- That any action be deferred until 31 st July 2014 to allow the Yorkley Court Community Farm Land Trust to submit a planning application. If a planning application has not been submitted by 31 st July, delegated authority be given to the Group Manager, Planning and Housing, to undertake enforcement action. Voting was as follows For (12) Terry Glastonbury, Arthur Thomas, Norman Stephens, Julia Gooch, Gabriella Kirkpatrick, Judy Davis, Roger Yeates, Lynn Sterry, Graham Morgan, Jackie Fraser, James Bevan, Gethyn Davies. Against (1) Roger Sterry Abstain (0) Total (13)
Word for word from the decision Forest of Dean published for this meeting.Source: meetings.fdean.gov.uk
Subject Unauthorised change of use of land at Yorkley Court, Yorkley Lane, Yorkley, Gloucestershire. (Reference EN/0240/12) Wards affected West Dean Accountable officer Peter Williams, Group Manager Planning and Housing. Tel: 01594 812300 e-mail: [email protected] Summary This report considers the expediency of issuing an Enforcement Notice in respect of an on-going breach of planning control consisting of the unauthorised change of use of land from agricultural to the use of land for the stationing and use of temporary structures, mobile homes, vehicles and the use of existing buildings for residential use on land at Yorkley Court, Yorkley Lane, Yorkley, Lydney, Gloucestershire. Recommendation It is recommended that the Group Manager for Planning, Housing and Regeneration and the Legal Team Manager be authorised to issue an Enforcement Notice under Section 172 of the Town and Country Planning Act 1990 (as amended) and be authorised to withdraw and to vary such notices and in the event of non-compliance, to take action by way of prosecution under Section 179 of the Act in respect of the breach of planning control/or for injunctive relief under Section 187B Corporate priorities Priority 4: Protect and improve our environment.
LEGAL FINANCIAL RISK EQUALITIES SUSTAINABILITY Implications Yes No No Yes No Enforcement report Land at Yorkley Court Farm, Yorkley Lane, Yorkley.
Update – Officer Comment – May 2014
Members will recall that this item was presented to the Planning Committee in October 2013, with a recommendation that enforcement action be taken. Members resolved to delay the decision to take formal enforcement action for a period of six months. The reason for the delay was to allow a planning application to be submitted to the Council by the Yorkley Court Community Farm Land Trust in an attempt to obtain permission for the development being undertaken.
To date no application has been submitted to the Council. The land is still occupied and used for residential purposes and there are structures and vehicles on the land being used in connection with these residential uses. The Council were contacted in early March 2014 by representatives from the Yorkley Court Community Farm Land Trust to arrange pre application meetings. Whilst an appointment to meet Planning Officers on 7th May 2014 to hold pre- application discussions has been made, this still does not represent the submission of a valid planning application as requested by Committee.
The recommendation remains one to pursue formal enforcement action in response to the continuing use of the land to station temporary structures, mobile homes, vehicles and existing buildings for residential uses.
Update - Officer Comment (October 2013) A Site Inspection Panel took place on Tuesday 17th September 2013. It has to be noted that the site had received significant attention for that visit and only one caravan and three huts were visible on the area of the site visited. The appearance of the site on that date differed from that of previous visits with two caravans removed and other huts cleared from the site. The photographs attached to the Committee Report depict the appearance of the site previously. Members’ attention is drawn to the original report which sets out the nature of the breaches of planning control. In the absence of any application for planning permission, formal enforcement action remains the only method of effectively managing the situation. Late Material presented to the September Meeting It is understood a representation in support of the residents of the site has been circulated directly to Members. The main points of that representation are summarised as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.