Q/0559/26 - Land Between 75 & 77 Church Road Warsash Southampton SO31 9GD

Agreed Planning 1 paper

AI summaryFareham Planning Committee delegates authority to vary a Section 106 agreement on land in Warsash so the developer can pay an off-site affordable housing contribution in instalments.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedHead of Planning to vary Section 106 for phased affordable housing payments
MoneyNo figure statedPapers refer to phased payments without giving amounts
What happens nextDeed of variation to be completedHead of Planning to finalise, with solicitor input
Who it affectsLand in Warsash, affordable housingSite between 75 and 77 Church Road, off-site contribution

What was decided

Members delegate to the Head of Planning, in consultation with the council's solicitor, to complete a deed of variation to the Section 106 agreement dated 10 November 2025, changing Schedule Two to allow an off-site affordable housing contribution paid in phases. Report 4.1

Members also delegate to the Head of Planning the power to make any necessary modification, deletion or addition to the deed of variation. Report P3, P4

Why

The application, registered as Q/0559/26, was before the committee and the officer recommendation was to delegate completion of the deed of variation to allow phased payments for the off-site affordable housing contribution. Report 4.1, P2

What happens next

The Head of Planning, with the Solicitor to the Council, will finalise the deed of variation to Schedule Two of the existing agreement and may make further changes to it as needed. Report 4.1, P3, P4

Options considered

  • Chosen: Officer recommendation: delegate to vary the Section 106 for phased off-site affordable housing payments. Recommended in the officer report Report 4.1

Implications

  • Legal: A deed of variation will amend Schedule Two of the Section 106 legal agreement dated 10 November 2025, with further modifications, deletions or additions allowed at the Head of Planning's discretion. Report 4.1, P3, P4
  • Financial: The affordable housing contribution will be made as phased payments off-site rather than on-site provision, though no sums or payment dates are given in the papers. Report 4.1, P2

Who and where

  • The site between 75 and 77 Church Road, Warsash, and the delivery of affordable housing linked to it Report 4.1, P2

Timeline

  • 10 November 2025: Date of the existing Section 106 legal agreement that is being varied Report 4.1
  • 2026-09-09: Planning Committee meeting at which the delegation was agreed

Plain English for the jargon

  • Section 106 agreement: A legal agreement between a developer and a local planning authority used to secure planning obligations
  • Deed of variation: A legal document that changes the terms of an existing agreement
  • Off-site affordable housing contribution: A payment made by a developer towards affordable housing provided elsewhere, instead of on the development site
  • Phased payments: The contribution is paid in instalments over time rather than as a single sum
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6(1)

Resolved

RESOLVED that Members delegate authority to the Head of Planning, in consultation with the Solicitor to the Council, to complete a deed of variation in relation to the existing Section 106 legal agreement dated 10 November 2025 to vary the terms of Schedule Two to allow for an off-site affordable housing contribution in the form of phased payments as set out in the Officers report, and further delegate to the Head of Planning authority to make any necessary modification, deletion or addition to the deed of variation.
Word for word from the decision Fareham published for this meeting. Source: moderngov.fareham.gov.uk

Follow this further

Built from Fareham's papers

What the report saysPro

Report to Planning Committee

OFFICER REPORT FOR COMMITTEE DATE: 09/09/2026

Q/0559/26 HOOK WITH WARSASH WARD APPLICANT: IMPERIAL HOMES AGENT: IMPERIAL HOMES

DEED OF VARIATION TO SECTION 106 OF THE TOWN AND COUNTRY PLANNING ACT 1990 RELATING TO PLANNING APPLICATION P/22/0450/FP

75 CHURCH ROAD, WARSASH

Report By Kim Hayler – direct dial 01329 824688

1.0Introduction

1.1Planning permission was granted for this site on 17 November 2025 for the following proposal:

‘Proposed development of 14 dwellings, including 9 detached market value dwellings and 5 affordable dwellings made up of 2 x 3 bed affordable rent, 1 x 4 bed affordable rent, 1 x 2/3 bed shared ownership and 1 x 1 bed adapted wheelchair accessible social rent, together with access road, parking and wildlife area.’

1.2Planning permission was granted subject to a Section 106 of the Town and Country Planning Act 1990 which, amongst other things, secures the provision of not less than 36% affordable housing (5 units) comprising:

• Three x 3 bedroom 6 person units; • One x 2 bedroom 4 person units; • One x 1 bedroom 2 person wheelchair accessible unit.

1.3This report relates to a proposed variation to the Section 106 Agreement which has been submitted to the Council by the housebuilder carrying out the development Imperial Homes.

2.0Description of proposal

2.1The developer has applied to the Council seeking a variation of the legal agreement. The developer has not been able to secure a Registered Provider capable of acquiring the affordable units. In their submissions they state that they had clear intentions to comply with the affordable housing obligations set out within the Section 106 Agreement, however this has become unviable in delivery terms due to the absence of a Registered Provider. The Section 106 was agreed on the assumption that a Registered Provider would be capable of acquiring the units.

2.2The developer has submitted evidence to demonstrate that they have undertaken proactive engagement with a number of Registered Providers in the affordable housing sector in this region of the country. All of the parties contacted by the developer have declined interest in acquiring the units. The developer has explained that this is likely because Registered Providers are increasingly not acquiring small sites and instead are typically requiring minimum thresholds of 30 plus units. This is a result of reduced grant funding availability from central government, increased build cost pressures, efficiency requirements within Registered Providers and a focus of large-scale delivery. As a result, small sites such as this are unattractive to Registered Providers.

2.3The developer also listed the units on the Government’s Social Housing Screening Platform, a platform created by Homes England to try and address this problem which has become prevalent across parts of the country. Regrettably, no Registered Providers have expressed interest, and no bids have been received.

2.4The only interest shown was from two Registered Providers solely on a shared equity basis, and not for social rent acquisition. This form of provision would not meet the Council’s identified housing need in Fareham. The Council’s Housing Development Officer has advised that, between the two options, they would prefer an off-site commuted sum to help deliver the affordable homes needed in the Borough.

3.0Planning considerations

3.1Officers consider the request to be acceptable in the circumstances given the nature of the development and the acknowledged challenges the developer is facing. Continuing to require compliance in its current form would delay or stall delivery, undermine the scheme’s viability and risk non-delivery of both much needed market and affordable housing.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q/0559/26: Land Between 75 & 77 Church Road Warsash Southampton SO31 9GDReport 1.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 13 attended
SD
Councillor Steve DuganChairman, apologies, sent representative
IB
Councillor Ian BastableChairman, present
MJ
Councillor Miss Joanne BurtonCommittee Member, present
GF
Councillor Gemma FurnivallCommittee Member, present
SI
Councillor Stephen IngramCommittee Member, apologies
MK
Councillor Mrs Kay MandryCommittee Member, apologies
MJ
Councillor Mrs Jacquie NeedhamCommittee Member, apologies, sent representative
PN
Councillor Paul NotherCommittee Member, present
KW
Councillor Kirsten WiltshireCommittee Member, present
RH
Councillor Ruth HallReserve, present as substitute
MC
Councillor Mrs Connie HockleyReserve, present as substitute
AF
Anna FloyerCommittee Officer, expected

All 13 on the meeting page

On this subject at Fareham

Search all
  1. Q/0559/26 - Land Between 75 & 77 Church Road Warsash Southampton SO31 9GDThis decision
  2. P/22/0450/fp - land between 75 & 77 church road warsashAgreed
  3. P/22/0450/fp - land between 75 and 77 church road, warsash, farehamDeferred
  4. P/23/1008/fp - land between and to the rear of 100 & 102 kiln roadRefused
  5. P/22/1629/rm - land between and to the rear of 56-66 greenaway laneApproved
  6. P/18/0756/oa - land between and to the rear of 56-66 greenaway lane warsashRefused

More from Fareham Planning Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 12 August 2026 be confirmed and signed as a c... Decided Open
9 Sep 2026 P/26/0722/FP - Single Storey Side Extension at 44 Crispin Close Locks Heath SO31 6TDRESOLVED that: - (i) IT BE CONFIRMED that had the planning application for a side extension at 44 Crispin Close (as p... Decided Open
9 Sep 2026 P/26/0791/AD - Barchester Care Home Stubbington Lane Stubbington PO14 2NFRESOLVED that: - (i) Advertisement Consent for Five Years be GRANTED , subject to:- (a) the Conditions in the report;... Decided Open
12 Aug 2026 Minutes of Previous MeetingRESOLVED that the minutes of the Planning Committee meeting held on the 15 July 2026 be confirmed and signed as a cor... Decided Open
12 Aug 2026 P/26/0249/FP - Chestnut Paddocks, 221 Titchfield Road, Fareham PO14 3EWRESOLVED that the application be REFUSED. Reason for refusal: The development will significantly affect the integrity... Refused Open