capital Expenditure & Opinion Strong - - 1 - Accounting
Banking Opinion Strong - - 2 -
Housing Advice & Opinion Strong - 1 2 - Register Recommendations Audit Plan Assurance Audit New New Outstanding Type Opinion New Essential Previous Essential Important Necessary or Important Corporate Governance Opinion Strong - 2 - - (24/25)
Solent Airport & Opinion Reasonable - - 2 - Daedalus
Developers Contributions and Opinion Reasonable - - 4 - Community Infrastructure Levy
Opportunities Plan Opinion Reasonable - 1 1 -
Parks and Open Opinion Limited - 4 4 1 Spaces
Property Responsive repairs - Council Opinion Limited 1 1 2 - Housing
Vehicle Management Opinion Minimal 3 12 2 13
Key Finance System Wider N/A - 1 1 - Data Analytics
Follow Up Reviews Wider N/A - - - 23
9. The following summarises the key findings from the completed audits:
Capital Expenditure & Accounting: As a high-risk area, the Councils Capital Expenditure and Accounting programme requires regular coverage (last review completed in 2022/23) FBC reported £13.37m of General Fund capital expenditure in 2024/25, against a revised programme of £15.51m, resulting in an underspend of £2.14m. For 2025/26 the council had approved a capital programme of £37m. The one necessary recommendation highlighted that project appraisal criteria should be updated to reflect the Authority’s current position.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Local Code of Corporate GovernanceAppendix Four | 442 KB | Download |
PDF |
Chief Internal Auditor's Quarterly ReportReport | 218 KB | DownloadRead as text |
Follow Audit and Governance Committee at Fareham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 8 Sep 2026 | Business ContinuityRESOLVED that the Audit and Governance Committee note the contents of the report. | Noted | Open |
| 8 Sep 2026 | Corporate Complaint Handling - Performance and Learnings 2025/26RESOLVED that the Audit and Governance Committee: - (a) note the content of the Fareham Housing specific 2025/26 Comp... | Noted | Open |
| 8 Sep 2026 | Chief Internal Auditor's Quarterly ReportRESOLVED that the Audit and Governance Committee notes the progress and findings arising from Internal Audit work. | Decided | Open |
| 8 Sep 2026 | Committee ReportRESOLVED that the Audit and Governance Committee: - a) notes the contents of Part One of the report, including the Co... | Approved | Open |
| 27 Jul 2026 | External Audit - Annual Plan and Fee 2026/27RESOLVED that the Audit and Governance Committee: a) approves the 2025/26 Audit Plan, attached as Appendix A to this ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.