CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Forest of Dean District Council
Cabinet, Thursday 15 January 2009 at 5.30pm

Newent Regeneration

Approved Executive 1 paper

Cabinet approved this item on Thursday 15 January 2009. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

RESOLVED – to approve a further allocation in the 2010/11 capital programme of £30,000 to cover possible cost over-runs on the Newent Town Centre Enhancement Scheme as at report EDP.8
Word for word from the decision Forest of Dean published for this meeting. Source: meetings.fdean.gov.uk

Follow this further

Built from Forest of Dean's papers

What the report saysPro

Report to Cabinet

Cabinet 15 January 2009 EDP.8

Subject CONTINGENCY FUNDING FOR NEWENT ENHANCEMENT SCHEME Accountable Councillor Patrick Molyneux, Cabinet Member for Economic member Regeneration Tel: 01594 812647, email: [email protected]

Accountable officer Steve Kendall, Group Manager Economic Development & Property Tel: 01594 812332, email: [email protected] Author Jessie Wainwright, Market Towns Officer Tel 01594 812334, email [email protected] Summary £30k additional capital allocation is required as additional contingency to fulfil SWRDA requirements that in the unlikely event of cost overruns to the Newent Enhancement Scheme, these additional costs can be met by Forest of Dean District Council and Gloucestershire County Council.

Recommendation Cabinet is asked to approve: A further allocation in the 2010/11 Capital Programme of £30,000 to cover possible cost over-runs on the Newent Town Centre Enhancement Scheme.

Corporate priorities Promote safe & thriving communities & resources Encourage a thriving economy Protect & improve our environment 1. BACKGROUND 1.1. A capital allocation toward the Newent Town Centre Enhancement Scheme was agreed at Executive Committee on 29th June 2006. 1.2. A further report was brought to Cabinet in September 2008 outlining the detail of the scheme, and seeking adoption by the Council to enable it to be referred to by Planners when considering future planning applications on sites adjacent to or affected by the Scheme. This was agreed at Cabinet on 14th August 2008. 1.3. The Scheme consists of a programme of works costing £871,364 to improve and enlarge the historic market square of Newent in order to increase accessibility, improve safety, and provide a space for markets and events. One of the key aims of the Scheme is to increase economic activity whilst emphasising the historic significance of the town. 1.4. The funding package contains £213,130 from Forest of Dean District Council, £207,550 from Gloucestershire County Council and £15,000 from Newent Town Council. South West Regional Development Agency has agreed in principle to provide £435,680 as 50% match funding from SWRDA. 1.5. The project is programmed to commence during 2009/10 financial year, and be completed during the first part of 2010/11. 1.6. SWRDA Has indicated that its level of grant is fixed, and whilst the scheme has already been costed with a 10% contingency sum, they require the County Council and FODDC to confirm that they will provide for any cost over-run on the project. 1.7. Given the current economic climate, it is not expected that cost over-runs will be incurred, but it is considered prudent for the Council to allocate a contingency for this in the sum of £30,000 in the |Council’s Capital programme for 20010/11 financial year. The County Council has already allocated such a sum.

2. FINANCIAL IMPLICATIONS 2.1. It is normal to include a contingency sum of 10% in major capital projects, and this has been done in this case. However, SWRDA insists that it will not be liable for any cost overruns beyond this 10% and that any extra costs must be met by County and District Council. County’s Highways engineers are satisfied that a 10% contingency will cover any cost overruns but have recommended an additional £60,000 (to be split between District and County) be made available on top of this contingency to be able to meet SWRDA’s required statement that any cost overruns be met by District and County. 2.2. This additional sum of £30,000 has not been approved by Council, and can be added to the Capital Programme for 2010/11. If this is not drawn down, the sum will be returned to the Council’s Capital reserve.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Newent RegenerationReport 92 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 19 attended
PA
Councillor Peter AmosCommittee Member, present
DE
Councillor Diana EdwardsCommittee Member, present
PM
Councillor Patrick MolyneuxCommittee Member, apologies
MQ
Councillor Martin QuaileVice Chair, present
BR
Councillor Brian RobinsonCommittee Member, present
MW
Councillor Marion WinshipChairman, present
DB
Derek BroomOfficer, in attendance
PH
Peter HibberdOfficer, in attendance
SP
Sue PangbourneOfficer, in attendance
TP
Tim PerrinOfficer, in attendance
PW
Peter Williams MRTPIOfficer, in attendance
PB
Councillor Philip BurfordEx-Officio-Other-Member, in attendance

All 19 on the meeting page

More from Forest of Dean Cabinet

All decisions
MeetingDecisionOutcome
10 Sep 2026 Introduction of James watch to Forest Linkline & Cotswold Careline product rangeResolved , that Cabinet: 1. Approves the introduction of the James Watch service within Forest Linkline and Cotswold ... Approved Open
10 Sep 2026 Health and Safety PoliciesResolved , that Cabinet; 1. Approves the implementation of the attached Health and Safety Delegated Responsibility Fr... Approved Open
10 Sep 2026 Quarter Performance Report - Period OneResolved, that Cabinet: 1. Notes overall progress on the Council priorities and service performance for 2026-27 Q1. A... Agreed Open
10 Sep 2026 Financial Performance Report - Period OneResolved, that Cabinet; 1. Notes the 2026-27 Quarter One Financial Performance report and, 2. That the Business Rates... Agreed Open
9 Jul 2026 Conservation Areas SWOT Analysis: Explorer Hubs and Summary SheetsResolved, that Cabinet: Noted the value of the analysis undertaken and support its appropriate use and application in... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies