Air Quality Review and Assessment Statutory Reporting

Agreed Executive 1 paper

AI summaryFenland Cabinet noted the 2025 air quality review, which found the district continues to meet national objectives, alongside plans to expand monitoring and review two remaining management areas.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedReport and proposed actions noted
Money£2.856m projected shortfall 2026/27Rising to £2.903 in 2027/28; monitoring budgeted or grant funded
What happens nextReview 2 remaining AQMAs in 2026New Whittlesey monitor and Saxon Pit mobile station in summer 2026
Who it affectsAll Fenland wardsEspecially Whittlesey and Wisbech residents near former AQMAs

What was decided

Cabinet noted the report, monitoring locations, plans and proposed actions to meet statutory duties under the Environment Act 1995 and to further improve air quality. Report P6

Members accepted that the 2025 review found no air quality concerns in Fenland, with the district continuing to meet national objectives, including notable improvements in March. Report P5, P12

Members noted that eight new sensors or monitors have been added since 2024, expanding the district-wide data network through partner and external funding. Report P12

Why

The council has a statutory duty under Section 82 of the Environment Act 1995 to regularly review and assess air quality and report to Defra annually. Report P5

Defra has directed the council to review the remaining two air quality management areas, as national objectives are being met within them, and to develop a wider air quality strategy if revocation proceeds. Report P5, P12

A 2025 joint public health risk assessment by UK Health Security Agency and Public Health on the Saxon Pit site in Whittlesey recommended further monitoring of relevance to local air quality management. Report P5, P12

What happens next

Review the remaining two air quality management areas: AQMA 3 Wisbech (NO2 from transport) and AQMA 4 Whittlesey (SO2 from brick works), with revocation possible where pollution sources have been removed. Report P5, P12

Install an additional monitor at Peterborough Road/Saxon Pit in Whittlesey in 2026, funded by the county council, and host an environment agency mobile monitoring station on the site in summer 2026. Report P12

Develop a district-wide air quality monitoring plan in partnership with the environment agency, including particulate and sulphur dioxide monitoring, and continue to gather data from the MVV Medworth, Forterra, Johnsons and East Midland Waste sites. Report P12, 1.21

The money

  • £2.856m Projected General Fund financial shortfall for 2026/27 per the MTFS Report 5.5
  • £2.903 Projected shortfall rising in 2027/28 per the MTFS Report 5.5

Options considered

  • Chosen: Carry out the annual statutory air quality review and assessment and report to Defra. Statutory obligation under the Environment Act 1995; no feasible alternative exists Report P5, P20, P21

Implications

  • Legal: The council has a statutory duty under Section 82 of the Environment Act 1995 to review, assess and, where appropriate, monitor air quality, and to report annually to Defra. Report P5, P21
  • Equalities: Air pollution particularly affects children, older people and those with heart and lung conditions, so monitoring is focused on areas of increased pollution risk across the district. Report 5.9
  • Financial: All monitoring, including staffing costs, is either budgeted for or funded by external grants, set against a projected £2.856m shortfall in 2026/27. Report 5.5
  • Other: Future legislation may require screening, reviewing and monitoring of PM2.5 particulates. Report 5.12

Who and where

  • All Fenland residents, particularly those with asthma and other lung conditions Report P5, 5.9
  • Residents living near the Saxon Pit site in Whittlesey, who have raised concerns about air quality Report P12
  • Residents and road users in Weasenham Lane, Wisbech, identified as a slight area of decline Report P12
  • Operators of industrial sites including Forterra brick works, Johnsons, East Midland Waste and MVV Medworth, who must comply with environmental permits Report P12, 1.21, 1.22

Timeline

  • March 2025: Cabinet agreed to revoke two air quality management areas in Wisbech related to a coal fired boiler removed in 2009 Report P5, P12
  • During 2025: Air quality monitoring network expanded with additional diffusion tubes and partner sensors Report P12
  • September 2025: Sensor installed at Thomas Clarkson Academy under MVV Medworth consent order Report P12
  • 5th February: Public consultation event held in Whittlesey on Saxon Pit monitoring options Report P12
  • 23 March 2026: Cabinet noted the 2025 annual air quality review and assessment Report P3, P6
  • Summer 2026: Environment agency mobile monitoring station to be deployed on the Saxon Pit site Report P12
  • 2026: New Whittlesey monitor installation planned, funded by the county council Report P12

Plain English for the jargon

  • AQMA: Air Quality Management Area: a location declared by a council where national air quality objectives are not being met
  • Defra: Department for Environment, Food and Rural Affairs, the UK government department to which air quality reports are submitted
  • NO2: Nitrogen Dioxide, a pollutant mainly from vehicle emissions
  • PM10 and PM2.5: Particulate matter of less than 10 micrometres or 2.5 micrometres in diameter, monitored for health impacts
  • SO2: Sulphur Dioxide, a pollutant historically linked to industrial combustion such as brick works
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB64/25

Resolved

AGREED to note the report, monitoring locations, plans and proposed actions to ensure the Council’s statutory obligations under the Environment Act 1995 continue to be met and actions are implemented to further improve air quality.
Word for word from the decision Fenland published for this meeting. Source: moderngov.fenland.gov.uk

Follow this further

Built from Fenland's papers

What the report saysPro

Report to Cabinet

Agenda Item 6 No:

Committee: Cabinet

Date: 23 March 2026 Air Quality Review and Assessment Statutory Reporting Report Title:

1 Purpose / Summary 1.1 To present the findings of the annual statutory 2025 review and assessment of air quality. 1.2 To update members on the development work undertaken in 2025 to increase monitoring sites and air quality data across Fenland. 1.3 To inform members of the key action plan priorities for 2026.

2 Key Issues 2.1 Section 82 of the Environment Act 1995 places a duty on every local authority to regularly review and assess air quality in their areas, and to determine whether nationally set air quality objectives are likely to be achieved. 2.2 Nationally set objectives apply to Nitrogen Dioxide (NO2), Sulphur Dioxide (SO2) and Particulates of certain sizes (PM10 and PM2.5 - particles of less than 10 micrometres or 2.5 micrometres in diameter). 2.3 Poor air quality has a direct impact on health, and particularly those residents with asthma and other lung conditions. 2.4 The Council routinely monitors air quality across the district in accordance with the national air quality strategy for England. Monitoring results are compared against the national objectives and reported annually to Defra. 2.5 Air quality reviews undertaken recently (the latest being 2025) have not identified any concerns when considering available air quality data for Fenland. 2.6 In areas where pollution exceeds air quality objective levels an air quality management area must be declared. For districts without an air quality management area the authority must write an air quality strategy detailing monitoring and actions to maintain good air quality. 2.7 Defra have requested Fenland Council continue to develop a wider air quality strategy and ensure any previous decisions to declare air quality management areas are reviewed and appropriate action is taken. The work referenced within this report fulfils that requirement. 2.8 The Fenland district area has been subject to a number of development consents and infrastructure improvements in recent years and these have all had an impact on the action plan for air quality. 2.9 In 2025 a joint public health risk assessment was undertaken by UK Health Security Agency and Public Health which specifically looked at health risks from the Saxon Pit site in Whittlesey. This assessment concludes with recommendations of relevance to local air quality management processes. 2.10 In March 2025 the Council agreed to revoke 2 air quality management areas (AQMA) declared in Wisbech because of the risk of sulphur dioxide and particulate matter levels from a coal fired boiler, which was removed in 2009. These were 2 of 4 air quality management areas historically declared in Fenland. 2.11 The Council must continue to review and potentially revoke the remaining 2 historic air quality management areas. This is a requirement within Defra’s feedback to the latest air quality review and assessment report. If these areas are considered appropriate for revocation, a district wide air quality strategy should be developed. 2.12 Air quality is an ever-changing situation and as road networks change and new industries emerge the monitoring of air quality continues to be incredibly important. 2.13 The development of a new air quality strategy is beneficial because it will reflect current conditions, and upcoming changes, and provide a clearer, more accurate basis for managing air quality.

3 Recommendations 3.1 For Cabinet to note the report, monitoring locations, plans and proposed actions to ensure the Council’s statutory obligations under the Environment Act 1995 continue to be met and actions are implemented to further improve air quality.

Wards Affected All

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Air Quality Review and Assessment Statutory ReportingReport 475 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 11 attended
CB
Councillor Chris BodenChairman, present
MJ
Councillor Mrs Jan FrenchVice-Chairman, present
GC
Councillor Gary ChristyCommittee Member, apologies
SC
Councillor Steve CountCommittee Member, present
MS
Councillor Miss Samantha HoyCommittee Member, present
SI
Councillor Sidney ImafidonCommittee Member, present
MD
Councillor Mrs Dee LawsCommittee Member, present
CS
Councillor Christopher SeatonCommittee Member, present
ST
Councillor Steve TierneyCommittee Member, present
SW
Councillor Susan WallworkCommittee Member, present
LA
Linda AlbonOfficer, in attendance

More from Fenland Cabinet

All decisions
MeetingDecisionOutcome
16 Nov 2026 Review of District Wide Public Space Protection Orders (Dog Control)AGREED to: · Note the public and agency feedback in paragraph 4 and Appendix 1. · Approve the proposed Public Space P... Agreed Open
16 Nov 2026 Investment Board Update and Review of the Commercial and Investment StrategyAGREED: · To note the Investment Board report · That the ongoing review of the current Commercial and Investment Stra... Agreed Open
16 Nov 2026 Impact of LGR UncertaintyAGREED to: · Note the challenges that LGR is causing the Council; · Give some focus to the budget setting process for... Agreed Open
19 Oct 2026 Manor Leisure Centre UpdateAGREED to: · Note the progress made since February 2026; · Note that costs and delivery programme will be revised for... Agreed Open
19 Oct 2026 National Planning Scheme of DelegationAGREED to recommend to Council to: · Note the forthcoming implementation of a National Scheme of Delegation for plann... Agreed Open